Nilfisk-ALTO 7309021 Example 20 m 40 m 30 m 60 m 30 m 15 m 80 m, Ring system, Bar 10 bar

Page 25

Example 3

20 m

 

 

 

40 m

 

 

 

 

20 m

 

 

 

 

 

 

 

 

c1

b1

a1

 

 

 

 

 

 

 

 

 

 

 

30 m

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

60 m 30 m

 

 

 

 

 

 

 

 

 

 

 

 

15 m

 

 

 

 

 

 

 

 

 

 

 

c2

 

 

 

 

 

 

20 m

 

 

 

30 m

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

b2

a2

 

 

20 m

 

 

 

 

 

 

40 m

 

 

 

20 m

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

80 m

 

 

 

 

 

 

M

Ring system

Selection of spray lance: 2 green spray lances each of 33 l/min 2 blue spray lances each of 17 l/min

If the maximum load is distributed evenly and symmetrically the maximum load on line b1 - c1 = 33 l/min.

If 15 mm pipe is selected 35 m pipes will result in a pressure drop of:

Maximum load on line M-a1 + a1-b1= 50 l/min.

If 90 m 22 mm pipe is used the resulting pressure drop will be:

Total pressure drop

PRESSURE DROP 6 bar

4bar

10 bar

This means that 22 mm pipe is to be used from the pumps to outlet points b1 and b2 and 15 mm for the rest.

The examples show different ways of installing the pipe system.What to prefer in each individual case highly depends on the building where it is to be located and special requirements, if any. Due regard should be paid to the fact that big pipe dimensions and units are considerably more expensive, and the financial costs of each solution should therefore always be compared to one another.

25

Image 25
Contents Deltabooster Deltabooster How to use the Deltabooster Layout of system Product DescriptionPage Model survey and main functions Deltabooster switchboardC3K pumps Number of Pumps Selection of systemLine Pressure Selection of Spray LanceIdentification of model Technical dataWater tank Control system2 C3K pump ClassificaNo. of pumps Model 44C3 Dimensions, weight and total performance per systemLocation of the Deltabooster Differential pressure of solenoid valve measured in bar Installation requirements for water connectionDeltabooster control system Installation requirements for mains power connectionMax 125 a Location of pipelines/general instructions Pipe systemTypes of pipes standards PipingComponents TuyauterieRørledningskomponenter Fittings, standardsRohrleitungskomponenten-Elements Bezeichnung Designation DimensionRohrhalterung tuyauSupport Bezeichnung DesignationdimensionKobber Copper Rohrleitungskomponenten-ElementsDimensioning of pipe systems Page Example 50 m 40 m 70 m ExamplesPressure Drop Bar30 m 10 m M 80 m Example 60 mPressure DropRing system Example 20 m 40 m 30 m 60 m 30 m 15 m 80 mBar 10 bar Mounting requirements and hints Temperature compensationBends/hose connections CompensationMounting of Pipe LINES/GENERAL Instructions Fixation AT Corners and TEE ConnectorsRemounting Mounting in Connection SocketOutlet Station Outlet points and accessoriesDetachable foam injector AccessoriesBar black nozzle protection Multipressure spray lance systemBar grey nozzle protection Location Sketch Mounting base Control of filter in water tank Connection of inlet waterFilter Page Oil control Starting up/runningStart Venting of pumpsVenting of pipe system Adjustment of line pressureSafety How to use the DeltaboosterDo not Interfere with this Setting Save these instructions for laterModel survey Functional diagram Control switch / starting switch and stopping switch Main / emergency switchInstrument panel Control panel Setting and reading of Deltabooster On 50C Setting of water temperatureBoth should be on for the operation of a single plant Connection and disconnection of C3K pumpsReading of hour meters Starting up/running in cf. Fig Page Multipressure spray lance system Operation after starting up Operation after starting up outlet points and equipmentAfter use Admixture of detergentsGeneral guidelines for the dosage of detergents Service intervals/oil change MaintenanceWater filter CouplingsProblem Possible cause Correction Trouble-shooting and possible correctionPortugal 7309021