The following is a list of component requirements for grounding and bonding:

Grounding of the HP POD 240e NA must comply with the requirements of Article 250 of the NEC, NFPA 70-2011 (NA/JPN), and with local and regional regulations (IEC for EMEA and AP).

Bonding of the piping systems and any exposed structural steel, installed to support the HP POD 240e NA, must be in accordance with NEC (NA) and with local and regional regulations (IEC for EMEA and APJ).

Grounding feature

Specification

 

 

Grounding electrode

The grounding electrode conductor connection bus pad is located on the outside of

conductor pad

the HP POD 240e NA on the cold aisle adjacent to the power cabinet.

 

The grounding pad must be connected to the grounding electrode system or

 

building steel in accordance with Article 250 of the NEC or equivalent regional

 

regulations.

 

 

Grounding lugs

Grounding lugs cannot be attached to any painted surface.

 

Grounding lugs must be compression-type 2-hole lugs and UL listed specifically for

 

grounding.

 

 

Ground rod system or

You must provide an effective grounding system with a ground rod or a ground well.

ground well

 

IMPORTANT: Before installing the HP POD 240e NA, consult your local AHJ for applicable regulations and to review site-specific location guidelines. If needed, obtain any necessary permits.

The grounding electrode conductor connections are located on IT sections A and B of the HP POD 240e NA. The following figure shows the location for both of the IT sections.

Side view shown

Site requirements 11

Image 11
Contents Abstract Page Contents Contacting HP About this document Safety and NEC complianceOverview Fire detection Site safety and securitySite assessment Site preparationSite pad Weight requirementsDimensions and required clearances Site requirementsSite requirements Future expansions RacksGrounding requirements Cold aisle clearanceGrounding electrode System utilities UtilitiesDrain locations PowerSite electrical system Transformers and switchboards Connection portals Supported facility connectionsEnvironmental control system Connections to central facility infrastructureECS EPO Fire box Demarcation boxFire, safety, and access notifications Access controlSupported facility connections Cold weather Areas prone to lightning or power surgesEnvironmental considerations Environmental risksZoning and permit requirements Site plan requirements and actionsCompleting a site assessment HP Site Preparation Drawing PackageSite planning InstallationLifting requirements Storage requirements Appendix a HP site assessment HP POD 240e NA site assessment checklistDescription Yes Initial Description Initial Pre-delivery tasks HP POD 240e NA site readiness checklistInstallation prerequisites Appendix B Preparing for deliveryWater supply Adiabatic media water supply Description Sign-off HP contact information Contacting HPBefore you contact HP HP POD 240e NA regulatory compliance Safety and NEC complianceRegulatory compliance notices Warranty information Safety and regulatory complianceEPO GlossaryPPE UPS Documentation feedback Index Index
Related manuals
Manual 8 pages 155 b Manual 26 pages 60.09 Kb Manual 93 pages 30.86 Kb