8 Installing Vent Pipe

A. Assemble Vent Sections

To attach the first vent component to the starting collars of the appliance:

Lock the vent components into place by sliding the pipe section onto the collar.

Align the seam of the pipe and seam of collar to allow engagement. Rotate the vent component to lock into place. Use this procedure for all vent components. See Figure 8.1.

Slide the gasket over the first vent section and place it flush to the appliance. This will prevent cold air infiltration. Caulk with a minimum of 300ºF continuous exposure rating may be used to hold the part in place.

Continue adding vent components, locking each succeeding component into place.

Ensure that each succeeding vent component is securely fitted and locked into the preceding component.

Commercial, Multi-family (Multi-level exceeding two sto- ries), or High-Rise Applications

For Installation into a commercial, multi-family (multi-level exceeding two stories) or high-rise applications: All outer pipe joints must be sealed with silicone with a minimum of 300ºF continuous exposure rating, including the slip section that connects directly to the horizontal termination cap.

Apply a bead of silicone sealant inside the female outer pipe joint prior to joining sections. See Figure 8.2

Only outer pipes need to be sealed. All unit collar, pipe, slip section, elbow and cap outer flues shall be sealed in this manner, unless otherwise stated.

WARNING! Risk of Fire or Explosion! DO NOT break silicone seals on slip sections. Use care when removing termination cap from slip pipe. If slip section seals are broken during removal of the termination cap, vent may leak.

Note: Align seams to engage pipe, then rotate counterclockwise to lock

Figure 8.1 Adding Venting Components

Figure 8.2 High Temperature Silicone Sealant

22

Heat & Glo • Soho24B • 2137-900 Rev. P • 8/12

Image 22
Contents What to do if you smell gas Model Soho24BHot glass will cause burns Congratulations Homeowner Reference InformationTable of Contents Listing and Code Approvals Installation of Carbon Monoxide Detectors Requirements for the Commonwealth of MassachusettsGetting Started Installation to ensure maximum safety and benefitTools and Supplies Needed Selecting Appliance Location Framing and ClearancesMantel Projections Constructing the Appliance Chase ClearancesVent Termination Minimum Clearances Termination LocationsSee .4 for specific clearances Covered Alcove Applications Inches U.S.AUse of Elbows Vent Information and DiagramsVent Table Key Measuring StandardsTwo Elbows Vent DiagramsTop Vent Horizontal Termination One Elbow Minimum MaximumTop Vent Horizontal Termination Three Elbows V1 Min H1 Max V2 Min H2 MaxV1 = 45 ft Max .72 m V1 = 3 ft Min mm Top Vent Vertical Termination No ElbowV1 Minimum H1 Maximum V1 + Top Vent Vertical Termination Three Elbows V1 Minimum H1+ H2 Maximum V1+ V2 MinimumWall Penetration Framing Vent Clearances and FramingPipe Clearances to Combustibles Combustible Wall PenetrationVertical Penetration Framing Pipe SLPFlat Ceiling Installation Install Attic Insulation ShieldVaulted Ceiling Installation Appliance Preparation Top VentInstallation of Non-combustible Facing Material MaterialSecuring and Leveling the Appliance Proper Positioning, Leveling and Securing of aInstalling Vent Pipe Assemble Vent SectionsAssemble Slip Sections Secure the Vent SectionsInstall Decorative Ceiling Components Disassemble Vent SectionsInstall Metal Roof Flashing Assemble and Install Storm CollarInstall Decorative Wall Components Install Vertical Termination CapHeat Shield Requirements for Horizontal Termination Install Horizontal Termination Cap 17 Venting through the wallGas Pressures Gas InformationFuel Conversions Gas Connection Pressure Natural Gas PropaneHigh Altitude Installations Recommendation for Wire Electrical InformationJunction Box Installation GRN wire Ground attached To GRN screw with Inside boxFacing Material FinishingSee for combustible/non-combustible definitions Installation of Non-Combustible Facing Materials PaintingAccessories Appliance SetupClean the Appliance Remove Shipping MaterialsStone Placement Soho24B Positioning StonesNo Stones in this Area Removing Glass Assembly Glass AssemblyAir Shutter Setting Replacing Glass AssemblyOperating Instructions Before Lighting ApplianceLighting Instructions IPI Final inspection byInitial Break-in Procedure Frequently Asked QuestionsAfter Appliance is Lit IntelliFire Ignition System TroubleshootingSympton Possible Cause Corrective Action Symptom Possible Cause Corrective Action Maintenance Tasks Maintaining and Servicing ApplianceInspect Maintenance Tasks Recommend addition of screen if one is not presentReference Materials Appliance Dimension DiagramAppliance Dimensions Table Location Inches MillimeterVent Components Diagrams SL Series Components B. Vent Components Diagrams Assembly 12-1/2 356 mm 330 mm305 mm 318 mmAt Depot Service PartsStocked 24 x 24 Direct Vent Fireplace#11 IPI Valve Assembly SOHO24B-ONYX No longer availableLimited Lifetime Warranty Limited Lifetime WarrantyWarranty Conditions Contact Information