K. Install Horizontal Termination Cap

WARNING! Risk of Fire! The telescoping flue section of the termination cap MUST be used when connecting vent.

1-1/2 (38 mm) minimum overlap of flue telescoping section is required.

Failure to maintain overlap may cause overheating and fire.

Vent termination must not be recessed in the wall. Siding may be brought to the edge of the cap base.

Flash and seal as appropriate for siding material at outside edges of cap.

When installing a horizontal termination cap, follow the cap location guidelines as prescribed by current ANSI Z223.1 and CAN/CGA-B149installation codes and refer to Section 6 of this manual.

CAUTION! Risk of Burns! Local codes may require installation of a cap shield to prevent anything or anyone from touching the hot cap.

NOTICE: For certain exposures which require superior resistance to wind-driven rain penetration, a flashing kit and HRC caps are available. When penetrating a brick wall, a brick extension kit is available for framing the brick.

Note: When using termination caps with factory-supplied heat shield attached, no additional wall shield firestop is required on the exterior side of a combustible wall.

HEAT SHIELD OR

HEAT SHIELD

EXTENDED

1-1/2 IN. (38 MM) MIN.

HEAT SHIELD

OVERLAP

WALL SHIELD

 

FIRESTOP

 

SLIP SECTION

 

CAN BE EXTENDED

 

INNER VENT

SHEATHING

OUTER VENT

 

INTERIOR

EXTERIOR

Figure 8.17 Venting through the wall

 

Heat & Glo • Soho24B • 2137-900 Rev. P • 8/12

27

Image 27
Contents Model Soho24B What to do if you smell gasHot glass will cause burns Homeowner Reference Information CongratulationsTable of Contents Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsInstallation to ensure maximum safety and benefit Getting StartedTools and Supplies Needed Framing and Clearances Selecting Appliance LocationMantel Projections Clearances Constructing the Appliance ChaseTermination Locations Vent Termination Minimum ClearancesSee .4 for specific clearances Inches U.S.A Covered Alcove ApplicationsMeasuring Standards Vent Information and DiagramsVent Table Key Use of ElbowsMinimum Maximum Vent DiagramsTop Vent Horizontal Termination One Elbow Two ElbowsV1 Min H1 Max V2 Min H2 Max Top Vent Horizontal Termination Three ElbowsTop Vent Vertical Termination No Elbow V1 = 45 ft Max .72 m V1 = 3 ft Min mmV1 Minimum H1 Maximum V1 + V1 Minimum H1+ H2 Maximum V1+ V2 Minimum Top Vent Vertical Termination Three ElbowsCombustible Wall Penetration Vent Clearances and FramingPipe Clearances to Combustibles Wall Penetration FramingPipe SLP Vertical Penetration FramingInstall Attic Insulation Shield Flat Ceiling InstallationVaulted Ceiling Installation Top Vent Appliance PreparationMaterial Installation of Non-combustible Facing MaterialProper Positioning, Leveling and Securing of a Securing and Leveling the ApplianceAssemble Vent Sections Installing Vent PipeSecure the Vent Sections Assemble Slip SectionsDisassemble Vent Sections Install Decorative Ceiling ComponentsAssemble and Install Storm Collar Install Metal Roof FlashingInstall Vertical Termination Cap Install Decorative Wall ComponentsHeat Shield Requirements for Horizontal Termination 17 Venting through the wall Install Horizontal Termination CapPressure Natural Gas Propane Gas InformationFuel Conversions Gas Connection Gas PressuresHigh Altitude Installations Electrical Information Recommendation for WireGRN wire Ground attached To GRN screw with Inside box Junction Box InstallationFinishing Facing MaterialSee for combustible/non-combustible definitions Painting Installation of Non-Combustible Facing MaterialsRemove Shipping Materials Appliance SetupClean the Appliance AccessoriesPositioning Stones Stone Placement Soho24BNo Stones in this Area Replacing Glass Assembly Glass AssemblyAir Shutter Setting Removing Glass AssemblyBefore Lighting Appliance Operating InstructionsFinal inspection by Lighting Instructions IPIFrequently Asked Questions Initial Break-in ProcedureAfter Appliance is Lit Troubleshooting IntelliFire Ignition SystemSympton Possible Cause Corrective Action Symptom Possible Cause Corrective Action Maintaining and Servicing Appliance Maintenance TasksRecommend addition of screen if one is not present Inspect Maintenance TasksLocation Inches Millimeter Appliance Dimension DiagramAppliance Dimensions Table Reference MaterialsSL Series Components Vent Components Diagrams B. Vent Components Diagrams Assembly 318 mm 356 mm 330 mm305 mm 12-1/224 x 24 Direct Vent Fireplace Service PartsStocked At Depot#11 IPI Valve Assembly No longer available SOHO24B-ONYXLimited Lifetime Warranty Limited Lifetime WarrantyWarranty Conditions Contact Information