HP Performance Optimized Data Center (POD) 240a manual Water supply

Page 29

Item

Description

Sign-off

 

 

 

7

Verify the average local temperatures and be sure that

 

 

adequate environment protection is provided. For example,

 

 

verify that cold weather protection is provided, if necessary.

 

8

Verify that site altitude is less than 3.048 meters (10,000 feet).

 

9

When installing on an elevated surface:

 

 

Verify that the maximum height requirements for the circuit

 

 

breaker actuator meet the local and national electric code

 

 

requirements of 200 cm (79 inch) (NEC 240.24-a).

 

 

Verify that proper landings and catwalk are planned for

 

 

electrical cabinet access.

 

 

 

 

10

Verify that the planning for the required egress includes routes

 

 

for all HP POD 240e NA personnel doors, cargo doors, and

 

 

service area doors, including landings, catwalk, and stairs.

 

11

Verify that the local AHJ has been contacted, all applicable

 

 

codes and site-specific location guidelines have been

 

 

reviewed, and all required permits are obtained.

 

12

Verify that the site location has clearances ("Dimensions and

 

 

required clearances" on page 7) for HP POD 240e NA

 

 

installation, including any permanent structures, such as fences,

 

 

walls, vestibules, and buildings.

 

13

Verify that all utilities, overhead and underground, are

 

 

identified to maintain required clearance.

 

14

Verify that there is adequate clearance around the HP POD

 

 

240e NA for door operation, installation, and maintenance

 

 

equipment.

 

15

Verify that the site location and site pads are marked for

 

 

POD-related infrastructure.

 

16

Verify that a truck and equipment staging area has been

 

 

identified. Verify planning for trucks for the HP POD 240e NA

 

 

and other equipment.

 

17

Verify that locations are available and identified for all

 

 

equipment that is required.

 

18

Verify the locations for crane off-loading and operation during

 

 

HP POD 240e NA installation.

 

19

Verify that the location for the storage area and the disposal of

 

 

packaging materials and trash are identified.

 

20

Verify that safety equipment is planned for and in place.

 

21

Verify the customer's interfaces of the HP POD 240e NA fire

 

 

alarm, security system, and communications systems to site

 

 

system. The customer is responsible for all connections.

 

22

Verify that existing contaminated or hazardous materials and

 

 

work related to them are disposed of properly.

 

23

Verify that there is an available temporary or permanent load

 

 

bank, if required.

 

24

Verify that tie-downs and other AHJ-required facilities for HP

 

 

POD 240e NA and power containers are completed at least

 

 

one week prior to the arrival of HP-provided equipment.

 

Water supply

Appendix B: Preparing for delivery 29

Image 29
Contents Abstract Page Contents Contacting HP About this document Safety and NEC complianceOverview Site assessment Site safety and securitySite preparation Fire detectionDimensions and required clearances Weight requirementsSite requirements Site padSite requirements Future expansions RacksGrounding requirements Cold aisle clearanceGrounding electrode System utilities UtilitiesDrain locations PowerSite electrical system Transformers and switchboards Environmental control system Supported facility connectionsConnections to central facility infrastructure Connection portalsECS EPO Fire box Demarcation boxFire, safety, and access notifications Access controlSupported facility connections Environmental considerations Areas prone to lightning or power surgesEnvironmental risks Cold weatherCompleting a site assessment Site plan requirements and actionsHP Site Preparation Drawing Package Zoning and permit requirementsSite planning InstallationLifting requirements Storage requirements Appendix a HP site assessment HP POD 240e NA site assessment checklistDescription Yes Initial Description Initial Installation prerequisites HP POD 240e NA site readiness checklistAppendix B Preparing for delivery Pre-delivery tasksWater supply Adiabatic media water supply Description Sign-off HP contact information Contacting HPBefore you contact HP HP POD 240e NA regulatory compliance Safety and NEC complianceRegulatory compliance notices Warranty information Safety and regulatory complianceEPO GlossaryPPE UPS Documentation feedback Index Index
Related manuals
Manual 8 pages 155 b Manual 26 pages 60.09 Kb Manual 93 pages 30.86 Kb