Item | Description | |||
|
|
|
| |
1 | Verify that the HP POD 240e NA is not in a drainage path or |
| ||
| flood prone area to prevent water from entering the HP POD |
| ||
| 240e NA. HP recommends setting the HP POD 240e NA on a |
| ||
| raised site pad. |
| ||
2 | Verify that the water quality meets drinking water standards. |
| ||
Adiabatic media water supply |
| |||
|
|
|
| |
Item |
| Description |
| |
|
|
|
| |
1 |
| Verify that the water pressure is between |
| |
|
| kPa) and that water temperature is between 1°C to 30°C |
| |
|
| (34°F to 86°F). |
| |
2 |
| Verify that the water instant |
| |
|
|
| flow of the fill solenoid valve (1.5 gpm maximum flow per |
|
|
|
| adiabatic unit, maximum instantaneous.) |
|
3 |
| Verify that water hardness is no greater than 40degFH or |
| |
|
| equal to 400 ppm of CaCO3. |
| |
4 |
| Verify that demineralized water (preferred) or drinking |
| |
|
| (potable) water is used. |
| |
Power requirements |
| |||
|
|
| ||
Item | Description |
| ||
|
|
| ||
1 | Verify that the following requirements are complete: |
| ||
| • | Short circuit analysis |
| |
| • | Arc flash study |
| |
| • Circuit breaker coordination studies |
| ||
|
|
| ||
2 | Verify that the power installation work is completed according |
| ||
| to the approved conduit routing drawings that show the exact |
| ||
| routes, plan view, sections, and elevations. |
| ||
3 | Verify that temporary site power for installation and |
| ||
| construction is planned and available. |
| ||
4 | Verify adequate site power (on page 13) per HP POD 240e |
| ||
| NA requirements. |
| ||
General |
|
| ||
|
|
| ||
Item | Description |
| ||
|
|
| ||
1 | Verify the utility connection including the main utility |
| ||
| transformers and metering equipment. |
| ||
2 | Verify the |
| ||
| required by the owner. |
| ||
3 | Verify that the HP Project Team activities are coordinated with |
| ||
| other site construction activities. |
|
Appendix B: Preparing for delivery 30