side panel installed in the previous step and secure with three #10 sheet metal screws.
5)Install the left side panel in the same manner as the right side.
6)Attach the front corners of the diverter panel to the side jacket panels using #10 sheet metal screws.
7)Install the horizontal (angle) jacket clips in the front edge of the side jacket panels. Slide this clip through the rectangular slot that is about halfway up the front edge of the side jacket panels and secure with the
8)Slip the Vertical Jacket Clip through the rectangular slot that is near the bottom of the front edge of the side jacket panels. Secure with the
9)Install the top jacket panel. Use #10 sheet metal screws to attach it to the rear jacket panel and the
10)Install the
11)Attach the door knobs to the
12)The labels have been applied at the factory. Verify the location of the labels according to the list below:
a)Clearance Label - Located on the top jacket panel.
b)Lighting Instructions - Located on the lower left corner of the right side panel next to the gas manifold
c)Lowest Permissible Water Level Plate - Located next to the bottom water gauge tapping.
d)Blow Down Card - Located just above the "Lowest Permissible" Water Level Plate
e)Wiring Diagram - Located on the inside of the removable door
f)"CROWN" Nameplate - Located on the top center of the outside of the removable door
g)Rating Plate - Located on the upper left of the right side panel
D.Gas Valve Installation
1)The gas valve assembly has been
2)Connect the pilot tubing from the pilot burner to the gas valve pilot tapping.
3)Connect the thermocouple lead to the gas valve (standing pilot boilers only).
E. Control and Trim Installation
(Refer to Figure A3 for Tapping Locations)
1)Install the tankless heater or blank cover plate on the opening on the right side of the heat exchanger using the gasket and 3/8 bolts provided.
2)Install the high limit well in the tapping in the tankless heater or cover plate.
3)Mount the limit control (L8148E or L8124E) onto the control well. Be sure that the temperature sensing bulb is bottomed out in the well. Tighten the screw on the bottom of the control so that it is securely clamped onto the well.
4)Install a 1/2 x 1/4 bushing and the tridicator gauge into tapping “C”. Tighten with wrench applied to the square shank on the back of the gauge. Do not apply pressure on the gauge case since this may ruin the calibration of the gauge.
5)Install relief valve (spindle must be in vertical position) into tapping “H” on the boiler left side (See Figure 1 in the installation manual) using the ¾” NPT nipples and elbow supplied. Pipe the discharge of the safety relief valve to a location where water or steam will not create a hazard or cause property damage if the valve opens. The end of the discharge pipe must terminate in an unthreaded pipe. The safety valve discharge piping must be in an area where it is not likely to become plugged by debris or subjected to freezing.
6)Install the
52