CEILING
COLLAR
3 SHEET METAL SCREWS
ROOF
3 SHEET METAL SCREWS OR RIVETS
Figure 5
ATTIC |
18" MIN. |
CEILING |
CENTER LINE |
OF ELBOW |
WALL |
FLOOR PROTECTOR |
TEE BOX ASSEM.
CLEAN OUT ACCESS "TEE" BOX ASSEM.
WALL
Figure 6
B. Wall Exit Into Metal Tee-Box
1. Mark the plumb line on the wall directly behind the center of the heater. (See Figure 6.)
NOTE: When using 24# ga. minimum blue or black steel pipe, maintain 18" between pipe and ceiling.
NOTE: Floor protector must be under horizontal pipe exit (See Figure 9. Page 19. )
2.Place the vertical portion of the heater pipe and the elbow in position and project a point onto the plumb line level with the center of the elbow.