NATURAL GAS

 

PROPANE / BUTANE

 

 

FLUEING WITH THREE 90° ELBOWS

FLUEING WITH THREE 90° ELBOWS

 

V + V1

(FT.)

H + H1 (FT.)

V + V1 (FT.)

H + H1 (FT.)

 

1' MIN. (305mm)

3' MAX. (914mm)

1' MIN. (305mm)

2' MAX. (610mm)

 

2' MIN. (610mm)

6' MAX.

(1.83m)

2' MIN. (610mm)

4' MAX.

(1.22m)

 

3' MIN. (914mm)

9' MAX.

(2.7m)

3' MIN. (914mm)

6’ MAX. (1.83m)

 

4' MIN. (1.22m)

12' MAX.

(3.6m)

4' MIN. (1.22m)

8' MAX.

(2.4m)

 

V+ V1 + H + H1 = 36’ MAX. (10.9m)

V+ V1 + H + H1 = 36’ MAX. (10.9m)

 

 

H + H1 = 12’ MAX. (3.6m)

 

H + H1 = 8’ MAX. (2.4m)

 

 

 

 

H1

 

 

 

 

 

 

 

 

 

V1

 

 

 

 

 

 

 

 

 

V

 

 

 

 

 

H

 

 

 

V1

 

 

 

 

 

 

 

 

 

 

 

 

NATURAL GAS

 

 

 

 

 

 

FLUEING WITH THREE 90° ELBOWS

 

 

 

 

 

V + V1 (FT.)

H + H1 (FT.)

 

 

 

 

 

1' MIN. (305mm)

3' MAX. (914mm)

 

 

 

 

 

2' MIN. (610mm)

6' MAX.

(1.83m)

 

 

 

 

 

3' MIN. (914mm)

9' MAX.

(2.7m)

H1

 

 

 

 

4' MIN. (1.22m)

12' MAX.

(3.6m)

 

 

 

V

5’ MIN. (1.5m)

15’ MAX.

(4.5m)

 

 

H

 

 

 

 

 

V+ V1 + H + H1 = 36’ MAX. (10.9m)

 

 

 

 

 

 

 

 

 

 

H + H1 = 15’ MAX. (4.5m)

 

 

 

 

 

 

PROPANE / BUTANE

 

 

 

 

 

 

FLUEING WITH THREE 90° ELBOWS

 

 

 

 

 

V + V1 (FT.)

H + H1 (FT.)

 

 

 

 

 

1' MIN. (305mm)

2' MAX. (610mm)

 

 

 

 

 

2' MIN. (610mm)

4' MAX.

(1.22m)

 

 

 

 

 

3' MIN. (914mm)

6’ MAX. (1.83m)

 

 

 

 

 

4' MIN. (1.22m)

8' MAX.

(2.4m)

 

 

 

 

 

5’ MIN. (1.5m)

10' MAX.

(3.0m)

 

 

 

 

 

V+ V1 + H + H1 = 36’ MAX. (10.9m)

 

 

 

 

 

H + H1 = 10’ MAX. (3.0m)

 

Figure 16. Flueing with three 90° elbows

 

 

 

 

 

26

Heat & Glo • PIER/ST/L&RCOR-HVB-CE2068-900 Rev. H • 6/07

 

 

Image 26
Contents 0087 Safety and Warning Information Table of Contents PIER-HVB-CE NG, LP Exploded Parts Diagram PIER-HVB-CEST-HVB-CE ST-HVB-CE LCOR-HVB-CE LCOR-HVB-CE RCOR-HVB-CE RCOR-HVB-CE Valve Assembly RCOR-HVB-CE ÍAppliance Certification Installation RegulationsPre-install Preparation CertificationDiagram of the PIER-HVB-CE Heat & Glo PIER/ST/L&RCOR-HVB-CE 2068-900 Rev. H 6/07Diagram of the ST-HVB-CE Diagram of the LCOR-HVB-CE and RCOR-HVB-CE Framing the Fireplace Fireplace Dimensions and LocationsLocating the Fireplace Clearance RequirementsModel AT Each Joint Identifying Flue Components Installing the Flue SystemFlue System Approvals Terminations KitsStraight OUT Horizontalflueing Max. RunFlueing with One 90 Elbow Flueing with Two 90 Elbows Propane / Butane Flueing with TWO 90 Elbows Flueing with three 90 elbows + H1 FT + V1 FT Installing Flue Components Attach the First Flue Component to the Starting CollarsCombustibles inside the framed firestop opening Install Support BracketsContinue Adding Flue Components Ceiling Firestop Ceiling Side Trapezoid Termination CapMinimum Height from Roof to Lowest Discharge Opening Vent Termination Minimum Clearances Securing of a Fireplace Positioning, Leveling, and Securing the FireplaceGas Control System Natural Gas Gas Supply LineGas Pressure Requirements Wall Switch Wiring the FireplaceOptional Accessories FinishingInstalling the Trim Installing Trim, Logs & Ember MaterialLog placement Attachment of Lower Door AssemblyHeat & Glo PIER/ST/L&RCOR-HVB-CE 2068-900 Rev. H 6/07 Heat & Glo PIER/ST/L&RCOR-HVB-CE 2068-900 Rev. H 6/07 3 4 Only for Model LCOR-HVB-CEHeat & Glo PIER/ST/L&RCOR-HVB-CE 2068-900 Rev. H 6/07 Heat & Glo PIER/ST/L&RCOR-HVB-CE 2068-900 Rev. H 6/07 Before Lighting the Fireplace After the InstallationDouble-check for faulty components Lighting the FireplaceReplacing old ember material Fireplace MaintenanceCleaning Glass Door Checking Flame Patterns, Flame Height5Troubleshooting Troubleshooting Be Placed in this Opening