Carrier XRV, 19XR specifications

Page 41

NOTE: The lead/lag function can be configured on the LEAD- LAG screen, which is accessed from the SERVICE menu and EQUIPMENT SERVICE table. See Table 2, Example 20. Lead/lag status during chiller operation can be viewed on the LL_MAINT display screen, which is accessed from the SER- VICE menu and CONTROL ALGORITHM STATUS table. See Table 2, Example 12.

Lead/Lag System Requirements:

all chillers in the system must have software capable of performing the lead/lag function

water pumps MUST be energized from the PIC II controls

water flows should be constant

the CCN time schedules for all chillers must be identical

Operation Features:

2 chiller lead/lag

addition of a third chiller for backup

manual rotation of lead chiller

load balancing if configured

staggered restart of the chillers after a power failure

chillers may be piped in parallel or in series chilled water flow

COMMON POINT SENSOR INSTALLATION — Lead/lag operation does not require a common chilled water point sen- sor. Common point sensors (Spare Temp #1 and #2) can be added to the CCM module, if desired. Spare Temp #1 and #2 are wired to plug J4 terminals 25-26 and 27-28 (J4 lower, respectively).

NOTE: If the common point sensor option is chosen on a chilled water system, each chiller should have its own common point sensor installed. Each chiller uses its own common point sensor for control when that chiller is designated as the lead chiller. The PIC II cannot read the value of common point sen- sors installed on the other chillers in the chilled water system.

If leaving chilled water control (ECW CONTROL OPTION is set to 0 [DSABLE] TEMP_CTL screen) and a common point sensor is desired (COMMON SENSOR OPTION in LEADLAG screen selected as 1) then the sensor is wired in Spare Temp #1 position on the CCM.

If the entering chilled water control option (ECW CON- TROL OPTION) is enabled (configured in TEMP_CTL screen) and a common point sensor is desired (COMMON SENSOR OPTION in LEADLAG screen selected as 1) then the sensor is wired in Spare Temp #2 position on the CCM.

When installing chillers in series, a common point sensor should be used. If a common point sensor is not used, the leav- ing chilled water sensor of the upstream chiller must be moved into the leaving chilled water pipe of the downstream chiller.

If return chilled water control is required on chillers piped in series, the common point return chilled water sensor should be installed. If this sensor is not installed, the return chilled water sensor of the downstream chiller must be relocated to the return chilled water pipe of the upstream chiller.

To properly control the common supply point temperature sensor when chillers are piped in parallel, the water flow through the shutdown chillers must be isolated so no water by- pass around the operating chiller occurs. The common point sensor option must not be used if water bypass around the oper- ating chiller is occurring.

CHILLER COMMUNICATION WIRING — Refer to the chiller’s Installation Instructions, Carrier Comfort Network Interface section for information on chiller communication wiring.

LEAD/LAG OPERATION — The PIC II not only has the ability to operate 2 chillers in lead/lag, but it can also start a designated standby chiller when either the lead or lag chiller is faulted and capacity requirements are not met. The lead/lag op- tion only operates when the chillers are in CCN mode. If any other chiller configured for lead/lag is set to the LOCAL or OFF modes, it will be unavailable for lead/lag operation.

Lead/Lag Chiller Configuration and Operation

A chiller is designated the lead chiller when its LEADLAG: CONFIGURATION value on the LEAD- LAG screen is set to “1.”

A chiller is designated the lag chiller when its LEADLAG: CONFIGURATION value is set to “2.”

A chiller is designated as a standby chiller when its LEADLAG: CONFIGURATION value is set to “3.”

A value of “0” disables the lead/lag designation of a chiller.

To configure the LAG ADDRESS value on the LEADLAG screen, always enter the address of the other chiller on the sys- tem. For example, if you are configuring chiller A, enter the ad- dress for chiller B as the lag address. If you are configuring chiller B, enter the address for chiller A as the lag address. This makes it easier to rotate the lead and lag chillers.

If the address assignments in the LAG ADDRESS and STANDBY ADDRESS parameters conflict, the lead/lag func- tion is disabled and an alert (!) message displays. For example, if the LAG ADDRESS matches the lead chiller’s address, the lead/lag will be disabled and an alert (!) message displayed. The lead/lag maintenance screen (LL_MAINT) displays the message ‘INVALID CONFIG’ in the LEADLAG: CONFIGU- RATION and CURRENT MODE fields.

The lead chiller responds to normal start/stop controls such as the occupancy schedule, a forced start or stop, and remote start contact inputs. After completing start-up and ramp load- ing, the PIC II evaluates the need for additional capacity. If ad- ditional capacity is needed, the PIC II initiates the start-up of the chiller configured at the LAG ADDRESS. If the lag chiller is faulted (in alarm) or is in the OFF or LOCAL modes, the chiller at the STANDBY ADDRESS (if configured) is requested to start. After the second chiller is started and is running, the lead chiller monitors conditions and evaluates whether the ca- pacity has been reduced enough for the lead chiller to sustain the system alone. If the capacity is reduced enough for the lead chiller to sustain the CONTROL POINT temperatures alone, then the operating lag chiller is stopped.

If the lead chiller is stopped in CCN mode for any reason other than an alarm (*) condition, the lag and standby chillers are also stopped. If the configured lead chiller stops for an alarm condition, the configured lag chiller takes the lead chill- er’s place as the lead chiller, and the standby chiller serves as the lag chiller.

If the configured lead chiller does not complete the start-up before the PRESTART FAULT TIMER (a user-configured value) elapses, then the lag chiller starts and the lead chiller shuts down. The lead chiller then monitors the start request from the acting lead chiller. The PRESTART FAULT TIMER is initiated at the time of a start request. The PRESTART FAULT TIMER provides a timeout if there is a prestart alert condition that prevents the chiller from starting in a timely manner. The PRESTART FAULT TIMER parameter is on the LEADLAG screen, which is accessed from the EQUIPMENT SERVICE table of the SERVICE menu.

If the lag chiller does not achieve start-up before the PRE- START FAULT TIMER elapses, the lag chiller stops, and the standby chiller is requested to start, if configured and ready.

41

Image 41
Contents Safety Considerations Start-Up, Operation, and Maintenance InstructionsContents Contents Abbreviations and Explanations Introduction19XR Identification Chiller FamiliarizationTypical 19XR Components Motor and Lubricating OIL Cooling Cycle Refrigeration CycleLubrication Cycle VFD Cooling CycleUnit-Mounted Solid-State Starter Optional Starting EquipmentDefinitions Unit-Mounted Wye-Delta Starter OptionalControls Variable Frequency Drive VFD 19XR Controls and Sensor Locations PIC II Component Panel Location Major PIC II Components Panel LocationsControl Panel CVC/ICVC Operation and Menus Fig Example of Status Screen 19XR Chiller Display Menu Structure CVC/ICVC 19XR Service Menu Structure Time and Date Example of Time Schedule Operation Screen Example of Set Point Screen CVC/ICVC Display Data Example 1 Chiller Display Default ScreenDescription Status Units Point Example 2 Maintstat Display ScreenExample 3 Startup Display Screen Startup Description Status Units PointExample 5 Heatex Display Screen Example 4 Compress Display ScreenExample 7 Ismstat Display Screen Example 6 Power Display ScreenExample 8 CVC/ICVCPSWD Display Screen Menu Setpoint Select Description Status Units Point DefaultCVC Icvc Description Status Units Point Example 9 Setpoint Display ScreenExample 12 Llmaint Display Screen Example 11 Override Display ScreenControl Algorithm Status Override Description Units Point Control Algorithm Status Wsmdefme Description Units Point Example 13 Ismhist Display ScreenExample 14 Wsmdefme Display Screen Ismconf Description Status Units Point Default ISM Starter Config DataExample 15 Netopt Display Screen Example 16 Ismconf Display ScreenExample 17 Options Display Screen Example 18 SETUP1 Display ScreenSpare ALERT/ALARM Enable LAG=2, STANDBY=3 Example 19 SETUP2 Display ScreenExample 20 Leadlag Display Screen Reset Type Description Status Units Point DefaultExample 21 Rampdem Display Screen Example 22 Tempctl Display ScreenSurge Prevention Mode occurs when Active Delta T Normal Control mode occurs when Active Delta TMode IGV VFD PIC II System FunctionsPage Protective Safety Limits and Control Settings Page Capacity Overrides Evaporator Freeze Protection Icvc only a Page Head Pressure Reference Output Surge Protection Fixed Speed ChillerPage Page Point Example of Attach to Network Device Screen Example of Holiday Period Screen START-UP/SHUTDOWN Default CVC/ICVC screen, press the MenuRecycle Sequence Fig Local Start-Up Local start-up or a manual start-up isEntering Condenser Water temperature plus 3 F -1.6C Equipment Required Before Initial START-UPJob Data Required 19XR Leak Test Procedures Page Page Temperature Pressure HFC-134a Pressure Temperature FHFC-134a Pressure Temperature C Perform dehydration as follows Inspect WiringWhite G Check StarterManufacturer Cable no Software Configuration Parameter Benshaw RediStart Micro Menu Items Verify VFD Configuration and Change Parameters if Necessary Description Settings VFD Title Setting ParameterDescription Setting Press Menu Press Status Press Compress Press Select Press Status Press Compress Press SelectLoad Surge Prevention Occurs TOO Soon Occurs TOO Late Estimated Minimum Load ConditionsCCM Temperature Thermistors Tests to be Devices Tested Performed Charge Refrigerant into ChillerControl Test Menu Functions Refrigerant HFC-134a Charge Initial START-UPCheck Oil Pressure and Compressor Stop Dry Run to Test Start-Up SequenceCheck Motor Rotation Operator Duties Operating InstructionsTo Start the Chiller To Stop the ChillerOperating the Optional Pumpout Unit Pumpout and Refrigerant Transfer ProceduresTime Date Cooler Condenser CompressorBearing FLAValve Condition Turn off pumpout condenser waterChillers with Isolation Valves Test After Service, Repair, or Major Leak If General MaintenanceGuide Vane Actuator Linkage Weekly MaintenanceCheck Safety and Operating Controls Monthly Scheduled MaintenanceInspect the Heat Exchanger Tubes and Flow Devices Compressor Bearing and Gear MaintenanceOptional Pumpout System Controls Ordering Replacement Chiller Parts WhenChecking Pressure Transducers Troubleshooting GuideOccdefcm HeatexLlmaint Shutdown in Progress Terminate Pumpdown ModeICE Build Ready to StartAlert PrestartAutorestart in Progress Running Temp ControlRUN Capacity FaultLimited SensorFailure to ProtectiveStart StopCommunication LossPotential FREEZE-UPLOW OIL Pressure Sensor AlertAutorestart PendingRecycle Pressure AlertOption Sensor DiffuserDrop Thermistor Temperature F vs. Resistance/Voltage DropTemperature PIC Resistance Thermistor Temperature C vs. Resistance/Voltage DropControl Modules Power is connected to Plug J1 on each moduleReplacing Defective Processor Modules Chiller Control Module CCM FigIntegrated Starter Module Fig Integratedstartermodule Checked Measure SCR Pairs Recorded Being BetweenNumber of Tubes English Code Heat Exchanger Data EnglishNumber of Tubes Code Heat Exchanger Data SI19XR Additional Data for Marine Waterboxes Compressor WeightsEnglish Motor 19XR Motor Weights Standard and High Efficiency Motors19XR Waterbox Cover Weights English lb 19XR Waterbox Cover Weights SI kg Motor Voltage Code Additional Miscellaneous WeightsOptional Pumpout System Electrical Data Description Torque Compressor Assembly TorquesCompressor Code View B High Speed Shaft 19XR Compressor ClearancesAllen-Bradley Wye-Delta Unit-Mounted Starter 100101 ISM 102Temp 103104 105 106 107 Power Panel Wiring Schematic108 Cutler-Hammer Wye Delta Unit Mounted Starter Sizes 3-5DP109 Cutler-Hammer Wye Delta Unit Mounted Starter Size 6DPSeparate Metering Option Ground Fault Phase Current Option111 AUX 112FU Fuse 113114 VFD 115116 Typical Variable Frequency Drive VFD Wiring Schematic117 118 119 120 121 122 Index Index JOB Data Required Remove and use for job fileCL-2 Inspect Wiring and Record Electrical Data Ratings10 to 40 to 10060.0 15 toCL-4 460 200 to105 to 115 85 to50 to 30 to20 to Psi CL-690 to 150 to125 125 toAmp 250 CL-8 65 to90 to 100 CL-9 25 toCL-10 50 to 1450200 0000 to0000 to 0200 CL-11004 To H.022 Job Sheet 60 for 60 Hz and 50 for 50 Hz 002 Power Module Dependent Selected motor 100% amps028 10 to Job Sheet 60 for 60 Hz and 50 for 50 Hz 000 100 to Selected line voltageCL-13 CL-14 CCN Local ResetPage Incurring obligations
Related manuals
Manual 40 pages 46.08 Kb

19XR, XRV specifications

The Carrier 19XR and 19XRV chillers are sophisticated cooling solutions that represent the forefront of HVAC technology. Designed for large commercial and industrial applications, these chillers provide exceptional performance, energy efficiency, and reliability, making them ideal for a variety of environments ranging from hospitals to manufacturing facilities.

One of the most significant features of the Carrier 19XR and 19XRV chillers is their advanced scroll compressor technology. These units employ a tandem scroll design that enhances efficiency while minimizing operational noise. This makes them ideal for urban environments where noise restrictions may be in place. Moreover, the compressors are equipped with variable speed drive options in the 19XRV model, which allows for greater energy savings by adjusting cooling output based on real-time demand.

In addition to their advanced compressors, the 19XR and 19XRV units incorporate the Carrier GreenChoice refrigerant, which has a lower global warming potential compared to traditional refrigerants. This innovative choice not only meets regulatory requirements but also contributes to sustainability goals, making these chillers a responsible choice for environmentally conscious organizations.

The units are engineered with a robust heat exchanger design, which enhances heat transfer efficiency and overall system performance. This ensures optimal operation even in extreme conditions. They feature a microprocessor-based control system that allows for precise monitoring and control of the chiller’s performance, enabling operators to make real-time adjustments to maximize energy efficiency.

The Carrier 19XR and 19XRV chillers also prioritize serviceability. The design incorporates easy access to key components, simplifying maintenance procedures and reducing downtime. This focus on maintainability extends the lifespan of the equipment, leading to lower lifecycle costs.

In terms of connectivity, these chillers are equipped with advanced Building Management System (BMS) integration capabilities. This allows for seamless monitoring and control of the chillers using a centralized platform, facilitating energy management and operational optimization.

Overall, the Carrier 19XR and 19XRV chillers stand out in the market for their blend of cutting-edge technology, energy efficiency, and user-friendly features. They are engineered to meet the demanding needs of modern commercial and industrial applications, making them a preferred choice for facility managers seeking reliable cooling solutions.