Heat & Glo LifeStyle 2137-900 Install Metal Roof Flashing, Assemble and Install Storm Collar

Page 25

F. Install Metal Roof Flashing

See minimum vent heights for various pitched roofs (Figure 8.11) to determine the length of pipe to extend through the roof.

Slide the roof flashing over the pipe sections extending through the roof as shown in Figure 8.12.

 

 

HORIZONTAL

 

 

OVERHANG

2 FT.

20 INCHES MIN.

VERTICAL

MIN.

 

 

WALL

 

LOWEST

 

 

 

DISCHARGE

 

 

OPENING

 

GAS DIRECT VENT

 

 

TERMINATION CAP

 

 

 

 

X

 

 

12

 

 

ROOF PITCH

 

 

IS X/ 12

 

H (MIN.) - MINIMUM HEIGHT FROM ROOF

 

TO LOWEST DISCHARGE OPENING

Roof Pitch

 

H (Min.) Ft.

Flat to 6/12........................................1.0*

Over 6/12 to 7/12............................1.25*

Over 7/12 to 8/12..............................1.5*

Over 8/12 to 9/12..............................2.0*

Over 9/12 to 10/12............................. 2.5

Over 10/12 to 11/12 ......................... 3.25

Over 11/12 to 12/12 ........................... 4.0

Over 12/12 to 14/12........................... 5.0

Over 14/12 to 16/12........................... 6.0

Over 16/12 to 18/12........................... 7.0

Over 18/12 to 20/12........................... 7.5

Over 20/12 to 21/12........................... 8.0

* 3 foot minimum in snow regions

Figure 8.11 Minimum Height From Roof To Lowest Discharge

Opening

 

 

NOTICE: Failure to properly caulk the roof flashing and pipe seams may permit entry of water.

Caulk the gap between the roof flashing and the outside diameter of the pipe.

Caulk the perimeter of the flashing where it contacts the roof surface. See Figure 8.12.

Caulk the overlap seam of any exposed pipe sections that are located above the roof line.

CAULK

Figure 8.12

G. Assemble and Install Storm Collar

CAUTION! Risk of Cuts, Abrasions or Flying Debris. Wear protective gloves and safety glasses during installation. Sheet metal edges are sharp.

Connect both halves of the storm collar with two screws (see Figure 8.13).

Wrap the storm collar around the exposed pipe section closest to the roof and align brackets. Insert a bolt (provided) through the brackets and tighten the nut to complete the storm collar assembly. Make sure the collar is tight against the pipe section.

Slide the assembled storm collar down the pipe section until it rests on the roof flashing (see Figure 8.14).

Caulk around the top of the storm collar (see Figure 8.15).

Figure 8.13 Assembling the Storm Collar

Figure 8.14 Assembling the Storm Collar Around the Pipe

Heat & Glo • Soho24B • 2137-900 Rev. P • 8/12

25

Image 25
Contents What to do if you smell gas Model Soho24BHot glass will cause burns Homeowner Reference Information CongratulationsTable of Contents Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsGetting Started Installation to ensure maximum safety and benefitTools and Supplies Needed Selecting Appliance Location Framing and ClearancesMantel Projections Clearances Constructing the Appliance ChaseVent Termination Minimum Clearances Termination LocationsSee .4 for specific clearances Inches U.S.A Covered Alcove ApplicationsVent Table Key Vent Information and DiagramsUse of Elbows Measuring StandardsTop Vent Horizontal Termination One Elbow Vent DiagramsTwo Elbows Minimum MaximumV1 Min H1 Max V2 Min H2 Max Top Vent Horizontal Termination Three ElbowsV1 = 45 ft Max .72 m V1 = 3 ft Min mm Top Vent Vertical Termination No ElbowV1 Minimum H1 Maximum V1 + V1 Minimum H1+ H2 Maximum V1+ V2 Minimum Top Vent Vertical Termination Three ElbowsPipe Clearances to Combustibles Vent Clearances and FramingWall Penetration Framing Combustible Wall PenetrationPipe SLP Vertical Penetration FramingFlat Ceiling Installation Install Attic Insulation ShieldVaulted Ceiling Installation Top Vent Appliance PreparationMaterial Installation of Non-combustible Facing MaterialProper Positioning, Leveling and Securing of a Securing and Leveling the ApplianceAssemble Vent Sections Installing Vent PipeSecure the Vent Sections Assemble Slip SectionsDisassemble Vent Sections Install Decorative Ceiling ComponentsAssemble and Install Storm Collar Install Metal Roof FlashingInstall Decorative Wall Components Install Vertical Termination CapHeat Shield Requirements for Horizontal Termination 17 Venting through the wall Install Horizontal Termination CapFuel Conversions Gas Connection Gas InformationGas Pressures Pressure Natural Gas PropaneHigh Altitude Installations Electrical Information Recommendation for WireGRN wire Ground attached To GRN screw with Inside box Junction Box InstallationFacing Material FinishingSee for combustible/non-combustible definitions Painting Installation of Non-Combustible Facing MaterialsClean the Appliance Appliance SetupAccessories Remove Shipping MaterialsPositioning Stones Stone Placement Soho24BNo Stones in this Area Air Shutter Setting Glass AssemblyRemoving Glass Assembly Replacing Glass AssemblyBefore Lighting Appliance Operating InstructionsFinal inspection by Lighting Instructions IPIInitial Break-in Procedure Frequently Asked QuestionsAfter Appliance is Lit IntelliFire Ignition System TroubleshootingSympton Possible Cause Corrective Action Symptom Possible Cause Corrective Action Maintaining and Servicing Appliance Maintenance TasksRecommend addition of screen if one is not present Inspect Maintenance TasksAppliance Dimensions Table Appliance Dimension DiagramReference Materials Location Inches MillimeterSL Series Components Vent Components Diagrams B. Vent Components Diagrams Assembly 305 mm 356 mm 330 mm12-1/2 318 mmStocked Service PartsAt Depot 24 x 24 Direct Vent Fireplace#11 IPI Valve Assembly No longer available SOHO24B-ONYXLimited Lifetime Warranty Limited Lifetime WarrantyWarranty Conditions Contact Information