HP Performance Optimized Data Center (POD) 240a manual Racks, Future expansions

Page 9

Side view clearances shown

End view clearances shown

For additional dimensions, see the HP Site Preparation Drawing Package (on page 22).

Future expansions

When selecting a site location, consider future space and accessibility requirements. Adequate space around the HP POD 240e NA is necessary for airflow and cooling purposes. Keep the specified areas clear.

For specific space requirements, see the HP POD 240e NA dimensions and required clearances.

Racks

The standard HP installed rack is a 50U rack. The HP POD 240e NA has 22 IT racks per IT section, for a total of 44 IT racks.

During maintenance, if you remove filler panels for maintenance purposes, you must replace them. Cold-aisle to hot-aisle separation must be maintained.

Site requirements 9

Image 9
Contents Abstract Page Contents Contacting HP Safety and NEC compliance OverviewAbout this document Site assessment Site safety and security Site preparation Fire detectionDimensions and required clearances Weight requirementsSite requirements Site padSite requirements Future expansions RacksGrounding requirements Cold aisle clearanceGrounding electrode System utilities UtilitiesDrain locations PowerSite electrical system Transformers and switchboards Environmental control system Supported facility connectionsConnections to central facility infrastructure Connection portalsECS EPO Fire box Demarcation boxFire, safety, and access notifications Access controlSupported facility connections Environmental considerations Areas prone to lightning or power surgesEnvironmental risks Cold weatherCompleting a site assessment Site plan requirements and actionsHP Site Preparation Drawing Package Zoning and permit requirementsSite planning InstallationLifting requirements Storage requirements Appendix a HP site assessment HP POD 240e NA site assessment checklistDescription Yes Initial Description Initial Installation prerequisites HP POD 240e NA site readiness checklistAppendix B Preparing for delivery Pre-delivery tasksWater supply Adiabatic media water supply Description Sign-off Contacting HP Before you contact HPHP contact information Safety and NEC compliance Regulatory compliance noticesHP POD 240e NA regulatory compliance Warranty information Safety and regulatory complianceEPO GlossaryPPE UPS Documentation feedback Index Index
Related manuals
Manual 8 pages 155 b Manual 26 pages 60.09 Kb Manual 93 pages 30.86 Kb