B. Mantel and Wall Projections

WARNING! Risk of Fire! Comply with all minimum clear- ances to combustibles as specified. Framing closer than the minimums listed must be constructed entirely of noncom- bustible materials (i.e., steel studs, concrete board, etc.) Failure to comply could cause fire.

Note: For non-combustible fireplace finish mate- rial (marble, stone, etc) specifications refer to Figure 13.13 and Figure 13.15.

Combustible Mantels

1/2 in. Thick Wall

Sheathing 12 in. MAX.

14 in. MEASUREMENT FROM TOP OF MIN. FIREPLACE OPENING

Figure 13.8 Clearances To Combustibles Mantels Or Other Combustibles Above Appliance

Non-combustible Mantels

1/2 in. Thick Wall

Sheathing 12 in. MAX.

14 in. MEASUREMENT MIN. FROM TOP OF FIREPLACE

OPENING

Figure 13.9 Clearances To Non-Combustible Mantels Or Other

Non-Combustibles Above Appliance

Combustible Mantel Legs Or Wall Projections Extending Past The Face Of The Fireplace

2 IN.

MINIMUM 3 FT. MAXIMUM

6 IN.

MINIMUM

Figure 13.10 Combustible Mantel Leg or Wall Projections (Acceptable on both sides of opening)

Non-combustible Mantel Legs Or Wall Projections Extending Past The Face Of The Fireplace

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3 IN.

 

 

 

 

 

 

 

 

 

UNLIMITED

MINIMUM

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Figure 13.11 Non-Combustible Mantel Leg or Wall Projections

Î

(Acceptable on both sides of opening)

 

50

Heat & Glo • SLR • 2143-900 Rev. B • 7/08

Image 50
Contents Model SLR Cosmo What to do if you smell gasCongratulations Homeowner Reference InformationTable of Contents User GuideFinishing Appliance SetupTroubleshooting Reference MaterialsLimited Lifetime Warranty Limited Lifetime Warranty Heat & GLO GAS Appliance ProductsListing and Code Approvals Installation of Carbon Monoxide Detectors Requirements for the Commonwealth of MassachusettsYour Fireplace Gas Fireplace SafetyOperating Instructions User Guide Clear Space Fixed Glass AssemblyRemote Controls, Wall Controls and Wall Switches Decorative Doors and FrontsLighting Instructions IPI Final inspection byAfter Fireplace is Lit Frequently Asked QuestionsInitial Break-in Procedure Glass Cleaning Maintenance and ServiceMaintenance Tasks-Homeowner Remote ControlVenting Maintenance Tasks-Qualified Service TechnicianGasket Seal and Glass Assembly Inspection FireboxGetting Started Typical Appliance SystemInspect Appliance and Components Design and Installation ConsiderationsTools and Supplies Needed Framing and Clearances Selecting Appliance LocationConstructing the Appliance Chase ClearancesNon-combustible Mantels Mantel and Wall ProjectionsCombustible Mantels Front Side Finishing DetailAIR Space Termination Locations Vent Termination Minimum ClearancesCovered Alcove Applications Vent Information and Diagrams Top Vent Horizontal Termination Venting with 1 elbow Minimum MaximumTop Vent Horizontal Termination Venting with 2 elbows Top Vent Horizontal Termination Venting with 3 elbowsTop Vent Horizontal Termination Venting with 3 elbows Top Vent Vertical Termination No Elbows V1 = 44 ft. Max .4 m Exhaust restrictor InstructionsTop Vent Vertical Termination Venting with 2 elbows V1 Minimum Maximum V1 + V2 MinimumTop Vent Vertical Termination Venting with 3 elbows Top Vent Vertical Termination Venting with 4 elbows V1 MIN H1 MAX V2 MIN H2 MAX V3 MINWall Penetration Framing Vent Clearances and FramingPipe Clearances to Combustibles Combustible Wall PenetrationInstall the Ceiling Firestop Pipe SLPVaulted Ceiling Installation Install Attic Insulation ShieldFlat Ceiling Installation Appliance Preparation Top VentSecuring and Leveling the Appliance Proper Positioning, Leveling And Securing Of AnInstalling Vent Pipe SLP Pipe Assemble Vent SectionsAssemble Slip Sections Secure The Vent SectionsInstall Decorative Ceiling Components Disassemble Vent SectionsInstall Metal Roof Flashing Assemble and Install Storm CollarInstall RF4-8 15 Secure Pipe with SLP-FSHeat Shield Requirements for Horizontal Termination Install Vertical Termination CapInstall Decorative Wall Components Install Horizontal Termination Cap 22 Venting through the wallGas Pressure Gas InformationFuel Conversion Gas Fitting Access Gas ConnectionOptional Accessories Requirements Wiring RequirementsIntellifire Ignition System Wiring Electrical InformationElectrical Service and Repair Junction Box Installation Junction Box DetailFinishing Framing and Finishing InstructionsFinishing Details Confirm Fireplace Opening Dimension Opening Facing Material 12 Overlap Fit Method Tonic or Martini Decorative Front14 Inside Fit Method Tonic Decorative Front Only Decorative Fronts 17 Tonic Decorative FrontClean the Appliance Appliance SetupRemove Fixed Glass Assembly AccessoriesCleaning the Rock Rock Media InstructionsScrew Air Shutter Settings Install the MeshAir Shutter Setting Intellifire Ignition System TroubleshootingSymptom Possible Cause Corrective Action Remove any contaminants that may have accumulated on Appliance Dimension Diagram Reference MaterialsVent Components Diagrams DVP-BEK2Extended Heat Shield SLP-45 45 ElbowSLP90- 90 Elbow RF4-8Horizontal Ceiling Firestop PVK-80Support Box-Black AdapterService Parts Part number list on followingAt Depot Service Parts ListStocked IPI Valve Assembly Contact Information