HP Performance Optimized Data Center (POD) 240a manual Description Initial

Page 27

Item

Description

Initial

 

 

 

8. Network

Provide HP information regarding the planned network infrastructure

 

infrastructure

connection points and pathways.

 

information

 

 

9. Permission for

Grant HP permission to take photographs or supply photographs to HP for

 

photographs

report illustration purposes.

 

10. Project logistics

Arrange site-specific project logistics at the time of scheduling. Failure to

 

 

provide necessary authorizations can limit the effectiveness of the service and

 

 

can, at the discretion of HP, impact scheduling or result in the postponement of

 

 

the service.

 

11. Business visas

Provide assistance in instances where a temporary business visa is required for

 

 

HP personnel to visit the site. This assistance typically takes the form of

 

 

preparing a letter of invitation. In some cases, a formal request must be made

 

 

by the local company for which the work is taking place, if applicable.

 

Appendix A: HP site assessment 27

Image 27
Contents Abstract Page Contents Contacting HP Safety and NEC compliance OverviewAbout this document Fire detection Site safety and securitySite assessment Site preparationSite pad Weight requirementsDimensions and required clearances Site requirementsSite requirements Future expansions RacksGrounding requirements Cold aisle clearanceGrounding electrode System utilities UtilitiesDrain locations PowerSite electrical system Transformers and switchboards Connection portals Supported facility connectionsEnvironmental control system Connections to central facility infrastructureECS EPO Fire box Demarcation boxFire, safety, and access notifications Access controlSupported facility connections Cold weather Areas prone to lightning or power surgesEnvironmental considerations Environmental risksZoning and permit requirements Site plan requirements and actionsCompleting a site assessment HP Site Preparation Drawing PackageSite planning InstallationLifting requirements Storage requirements Appendix a HP site assessment HP POD 240e NA site assessment checklistDescription Yes Initial Description Initial Pre-delivery tasks HP POD 240e NA site readiness checklistInstallation prerequisites Appendix B Preparing for deliveryWater supply Adiabatic media water supply Description Sign-off Contacting HP Before you contact HPHP contact information Safety and NEC compliance Regulatory compliance noticesHP POD 240e NA regulatory compliance Warranty information Safety and regulatory complianceEPO GlossaryPPE UPS Documentation feedback Index Index