I. Install Vertical Termination Cap

Attach the vertical termination cap by sliding the inner collar of the cap into the inner flue of the pipe section while placing the outer collar of the cap over the outer flue of the pipe section.

Secure the cap by driving three self-tapping screws (supplied) through the pilot holes in the outer collar of the cap into the outer flue of the pipe (see Figure 10.20).

TERMINATION CAP

(1 of 3)

STORM

COLLAR

SCREWS

CAULK

Figure 10.20

J. Install Decorative Wall Components

A decorative wall thimble can be installed on wall through which the vent passes. The decorative wall thimble is used to cover the firestop.

Slide the decorative wall thimble over the last section of horizontal pipe before connecting the termination cap to the pipe.

Once the pipe section and the termination cap have been connected, slide the wall thimble up to the interior wall surface and attach with screws provided. See Figure 10.21.

K.Heat Shield Requirements for Horizontal Termination

WARNING! Risk of Fire! To prevent overheating and fire, heat shields must extend through the entire wall thick- ness.

DO NOT remove the heat shields attached to the wall shield firestop and the horizontal termination cap (shown in Figure 10.22).

Heat shields must overlap 1-1/2 in. (38 mm) mini- mum.

There are two sections of the heat shield. One section is factory-attached to the wall shield firestop. The other section is factory-attached to the cap. See Figure 10.22.

If the wall thickness does not allow the required 1-1/2 in. (38 mm) heat shield overlap when installed, an extended heat shield must be used.

If the wall thickness is less than 4 in./102 mm (DVP) or 4-3/8 in./ 111 mm (SLP), the heat shields on the cap and wall shield firestop must to be trimmed. A minimum 1-1/2 in. (38 mm) overlap MUST be maintained.

Use an extended heat shield if the finished wall thickness is greater than 7-1/4 in. (184 mm).

The extended heat shield may need to be cut to length maintaining sufficient length for a 1-1/2 in. (38 mm) overlap between heat shields.

Attach the extended heat shield to either of the existing heat shields using the screws supplied with the extended heat shield. Refer to vent components diagrams in the back of this manual.

Rest the small leg on the extended heat shield on top of the pipe section to properly space it from the pipe section.

Important Notice: Heat shields may not be field constructed.

Figure 10.21 Wall Thimble

Heat & Glo • SLR • 2143-900 Rev. B • 7/08

41

Image 41
Contents What to do if you smell gas Model SLR CosmoHomeowner Reference Information CongratulationsUser Guide Table of ContentsTroubleshooting Appliance SetupFinishing Reference MaterialsLimited Lifetime Warranty Heat & GLO GAS Appliance Products Limited Lifetime WarrantyListing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsYour Fireplace Gas Fireplace SafetyOperating Instructions User Guide Remote Controls, Wall Controls and Wall Switches Fixed Glass AssemblyClear Space Decorative Doors and FrontsFinal inspection by Lighting Instructions IPIAfter Fireplace is Lit Frequently Asked QuestionsInitial Break-in Procedure Maintenance Tasks-Homeowner Maintenance and ServiceGlass Cleaning Remote ControlGasket Seal and Glass Assembly Inspection Maintenance Tasks-Qualified Service TechnicianVenting FireboxTypical Appliance System Getting StartedInspect Appliance and Components Design and Installation ConsiderationsTools and Supplies Needed Selecting Appliance Location Framing and ClearancesClearances Constructing the Appliance ChaseCombustible Mantels Mantel and Wall ProjectionsNon-combustible Mantels Front Side Finishing DetailAIR Space Vent Termination Minimum Clearances Termination LocationsCovered Alcove Applications Vent Information and Diagrams Minimum Maximum Top Vent Horizontal Termination Venting with 1 elbowTop Vent Horizontal Termination Venting with 2 elbows Venting with 3 elbows Top Vent Horizontal TerminationTop Vent Horizontal Termination Venting with 3 elbows Exhaust restrictor Instructions Top Vent Vertical Termination No Elbows V1 = 44 ft. Max .4 mV1 Minimum Maximum V1 + V2 Minimum Top Vent Vertical Termination Venting with 2 elbowsTop Vent Vertical Termination Venting with 3 elbows V1 MIN H1 MAX V2 MIN H2 MAX V3 MIN Top Vent Vertical Termination Venting with 4 elbowsPipe Clearances to Combustibles Vent Clearances and FramingWall Penetration Framing Combustible Wall PenetrationPipe SLP Install the Ceiling FirestopVaulted Ceiling Installation Install Attic Insulation ShieldFlat Ceiling Installation Top Vent Appliance PreparationProper Positioning, Leveling And Securing Of An Securing and Leveling the ApplianceAssemble Vent Sections Installing Vent Pipe SLP PipeSecure The Vent Sections Assemble Slip SectionsDisassemble Vent Sections Install Decorative Ceiling ComponentsAssemble and Install Storm Collar Install Metal Roof Flashing15 Secure Pipe with SLP-FS Install RF4-8Heat Shield Requirements for Horizontal Termination Install Vertical Termination CapInstall Decorative Wall Components 22 Venting through the wall Install Horizontal Termination CapGas Pressure Gas InformationFuel Conversion Gas Connection Gas Fitting AccessIntellifire Ignition System Wiring Wiring RequirementsOptional Accessories Requirements Electrical InformationJunction Box Detail Electrical Service and Repair Junction Box InstallationFraming and Finishing Instructions FinishingFinishing Details Confirm Fireplace Opening Dimension Opening 12 Overlap Fit Method Tonic or Martini Decorative Front Facing Material14 Inside Fit Method Tonic Decorative Front Only 17 Tonic Decorative Front Decorative FrontsRemove Fixed Glass Assembly Appliance SetupClean the Appliance AccessoriesRock Media Instructions Cleaning the RockScrew Air Shutter Settings Install the MeshAir Shutter Setting Intellifire Ignition System TroubleshootingSymptom Possible Cause Corrective Action Remove any contaminants that may have accumulated on Reference Materials Appliance Dimension DiagramDVP-BEK2 Vent Components DiagramsSLP90- 90 Elbow SLP-45 45 ElbowExtended Heat Shield RF4-8Support Box-Black PVK-80Horizontal Ceiling Firestop AdapterPart number list on following Service PartsAt Depot Service Parts ListStocked IPI Valve Assembly Contact Information