HP Performance Optimized Data Center (POD) 240a manual Site planning, Installation

Page 23

Interface directly with the HP installation project manager to be sure clear lines of communication exist during the installation and commissioning processes.

Site planning

A comprehensive site plan assists with the site design (MEP) and helps you to be sure that you use the best possible HP POD 240e NA installation process. When creating a site plan, consider the following information:

HP POD 240e NA site requirements detailed in this document ("Site requirements" on page 7)

HP POD 240e NA site preparation drawing package ("HP Site Preparation Drawing Package" on page 22)

HP POD 240e NA readiness checklist ("HP POD 240e NA site readiness checklist" on page 28)

HP POD 240e NA installation ("Installation equipment staging" on page 23)

The HP team can assist you by answering questions and by helping to guide you throughout the process.

Installation

HP POD 240e NA installation includes the following:

Installation equipment staging (on page 23)

Locations for the HP POD 240e NA and equipment (on page 23)

HP POD 240e NA lifting requirements ("Lifting requirements" on page 24)

HP POD 240e NA storage requirements ("Storage requirements" on page 24)

Other structures (on page 24)

Installation equipment staging

Staging for the following items must be identified and considered:

Truck and component staging

Installation equipment staging

Site traffic

Regulatory or local permits

Locations for the HP POD 240e NA and equipment

When preparing a site plan, identify where the HP POD 240e NA, and equipment used to assemble it, are going to be placed. Discuss and plan the following items as applicable to the installation:

HP POD 240e NA location and order of assembly

Generator and UPS units

POD-related switchgear

Housekeeping pads for required electrical equipment

Crane capacity, location, and reach

Site plan requirements and actions 23

Image 23
Contents Abstract Page Contents Contacting HP About this document Safety and NEC complianceOverview Fire detection Site safety and securitySite assessment Site preparationSite pad Weight requirementsDimensions and required clearances Site requirementsSite requirements Future expansions RacksGrounding requirements Cold aisle clearanceGrounding electrode System utilities UtilitiesDrain locations PowerSite electrical system Transformers and switchboards Connection portals Supported facility connectionsEnvironmental control system Connections to central facility infrastructureECS EPO Fire box Demarcation boxFire, safety, and access notifications Access controlSupported facility connections Cold weather Areas prone to lightning or power surgesEnvironmental considerations Environmental risksZoning and permit requirements Site plan requirements and actionsCompleting a site assessment HP Site Preparation Drawing PackageSite planning InstallationLifting requirements Storage requirements Appendix a HP site assessment HP POD 240e NA site assessment checklistDescription Yes Initial Description Initial Pre-delivery tasks HP POD 240e NA site readiness checklistInstallation prerequisites Appendix B Preparing for deliveryWater supply Adiabatic media water supply Description Sign-off HP contact information Contacting HPBefore you contact HP HP POD 240e NA regulatory compliance Safety and NEC complianceRegulatory compliance notices Warranty information Safety and regulatory complianceEPO GlossaryPPE UPS Documentation feedback Index Index