Transformers and switchboards

The input power for the Critical IT Loads requires a source of 380-415V, 3phase wye power. If it does not already exist at the source, you might have to obtain custom transformers to derive this power. In addition to the overall loading and KVA size, you must consider the Harmonic Content of the installation when specifying the K-Factor of the transformers. Alternatively, you can use Harmonic Mitigating Transformers to passively cancel the harmonics generated by the IT equipment.

HP offers several power solutions that include automatic transfer switching, UPS backup, transformers and output distribution switchboards to supply your power needs.

On-site connections might include:

Main facility power to the primary side of the transformer

Transformer to the switchboard

Switchboard assembly to the HP POD 240e NA

For connection information, see the HP Site Preparation Drawing Package (on page 22).

Site requirements 15

Image 15
Contents Abstract Page Contents Contacting HP Safety and NEC compliance OverviewAbout this document Fire detection Site safety and securitySite assessment Site preparationSite pad Weight requirementsDimensions and required clearances Site requirementsSite requirements Future expansions RacksGrounding requirements Cold aisle clearanceGrounding electrode System utilities UtilitiesDrain locations PowerSite electrical system Transformers and switchboards Connection portals Supported facility connectionsEnvironmental control system Connections to central facility infrastructureECS EPO Fire box Demarcation boxFire, safety, and access notifications Access controlSupported facility connections Cold weather Areas prone to lightning or power surgesEnvironmental considerations Environmental risksZoning and permit requirements Site plan requirements and actionsCompleting a site assessment HP Site Preparation Drawing PackageSite planning InstallationLifting requirements Storage requirements Appendix a HP site assessment HP POD 240e NA site assessment checklistDescription Yes Initial Description Initial Pre-delivery tasks HP POD 240e NA site readiness checklistInstallation prerequisites Appendix B Preparing for deliveryWater supply Adiabatic media water supply Description Sign-off Contacting HP Before you contact HPHP contact information Safety and NEC compliance Regulatory compliance noticesHP POD 240e NA regulatory compliance Warranty information Safety and regulatory complianceEPO GlossaryPPE UPS Documentation feedback Index Index
Related manuals
Manual 8 pages 155 b Manual 26 pages 60.09 Kb Manual 93 pages 30.86 Kb