New Buck Corporation 74 installation instructions Chimney, Floor Protection

Page 14

Chimney

This model is designed for connection to the following listed 2100º UL103 HT chimneys and parts. Follow chimneys manufacturer's instructions carefully.

Simpson Duravent

Metal Fab

Security

Airjet

Selkirk Metal Bestos

Jakes Evans

This room heater must be converted to (1) a chimney complying with the requirements for Type HT chimneys in the Standard for chimneys, Factory-Built, Residential, Type and Building Heating Appliance, UL 103, or (2) a code approved masonry chimney with a flue liner.

Floor Protection:

Floor protection must be 3/8” minimum thickness non-combustible material or equivalent.

How to use alternate materials and how to calculate equivalent thickness.

An easy means of determining if a proposed alternate floor protector meets requirements listed in the appliance manual is to follow this procedure:

1. Convert specification to R-value:

R-value is given—no conversion is needed.

K– factor is given with a required thickness (T) in inches: C-factor is given: R=1/C

2. Determine the R-value of the proposed alternate floor protector.

Use the formula in step (1) to convert values not expressed as “R”

For multiple layers, add R-values of each layer to determine the overall R-value.

3.If the overall R-value of the system is grater than the R-value of the specified floor protector, the alternate is acceptable.

Example:

The specified floor protector should be 3/4” thick material with a K-factor of 0.84.

The proposed alternate is 4” brick with a C-factor of 1.25 over 1/8” mineral board with a K-factor of 0.29.

Step (a): Use formula above to convert specification to R-value. R= 1/K x T = 1/0.84 x .75 = 0.893

12

Image 14
Contents BUCKSTOVE Page TABLE OF CONTENTS BEFORE INSTALLING YOUR NEW BUCK STOVE INSTALLATION, OPERATION, ANDMAINTENANCE INSTRUCTIONS MODEL IMPORTANT INSTRUCTIONSSECTION INTRODUCTIONMODEL MASONRY INSERT INSTALLATIONMINIMUM CLEARANCE MASONRY INSERT SECTIONMASONRY INSERT INSTALLATION POSSIBLE TOOLS NEEDED FOR INSTALLATIONINSTALLATION PREPARATION INSTALLATION OPTIONSOPTION A AIRTIGHT INSU LATED CLEAN OUT REMOVE DAMPEROR WIRE IT OPEN OPTION BPOSITIONING INSTALLATION PROCEDUREPOSITIONING THE HEATER MOUNTING THE TRIM PANELSFINAL CHECK Page SECTION PRE-FABINSERT INSTALLATION heater to the remainder of the home SECTION RESIDENTIAL FREESTANDING INSTALLATIONPREPARING THE STOVE FOR INSTALLATION Chimney Floor ProtectionDETERMINING THE CHIMNEY LOCATION B. Wall Exit Into Metal Tee-Box Page D. Ceiling Exit-CloseClearance Alcove Installation Clearances COLLARFINAL CHECK CLEARANCES FOR MODEL CLEARANCES FOR MODEL MINIMUM CLEARANCES TO COMBUSTIBLESRESIDENTIAL / MOBILE HOME CLEARANCES FOR MODEL CONNECTOR WITHOUT CLOSE CLEARANCE SHIELDSDOUBLE WALL OR SHIELDED SINGLE WALL MINIMUM CLEARANCES TO COMBUSTIBLESInstallation of Close Clearance Shields Optional WITH CLOSE CLEARANCE SHIELDS CLEARANCES FOR MODEL ALCOVE INSTALLATION DOUBLEOR SHIELDED SINGLE WALL CONNECTOR B H CSECTION FREESTANDING MOBILE HOME INSTALLATION FLOOR PROTECTIONCHIMNEY TOOLS FOR INSTALLATIONPREPARING THE HEATER FOR INSTALLATION PREPARING THE LOCATION FOR ROOM HEATER Ceiling Exit Using Close Clearance listed chimney Page FINAL CHECK 1.Recheck the specified clearancesSECTION WOOD HEATER SAFETY SECTION OPERATION BUILDING A FIRESOLUTION SECTION TROUBLESHOOTINGPROBLEM POSSIBLE CAUSEPOSSIBLE CAUSE PROBLEMSOLUTION NEW BUCK CORPORATION NBC WARRANTY TIME PERIODSPROCEDURE PRODUCTS COVEREDCONDITIONS AND EXCLUSIONS OTHER RIGHTS