HP Performance Optimized Data Center (POD) 240a manual Site plan requirements and actions

Page 22

Site plan requirements and actions

Completing a site assessment

HP requires a detailed assessment before planning and preparing your site location for the HP POD 240e NA. Consult with HP to schedule a site assessment.

A standard site assessment visit includes the following tasks:

Selecting an appropriate site for the HP POD 240e NA

Assessing the proposed site for: o Measurements for clearances

o Infrastructure for the final solution o Access to utilities

o Site pad

o Installation considerations, including locations for delivery trucks, large installation equipment (such as cranes), and storage

o Electrical infrastructure

o Facility network and access control systems

Developing an engagement plan and verifying your contacts

Discussing future development and growth plans

For a complete site assessment checklist, see "Appendix A: HP site assessment (on page 25)."

HP Site Preparation Drawing Package

After receiving a signed purchase agreement, HP provides detailed engineering drawings. These drawings contain information to assist you and your MEP team to prepare the site for POD installation. If there are areas of special interest, HP can work directly with your MEP team to provide additional assistance.

Zoning and permit requirements

You are responsible for compliance of the overall installation in accordance with all local and national regulations, ordinances, codes, and the product specifications.

Project coordination

Your Project Manager must perform the following tasks:

Coordinate with all trades before installation to be sure that trade conflicts are resolved.

Coordinate the installation and integration of all systems.

Be sure that the site safety and security programs are properly administered.

Site plan requirements and actions 22

Image 22
Contents Abstract Page Contents Contacting HP Overview Safety and NEC complianceAbout this document Site preparation Site safety and securitySite assessment Fire detectionSite requirements Weight requirementsDimensions and required clearances Site padSite requirements Racks Future expansionsCold aisle clearance Grounding requirementsGrounding electrode Utilities System utilitiesPower Drain locationsSite electrical system Transformers and switchboards Connections to central facility infrastructure Supported facility connectionsEnvironmental control system Connection portalsECS EPO Demarcation box Fire boxAccess control Fire, safety, and access notificationsSupported facility connections Environmental risks Areas prone to lightning or power surgesEnvironmental considerations Cold weatherHP Site Preparation Drawing Package Site plan requirements and actionsCompleting a site assessment Zoning and permit requirementsInstallation Site planningLifting requirements Storage requirements HP POD 240e NA site assessment checklist Appendix a HP site assessmentDescription Yes Initial Description Initial Appendix B Preparing for delivery HP POD 240e NA site readiness checklistInstallation prerequisites Pre-delivery tasksWater supply Adiabatic media water supply Description Sign-off Before you contact HP Contacting HPHP contact information Regulatory compliance notices Safety and NEC complianceHP POD 240e NA regulatory compliance Safety and regulatory compliance Warranty informationGlossary EPOPPE UPS Documentation feedback Index Index