B. Assemble Slip Sections

Slide the inner flue of the slip section into the inner flue of the pipe section and the outer flue of the slip section over the outer flue of the pipe section. See Figure 8.3.

Slide together to the desired length.

Pilot hole

Figure 8.3 Slip Section Pilot Holes

Maintain a 1-1/2 in. (38 mm) overlap between the slip section and the pipe section.

Secure the pipe and slip section with two screws no longer than 1/2 in. (13 mm), using the pilot holes in the slip section. See Figure 8.4.

Figure 8.4 Screws into Slip Section

Continue adding pipe as necessary following instructions in “Assembling Pipe Sections.”

NOTICE: If slip section is too long, the inner and outer flues of the slip section can be cut to the desired length.

NOTICE: When installing a vent system with an HRC termination cap, all pipe system joints shall be sealed using a high temperature silicone sealant.

Apply a bead of silicone sealant inside the female outer pipe joint prior to joining sections.

Only outer pipes are sealed, sealing the inner flue is not required.

All unit collar, pipe, slip section, elbow and cap outer flues shall be sealed.

C. Secure the Vent Sections

Vertical runs of SLP pipe must be supported every 8 ft. (2.44 m).

Horizontal sections must be supported every 5 feet (1.52 m).

Vent supports or plumbers strap (spaced 120º apart) may be used to support. See Figures 8.5 and 8.6.

Wall shield firestops may be used to provide horizontal support.

SLP ceiling firestops have tabs that may be used to provide vertical support.

WARNING! Risk of Fire, Explosion or Asphyxiation! Improper support may allow vent to sag and separate. Use vent run supports and connect vent sections per installation instructions. DO NOT allow vent to sag below connection point to appliance.

Figure 8.5 Securing Vertical Pipe Sections

Figure 8.6 Securing Horizontal Pipe Sections

Heat & Glo • Soho24B • 2137-900 Rev. P • 8/12

23

Image 23
Contents Hot glass will cause burns Model Soho24BWhat to do if you smell gas Homeowner Reference Information CongratulationsTable of Contents Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsTools and Supplies Needed Installation to ensure maximum safety and benefitGetting Started Mantel Projections Framing and ClearancesSelecting Appliance Location Clearances Constructing the Appliance ChaseSee .4 for specific clearances Termination LocationsVent Termination Minimum Clearances Inches U.S.A Covered Alcove ApplicationsMeasuring Standards Vent Information and DiagramsVent Table Key Use of ElbowsMinimum Maximum Vent DiagramsTop Vent Horizontal Termination One Elbow Two ElbowsV1 Min H1 Max V2 Min H2 Max Top Vent Horizontal Termination Three ElbowsV1 Minimum H1 Maximum V1 + Top Vent Vertical Termination No ElbowV1 = 45 ft Max .72 m V1 = 3 ft Min mm V1 Minimum H1+ H2 Maximum V1+ V2 Minimum Top Vent Vertical Termination Three ElbowsCombustible Wall Penetration Vent Clearances and FramingPipe Clearances to Combustibles Wall Penetration FramingPipe SLP Vertical Penetration FramingVaulted Ceiling Installation Install Attic Insulation ShieldFlat Ceiling Installation Top Vent Appliance PreparationMaterial Installation of Non-combustible Facing MaterialProper Positioning, Leveling and Securing of a Securing and Leveling the ApplianceAssemble Vent Sections Installing Vent PipeSecure the Vent Sections Assemble Slip SectionsDisassemble Vent Sections Install Decorative Ceiling ComponentsAssemble and Install Storm Collar Install Metal Roof FlashingHeat Shield Requirements for Horizontal Termination Install Vertical Termination CapInstall Decorative Wall Components 17 Venting through the wall Install Horizontal Termination CapPressure Natural Gas Propane Gas InformationFuel Conversions Gas Connection Gas PressuresHigh Altitude Installations Electrical Information Recommendation for WireGRN wire Ground attached To GRN screw with Inside box Junction Box InstallationSee for combustible/non-combustible definitions FinishingFacing Material Painting Installation of Non-Combustible Facing MaterialsRemove Shipping Materials Appliance SetupClean the Appliance AccessoriesPositioning Stones Stone Placement Soho24BNo Stones in this Area Replacing Glass Assembly Glass AssemblyAir Shutter Setting Removing Glass AssemblyBefore Lighting Appliance Operating InstructionsFinal inspection by Lighting Instructions IPIAfter Appliance is Lit Frequently Asked QuestionsInitial Break-in Procedure Sympton Possible Cause Corrective Action TroubleshootingIntelliFire Ignition System Symptom Possible Cause Corrective Action Maintaining and Servicing Appliance Maintenance TasksRecommend addition of screen if one is not present Inspect Maintenance TasksLocation Inches Millimeter Appliance Dimension DiagramAppliance Dimensions Table Reference MaterialsSL Series Components Vent Components Diagrams B. Vent Components Diagrams Assembly 318 mm 356 mm 330 mm305 mm 12-1/224 x 24 Direct Vent Fireplace Service PartsStocked At Depot#11 IPI Valve Assembly No longer available SOHO24B-ONYXLimited Lifetime Warranty Limited Lifetime WarrantyWarranty Conditions Contact Information