12 Electrical Information

A. Wiring Requirements

NOTICE: This appliance must be electrically wired and grounded in accordance with local codes or, in the absence of local codes, with National Electric Code ANSI/NFPA 70-latest edition or the Canadian Electric

Code CSA C22.1.

Wire the appliance junction box to 110-120 VAC. This is required for use of optional accessories (standing pilot ignition) or proper operation of the appliance (Intellifire ignition).

Low voltage and 110 VAC voltage cannot be shared within the same wall box.

WARNING! Risk of Shock or Explosion! DO NOT wire 110V to the valve or to the appliance wall switch. Incorrect wiring will damage controls.

B. Intellifire Ignition System Wiring

Wire the appliance junction box to 110 VAC for proper operation of the appliance.

WARNING! Risk of Shock or Explosion! DO NOT wire IPI controlled appliance junction box to a switched circuit. Incorrect wiring will override IPI safety lockout.

Refer to Figure 12.2, Intellifire Pilot Ignition (IPI) Wiring Diagram.

This appliance is equipped with an Intellifire control valve which operates on a 3 volt system.

Plug the 3-volt AC transformer into the appliance junction box to supply power to the unit OR install two D cell batteries (not included) into the battery pack before use.

NOTICE: Batteries should not be placed in the battery pack while using the transformer. Remove batteries before using the transformer, and unplug the transformer before installing the batteries. Battery polarity must be correct or module damage will occur.

C. Optional Accessories Requirements

This appliance may be used with a wall switch, wall mounted thermostat and/or a remote control.

Wiring for optional Hearth & Home Technologies approved accessories should be done now to avoid reconstruction. Follow instructions that come with those accessories.

Optional Remote Control Receiver and Battery Pack Location

Batteries are to be installed only when battery power is

Î

 

required. Because of the limited accessibility to valve

 

cavity, the position of the Battery Tray, IPI Control Module,

 

and Optional Remote Control Receiver locations must be

 

installed as shown in Figure 12.1.

 

The Battery Tray, Control Module, and Remote Control

 

receiver can be accessed thru the air space between the

 

firebox front and the lower-front finishing cover panel. The

 

decorative front and glass assembly must be removed to

 

access these components.

 

The battery tray is attached with velcro to the inside of

 

the lower cover panel. The IPI control module and the

 

remote control receiver are placed on the firebox bottom.

 

FIREBOX BOTTOM

BATTERY TRAY

IPI CONTROL MODULE

REMOTE CONTROL RECEIVER

LOWER ACCESS PANEL

Figure 12.1 Valve Cavity

Heat & Glo • SLR • 2143-900 Rev. B • 7/08

45

Image 45
Contents What to do if you smell gas Model SLR CosmoHomeowner Reference Information CongratulationsUser Guide Table of ContentsTroubleshooting Appliance SetupFinishing Reference MaterialsLimited Lifetime Warranty Heat & GLO GAS Appliance Products Limited Lifetime WarrantyListing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsGas Fireplace Safety Operating Instructions User GuideYour Fireplace Remote Controls, Wall Controls and Wall Switches Fixed Glass AssemblyClear Space Decorative Doors and FrontsFinal inspection by Lighting Instructions IPIFrequently Asked Questions Initial Break-in ProcedureAfter Fireplace is Lit Maintenance Tasks-Homeowner Maintenance and ServiceGlass Cleaning Remote ControlGasket Seal and Glass Assembly Inspection Maintenance Tasks-Qualified Service TechnicianVenting FireboxTypical Appliance System Getting StartedDesign and Installation Considerations Tools and Supplies NeededInspect Appliance and Components Selecting Appliance Location Framing and ClearancesClearances Constructing the Appliance ChaseCombustible Mantels Mantel and Wall ProjectionsNon-combustible Mantels Front Side Finishing DetailAIR Space Vent Termination Minimum Clearances Termination LocationsCovered Alcove Applications Vent Information and Diagrams Minimum Maximum Top Vent Horizontal Termination Venting with 1 elbowTop Vent Horizontal Termination Venting with 2 elbows Venting with 3 elbows Top Vent Horizontal TerminationTop Vent Horizontal Termination Venting with 3 elbows Exhaust restrictor Instructions Top Vent Vertical Termination No Elbows V1 = 44 ft. Max .4 mV1 Minimum Maximum V1 + V2 Minimum Top Vent Vertical Termination Venting with 2 elbowsTop Vent Vertical Termination Venting with 3 elbows V1 MIN H1 MAX V2 MIN H2 MAX V3 MIN Top Vent Vertical Termination Venting with 4 elbowsPipe Clearances to Combustibles Vent Clearances and FramingWall Penetration Framing Combustible Wall PenetrationPipe SLP Install the Ceiling FirestopInstall Attic Insulation Shield Flat Ceiling InstallationVaulted Ceiling Installation Top Vent Appliance PreparationProper Positioning, Leveling And Securing Of An Securing and Leveling the ApplianceAssemble Vent Sections Installing Vent Pipe SLP PipeSecure The Vent Sections Assemble Slip SectionsDisassemble Vent Sections Install Decorative Ceiling ComponentsAssemble and Install Storm Collar Install Metal Roof Flashing15 Secure Pipe with SLP-FS Install RF4-8Install Vertical Termination Cap Install Decorative Wall ComponentsHeat Shield Requirements for Horizontal Termination 22 Venting through the wall Install Horizontal Termination CapGas Information Fuel ConversionGas Pressure Gas Connection Gas Fitting AccessIntellifire Ignition System Wiring Wiring RequirementsOptional Accessories Requirements Electrical InformationJunction Box Detail Electrical Service and Repair Junction Box InstallationFraming and Finishing Instructions FinishingFinishing Details Confirm Fireplace Opening Dimension Opening 12 Overlap Fit Method Tonic or Martini Decorative Front Facing Material14 Inside Fit Method Tonic Decorative Front Only 17 Tonic Decorative Front Decorative FrontsRemove Fixed Glass Assembly Appliance SetupClean the Appliance AccessoriesRock Media Instructions Cleaning the RockScrew Install the Mesh Air Shutter SettingAir Shutter Settings Troubleshooting Symptom Possible Cause Corrective ActionIntellifire Ignition System Remove any contaminants that may have accumulated on Reference Materials Appliance Dimension DiagramDVP-BEK2 Vent Components DiagramsSLP90- 90 Elbow SLP-45 45 ElbowExtended Heat Shield RF4-8Support Box-Black PVK-80Horizontal Ceiling Firestop AdapterPart number list on following Service PartsService Parts List StockedAt Depot IPI Valve Assembly Contact Information