HP POD 240e NA site assessment checklist

During a survey of the readiness of a proposed customer site for the HP POD 240e NA, the site is inspected for the following:

Accessibility of machinery for the transportation and installation of the HP POD 240e NA

Assessment of the suitability of the site infrastructure for installing the HP POD 240e NA and for supporting infrastructure preparation and serviceability requirements

HP responsibilities

Item

Description

 

Yes

No

N/A

Initial

 

 

 

 

 

 

 

 

 

1. Engagement plan

Develop an engagement plan with specific requirements

 

 

 

 

 

 

 

 

relating to the proposed installation site.

 

 

 

 

 

 

2.

Site visits

Schedule site visits on mutually acceptable dates, during

 

 

 

 

 

 

 

 

normal HP business hours.

 

 

 

 

 

 

3.

Test equipment

Document any test equipment that is required for installation

 

 

 

 

 

 

 

or commissioning.

 

 

 

 

 

 

4.

Installation site

Review and discuss the proposed installation site:

 

 

 

 

 

 

review

Physical examination of the proposed installation site.

 

 

 

 

 

 

 

 

At HP's discretion, include physical measurements of the

 

 

 

 

 

 

 

 

area.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

5.

Indoor/outdoor

Determine if the HP POD 240e NA installation is indoors or

 

 

 

 

 

installation

outdoors.

 

 

 

 

 

 

6.

Site pad

Inspect the proposed installation site to be sure that the

 

 

 

 

 

 

 

 

customer is aware of the following requirements:

 

 

 

 

 

 

 

 

POD load pads are in the proper location.

 

 

 

 

 

 

 

 

Upon installation, the POD structure must be leveled to

 

 

 

 

 

 

 

 

0.5º, which can be checked at that time with a surveyor’s

 

 

 

 

 

 

 

 

transit.

 

 

 

 

 

 

 

 

Shimming is allowed at the load pads only.

 

 

 

 

 

 

 

 

Place shims in increments across the load pads to be sure

 

 

 

 

 

 

 

 

that there is sufficient load transfer.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

7.

Construction site

Visually inspect the construction site and identify the location

 

 

 

 

 

inspection

to install the crane.

 

 

 

 

 

 

8.

Staging

Be sure the following areas exist and are identified:

 

 

 

 

 

 

 

 

Truck delivery

 

 

 

 

 

 

 

 

Staging

 

 

 

 

 

 

 

 

Waste removal

 

 

 

 

 

 

 

 

 

 

 

 

 

 

9.

Clearances

Inspect the proposed installation site to confirm the clearance

 

 

 

 

 

 

 

requirements are met for installing and servicing the POD

 

 

 

 

 

 

 

 

based on the HP POD 240e NA specifications. Consider

 

 

 

 

 

 

 

 

future planning for the space around the installation site.

 

 

 

 

 

 

10. Support

Evaluate the HP POD 240e NA installation site in relation to

 

 

 

 

 

infrastructure

the existing and planned support infrastructure location.

 

 

 

 

 

 

location

 

 

 

 

 

 

 

 

 

 

 

 

Appendix A: HP site assessment 25

Image 25
Contents Abstract Page Contents Contacting HP Overview Safety and NEC complianceAbout this document Site assessment Site safety and securitySite preparation Fire detectionDimensions and required clearances Weight requirementsSite requirements Site padSite requirements Future expansions RacksGrounding requirements Cold aisle clearanceGrounding electrode System utilities UtilitiesDrain locations PowerSite electrical system Transformers and switchboards Environmental control system Supported facility connectionsConnections to central facility infrastructure Connection portalsECS EPO Fire box Demarcation boxFire, safety, and access notifications Access controlSupported facility connections Environmental considerations Areas prone to lightning or power surgesEnvironmental risks Cold weatherCompleting a site assessment Site plan requirements and actionsHP Site Preparation Drawing Package Zoning and permit requirementsSite planning InstallationLifting requirements Storage requirements Appendix a HP site assessment HP POD 240e NA site assessment checklistDescription Yes Initial Description Initial Installation prerequisites HP POD 240e NA site readiness checklistAppendix B Preparing for delivery Pre-delivery tasksWater supply Adiabatic media water supply Description Sign-off Before you contact HP Contacting HPHP contact information Regulatory compliance notices Safety and NEC complianceHP POD 240e NA regulatory compliance Warranty information Safety and regulatory complianceEPO GlossaryPPE UPS Documentation feedback Index Index
Related manuals
Manual 8 pages 155 b Manual 26 pages 60.09 Kb Manual 93 pages 30.86 Kb