2.4Mains power connection between the DELTABOOSTER and the supply network (cf. Fig. 5)

All measurements and connections described below should be carried

out by authorized specialists !

1)The DELTABOOSTER should be connected to a three-phase mains supply at the rated voltage, cf. the model plate. Max. 125 Amp pre-fuses.

2)The connection should be established through a flexible rubber cable with 3 phase cores

and one earth conductor to be led through the sealing connection (2) and into the bottom of the switchboard through the open angle flange (3). The angle flange is opened by loosening two nuts. The cable should be connected direct at the main switch S1 and the main earth terminal (4). When the cable has been properly mounted in the main switch S1, the angle flange should be closed around the sealing connection (2) and the cable placed in the two cable reliefs (1).

The cable should be rated to the existing current consumption which has been stamped on the DELTABOOSTER model plate. It is advisable to apply a cable with a conductor cross section of minimum 25 in preparation for a later expansion.

3)It is also advisable to take additional precautionary measures to protect the user by installing a Residual Current Device (RCD) / Ground fault circuit interruptor (GFCI) in the DELTA- BOOSTER supply line.

4)Finally, check that fuses F1 - F2 and F3 (cf. wiring diagram) have been mounted in the re- tainers and that the overload cut-out Q1-Q? has been connected and set correctly (cf. C3K model plate).

5)With an appropriate measuring equipment the connection of earth cables from the outlet of the fixed installation to a metallic part on the high pressure outlet of the machine should be checked. The phase conductors of the supply cable should be subjected to a high voltage test with the main switch in off position.

At Nilfisk-ALTO the DELTABOOSTER has been tested on the above-mentioned items as a separate machine.

6)The door to the switchboard should be closed and locked. The system is now ready for run- ning in and function testing.

Fig. 5

2.Sealing connection

1.Cable reliefs

4.Main earth terminal

3.Angle flange

35

Image 35
Contents Deltabooster Deltabooster How to use the Deltabooster Layout of system Product DescriptionPage Model survey and main functions Deltabooster switchboardC3K pumps Selection of Spray Lance Selection of systemNumber of Pumps Line PressureIdentification of model Technical dataClassifica Control systemWater tank 2 C3K pumpNo. of pumps Model 44C3 Dimensions, weight and total performance per systemLocation of the Deltabooster Differential pressure of solenoid valve measured in bar Installation requirements for water connectionMax 125 a Installation requirements for mains power connectionDeltabooster control system Types of pipes standards Pipe systemLocation of pipelines/general instructions Fittings, standards TuyauteriePipingComponents RørledningskomponenterRohrleitungskomponenten-Elements Bezeichnung Designation DimensionRohrhalterung tuyauSupport Bezeichnung DesignationdimensionKobber Copper Rohrleitungskomponenten-ElementsDimensioning of pipe systems Page Bar ExamplesExample 50 m 40 m 70 m Pressure DropDrop Example 60 m30 m 10 m M 80 m PressureBar 10 bar Example 20 m 40 m 30 m 60 m 30 m 15 m 80 mRing system Compensation Temperature compensationMounting requirements and hints Bends/hose connectionsMounting of Pipe LINES/GENERAL Instructions Fixation AT Corners and TEE ConnectorsRemounting Mounting in Connection SocketOutlet Station Outlet points and accessoriesDetachable foam injector AccessoriesBar grey nozzle protection Multipressure spray lance systemBar black nozzle protection Location Sketch Mounting base Filter Connection of inlet waterControl of filter in water tank Page Venting of pumps Starting up/runningOil control StartVenting of pipe system Adjustment of line pressureSave these instructions for later How to use the DeltaboosterSafety Do not Interfere with this SettingModel survey Functional diagram Instrument panel Main / emergency switchControl switch / starting switch and stopping switch Control panel Setting and reading of Deltabooster On 50C Setting of water temperatureBoth should be on for the operation of a single plant Connection and disconnection of C3K pumpsReading of hour meters Starting up/running in cf. Fig Page Multipressure spray lance system Operation after starting up Operation after starting up outlet points and equipmentAfter use Admixture of detergentsGeneral guidelines for the dosage of detergents Couplings MaintenanceService intervals/oil change Water filterProblem Possible cause Correction Trouble-shooting and possible correctionPortugal 7309021