Crown Boiler CWI310, CWI172, CWI345, CWI103, CWI276, CWI Series, CWI069 XI Service and Maintenance

Page 35
XI Service and Maintenance

XI Service and Maintenance

The following routine maintenance should be performed on an annual basis:

1)Turn off electrical power and gas supply to the boiler

2)Inspect the flue passages for signs of blockage. If there is any carbon in the combustion chamber or the flue passages, clean the heat exchanger before proceeding further. See the cleaning procedure below.

3)Remove any debris found in the combustion chamber, being careful not to disturb combustion chamber insulation.

4)Remove all burners, noting the location of the pilot main burner. If burners show signs of deterioration, they should be replaced (some discoloration around the burner ports is normal). Clean the burners by first brushing the ports with a soft bristle brush and then vacuuming out any debris through the venturi opening.

5)Inspect the pilot assembly:

Standing Pilots - Check the thermocouple for deterioration (some discoloration of the thermocouple is normal). If any deterioration is present, replace the thermocouple. Inspect the pilot assembly for deposits and deterioration. Clean or replace the pilot assembly as necessary.

Intermittent Pilots - Clean any deposits found on the electrode and grounding strap. The ideal gap between the electrode and the ground strap is 1/8”. Inspect the porcelain for cracks or other deterioration. Replace pilot assembly if deterioration is found.

6)Inspect the combustion chamber insulation for deterioration.

7)(Intermittent Pilot Boilers) - Inspect the ignition cable insulation for cracks or other deterioration. If deterioration is found, replace cable.

8)Reinstall burners, being careful to put the pilot main burner in its original location.

9)Inspect all boiler wiring for loose connections or deterioration.

CAUTION

LABEL ALL WIRES PRIOR TO DISCONNECTION WHEN SERVICING CONTROLS. WIRING ERRORS CAN CAUSE IMPROPER AND DANGEROUS OPERATION. VERIFY PROPER OPERATION AFTER SERVICING.

10)Inspect the vent system:

Make sure that the vent system is free of obstructions.

Make sure that all vent system supports are intact.

Inspect joints for signs of condensate or flue gas leakage.

Inspect venting components for corrosion or other deterioration. Replace any defective vent components.

11)Inspect the boiler and hydronic system for leaks.

CAUTION

WATER LEAKS CAN CAUSE SEVERE CORROSION DAMAGE TO THE BOILER OR OTHER SYSTEM COMPO- NENTS. REPAIR ANY LEAKS FOUND IMMEDIATELY.

12)Place the boiler back in operation using the procedure outlined in “Start-up”. Check the pilot line and any other gas piping disturbed during the inspection process for leaks.

35

34

Image 35
Contents These instructions must be affixed on or adjacent to the boiler Gas-Fired Natural Draft Water Boilers INSTALLATION INSTRUCTIONSCWI Series ModelsI Product Description Table of ContentsTABLE 1 CWI SPECIFICATIONS II SpecificationsFIGURE 1 CWI BOILERS - GENERALCONFIGURATION IV Locating the Boiler III Before InstallingV Air for Combustion and Ventilation Example For Buildings of Other than Unusually Tight ConstructionForBuildingsofUnusuallyTightConstruction FIGURE 5 ALL AIR FROM OUTDOORS VIA VENTILATED ATTIC FIGURE3BOILERINSTALLEDINCONFINEDSPACE, ALL AIR FROM INSIDEFIGURE 4 ALL AIR FROM OUTDOORS, VENTILATED CRAWL SPACE AND ATTIC FIGURE 6 ALL AIR FROM OUTDOORS, USING OPENINGS INTO BOILER ROOM VI Venting Removing an Existing Boiler from a Common Chimney FIGURE 9 VENT DAMPER INSTALLATION DETAILS FIGURE8 CWI BOILERTYPICALVENTSYSTEM INSTALLATION AND COMPONENTSVII Gas Piping DANGER VIII System PipingStandardPiping Piping for Special Situations 1413BOILERSIDEPIPING FIGURE 11 STANDARD BOILER PIPING FIGURE 12 INDIRECT WATER HEATERFIGURE13 BOILERBYPASSPIPING FIGURE15 BOILERPIPINGWITHCHILLER FIGURE14 ISOLATIONOFBOILERFROMSYSTEMWITHAHEATEXCHANGERIX TANKLESS HEATER PIPING FIGURE 17TANKLESSHEATERPIPING A mixing valve does not eliminate the risk of scaldingFeel water before showering or bathing SingleZoneWiring IX WiringFIGURE 20 WIRING DIAGRAM, STANDING PILOT WITH TANKLESS HEATER Wiring Variations FACTORYWIRING NOT SHOWN - SEE FIGURES 18 FIGURE 22 CIRCULATOR ZONEWIRING USING HONEYWELLR845AsFACTORY BOILER WIRING NOT SHOWN - SEE FIGURES 18 FIGURE23ZONEWIRINGUSINGHONEYWELLV8043FZONEVALVESSequence of Operation, Standing Pilot, With Tankless Heater CWI Control System - Sequence of OperationSequence of Operation, Standing Pilot, Less Tankless Heater Sequence of Operation, Intermittent Ignition, With Tankless Heater Sequence of Operation, Intermittent Ignition, Less Tankless HeaterSafety Control Operation - Standing Pilot and Intermittent Ignition XI Start-up and CheckoutFIGURE 24 STANDING PILOT BURNER FLAME 2726Page Page LIGHTING INSTRUCTIONS FOR BOILERS EQUIPPED WITH HONEYWELL FOR YOUR SAFETY READ BEFORE OPERATINGLIGHTING INSTRUCTIONS TO TURN OFF GAS TO APPLIANCE7000ERHC SERIES GAS VALVES STANDING PILOT FOR YOUR SAFETY READ BEFORE LIGHTINGLIGHTING INSTRUCTIONS FOR BOILERS EQUIPPED WITH ROBERTSHAW VR8204 AND VR8304 SERIES GAS VALVES INTERMITTENT PILOT FOR YOUR SAFETY READ BEFORE LIGHTINGOPERATING INSTRUCTIONS TO TURN OFF GAS TO APPLIANCE7000DERHC SERIES GAS VALVES INTERMITTENT PILOT FIGURE 28b GASVALVEDETAIL-ROBERTSHAW 7000DERHC INTERMITTENT IGNITION FIGURE 27a GASVALVEDETAIL-HONEYWELLVR8200ORVR8300STANDINGPILOTXI Service and Maintenance Heat Exchanger Cleaning Procedure XIII Troubleshooting C1&C2? STARTNational Fuel Gas Code 5&6 onL2 ? STARTC2 and C1&C2?T&TV? Caution Read page 36 before attempting to use this chart Standing Pilot Ignition System Troubleshooting ChartIntermittent Ignition System Troubleshooting Chart XIV PARTS Page 40mm BURNERS ONLY These Valves Piped in Series to Provide Redundent Shut-off1/4 Pilot Tubing Used with Robertshaw Valves Page KEY # Page C. Heat Exchanger and Flue Collector Installation Appendix A Knockdown Boiler Assembly InstructionsA. Before Installing B. BaseAssembly PreparationFIGUREA1 BASE, HEAT EXCHANGER, FLUE COLLECTORASSEMBLY E. Control and Trim Installation D. Gas Valve InstallationFIGURE A2 JACKET INSTALLATION G. Complete Installation F. Electrical Wiring ConnectionsFIGURE A3 TAPPING LOCATIONS SEE TEXT FOR TAPPING USES Philadelphia P.O. Box3633 I. Street