Regency G36D installation manual Installation

Page 17

INSTALLATION

The G36D is approved for a maximum 37 ft. (11.3m) straight vertical, with Rigid

Pipe vent systems for Propane and Natural Gas, as per the diagram 3.

The shaded area in the diagram 3 shows all allowable combinations of straight vertical and offset to vertical terminations with Rigid Pipe vent systems for Propane and Natural Gas. Maximum two 45o elbows allowed.

• Vent must be supported at offsets

Firestops are required at each floor level and whenever passing through a wall.

• Maintain clearances to combustibles as listed in the "Clearances" section.

Diagram 3

UltraGlow® G36D Zero Clearance Direct Vent Gas Fireplace

17

Image 17
Contents 12/18/05 G36D Zero Clearance Direct Vent Gas FireplaceTo the New Owner Information for MOBILE/MANUFACTURED Homes After First SaleTable of Contents Copy of Safety Decal for G36D-NG1 Safety Label300 Certified for/Certifiée pour Canada and U.S.AInstallation Checklist InstallationImportant Message Save These Instructions Before YOU StartDiagram G36D Unit DimensionsLocating Your GAS Stove Manufactured Mobile Home Additional RequirementsFraming Finishing ClearancesMantel LEG Clearances Combustible Mantels Top Standoff Assembly Unit Assembly Prior to InstallationVenting Introduction Top Facing Support Side Nailing StripsExterior Vent Area where terminal is not permitedLocations Vertical TerminationVenting Secure Vent Rigid Pipe Venting Components ListAlternate Rigid Pipe Venting SystemsUltraGlow Direct Vent System Flex Rigid Pipe Venting Arrangements Horizontal TerminationsInstallation Rigid Pipe Venting Arrangements Vertical Terminations Installation Required Parts Vertical Termination With CO-LINEAR Flex SystemDescription Flex LinerVenting Arrangements Vertical Terminations Snorkel Terminations Diagram 3aI g h t Achieved Diagram Roof Pitch Firestop spacer must be installedCeiling to the position Continue to assemble pipe lengthsFor UltraGlow Direct Vent System Flex Installation ProceduresOffset Chart GAS Line Installation Pilot AdjustmentGAS Pipe Pressure Testing High ElevationLPG Conversion Kit Contains Installation of LPG Conversion KitQty DC Sparker Kit Contains QtySparker Ignitor Wire Ignitor WireGround Wire from Kit Piezo IgnitorChain Install the 1/2 bushing to the heat shieldHeat Shield 02-53 02-51 02-54 LOG SET Installation02-75 02-55 02-52 Log indentation 5th Grate TabRear Grate Tab Front BracketsPlace embers in these 3 locations On the burner tray Install fl ush glass as per instructions in manualOptional Flush Trim Standard Flush DoorFlush Louvers Wall Switch Remote ControlThermostat Wire Table Wall ThermostatDo not cut the ground terminal off under any circumstances Wiring DiagramOpen the bottom louver door Installing the Optional FANTo Remove the Fan Operating Instructions Normal Operating Sounds of GAS Appliances Maintenance InstructionsCopy of the Lighting Plate Instructions Maintenance Removing Valve Installing ValveG36D Main Assembly Pilot Assembly Gasket Parts ListG36D Flush Front Assembly UltraGlow G36D Zero Clearance Direct Vent Gas Fireplace UltraGlow G36D Zero Clearance Direct Vent Gas Fireplace Exclusions WarrantyConditions Register your UltraGlow online at