D. Install Attic Insulation Shield

WARNING! Fire Risk. DO NOT allow loose materials or insulation to touch vent. Hearth & Home Technologies Inc. requires the use of an attic shield.

The National Fuel Gas Code ANSI Z223.1 and NFPA 54 requires an attic shield constructed of 26 gauge minimum metal that extends at least 2 in. (51 mm) above insulation.

Attic shields must meet specified clearance and be se- cured in place.

Flat Ceiling Installation

• Remove one shield from box.

NOTICE: Cut previously installed batt insulation to make room for the attic insulation shield.

Wrap shield around pipe if pipe is already installed in area to be insulated.

Match the three holes in each side and fasten with three screws to form a tube.

Bend three tabs on the bottom of the shield outward to allow attachment to the ceiling firestop.

Bend the remaining bottom tabs inward 90° to maintain the air space between the pipe and the shield. Set the shield on the ceiling firestop and attach to the firestop.

Bend all tabs inward 90° around the top of the shield. These tabs must be used to prevent blown insulation from getting between the shield and vent pipe, and to maintain air space clearance.

Vaulted Ceiling Installation

The attic insulation shield has been laser-etched with cut lines and ceiling pitches to make field trimming easier.

Remove one shield from box.

NOTICE: Cut previously installed batt insulation to make room for the attic insulation shield.

Cut the attic insulation shield (if application is for vaulted ceiling) using a laser-etched cut line, to fit your ceiling pitch. Snip cut edge to recreate 1 in. bend tabs all the way around the bottom.

Wrap shield around pipe if pipe is already installed in area to be insulated.

Match the three holes in each side and fasten with three screws to form a tube.

Bend three tabs on the bottom of the shield outward to allow attachment to the ceiling firestop.

Bend the remaining bottom tabs inward 90° to maintain the air space between the pipe and the shield. Set the shield on the ceiling firestop and attach to the firestop.

Bend all tabs inward 90° around the top of the shield. These tabs must be used to prevent blown insulation from getting between the shield and vent pipe, and to maintain air space clearance.

BEND ALL TABS INWARD 90°

TO MAINTAIN CLEARANCE

AND PREVENT INSULATION

FROM FALLING INSIDE

LASER-ETCHED

INSERT 3 CUT LINES

SCREWS

BEND 3 TABS

OUTWARD TO

FASTEN TO CEILING

FIRESTOP-BEND

REMAINING TABS

INWARD 90 DEGREES

TO MAINTAIN

CLEARANCE

Figure 8.6 Attic Insulation Shield

Heat & Glo • SLR • 2143-900 Rev. B • 7/08

33

Image 33
Contents What to do if you smell gas Model SLR CosmoHomeowner Reference Information CongratulationsUser Guide Table of ContentsTroubleshooting Appliance SetupFinishing Reference MaterialsLimited Lifetime Warranty Heat & GLO GAS Appliance Products Limited Lifetime WarrantyListing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsGas Fireplace Safety Operating Instructions User GuideYour Fireplace Remote Controls, Wall Controls and Wall Switches Fixed Glass AssemblyClear Space Decorative Doors and FrontsFinal inspection by Lighting Instructions IPIFrequently Asked Questions Initial Break-in ProcedureAfter Fireplace is Lit Maintenance Tasks-Homeowner Maintenance and ServiceGlass Cleaning Remote ControlGasket Seal and Glass Assembly Inspection Maintenance Tasks-Qualified Service TechnicianVenting FireboxTypical Appliance System Getting StartedDesign and Installation Considerations Tools and Supplies NeededInspect Appliance and Components Selecting Appliance Location Framing and ClearancesClearances Constructing the Appliance ChaseCombustible Mantels Mantel and Wall ProjectionsNon-combustible Mantels Front Side Finishing DetailAIR Space Vent Termination Minimum Clearances Termination LocationsCovered Alcove Applications Vent Information and Diagrams Minimum Maximum Top Vent Horizontal Termination Venting with 1 elbowTop Vent Horizontal Termination Venting with 2 elbows Venting with 3 elbows Top Vent Horizontal TerminationTop Vent Horizontal Termination Venting with 3 elbows Exhaust restrictor Instructions Top Vent Vertical Termination No Elbows V1 = 44 ft. Max .4 mV1 Minimum Maximum V1 + V2 Minimum Top Vent Vertical Termination Venting with 2 elbowsTop Vent Vertical Termination Venting with 3 elbows V1 MIN H1 MAX V2 MIN H2 MAX V3 MIN Top Vent Vertical Termination Venting with 4 elbowsPipe Clearances to Combustibles Vent Clearances and FramingWall Penetration Framing Combustible Wall PenetrationPipe SLP Install the Ceiling FirestopInstall Attic Insulation Shield Flat Ceiling InstallationVaulted Ceiling Installation Top Vent Appliance PreparationProper Positioning, Leveling And Securing Of An Securing and Leveling the ApplianceAssemble Vent Sections Installing Vent Pipe SLP PipeSecure The Vent Sections Assemble Slip SectionsDisassemble Vent Sections Install Decorative Ceiling ComponentsAssemble and Install Storm Collar Install Metal Roof Flashing15 Secure Pipe with SLP-FS Install RF4-8Install Vertical Termination Cap Install Decorative Wall ComponentsHeat Shield Requirements for Horizontal Termination 22 Venting through the wall Install Horizontal Termination CapGas Information Fuel ConversionGas Pressure Gas Connection Gas Fitting AccessIntellifire Ignition System Wiring Wiring RequirementsOptional Accessories Requirements Electrical InformationJunction Box Detail Electrical Service and Repair Junction Box InstallationFraming and Finishing Instructions FinishingFinishing Details Confirm Fireplace Opening Dimension Opening 12 Overlap Fit Method Tonic or Martini Decorative Front Facing Material14 Inside Fit Method Tonic Decorative Front Only 17 Tonic Decorative Front Decorative FrontsRemove Fixed Glass Assembly Appliance SetupClean the Appliance AccessoriesRock Media Instructions Cleaning the RockScrew Install the Mesh Air Shutter SettingAir Shutter Settings Troubleshooting Symptom Possible Cause Corrective ActionIntellifire Ignition System Remove any contaminants that may have accumulated on Reference Materials Appliance Dimension DiagramDVP-BEK2 Vent Components DiagramsSLP90- 90 Elbow SLP-45 45 ElbowExtended Heat Shield RF4-8Support Box-Black PVK-80Horizontal Ceiling Firestop AdapterPart number list on following Service PartsService Parts List StockedAt Depot IPI Valve Assembly Contact Information