Carrier 19XR Operating Instructions, Operator Duties, To Start the Chiller, To Stop the Chiller

Page 66

OPTIONAL PUMPOUT STORAGE TANK AND PUMP- OUT SYSTEM — Transfer valves and pumpout system, refrig- erant charging and pumpdown procedure, and relief devices.

MOTOR COMPRESSOR ASSEMBLY — Guide vane actu- ator, transmission, motor cooling system, oil cooling system, temperature and pressure sensors, oil sight glasses, integral oil pump, isolatable oil filter, extra oil and motor temperature sen- sors, synthetic oil, and compressor serviceability.

MOTOR COMPRESSOR LUBRICATION SYSTEM — Oil pump, cooler filter, oil heater, oil charge and specification, operating and shutdown oil level, temperature and pressure, and oil charging connections.

CONTROL SYSTEM — CCN and LOCAL start, reset, menu, softkey functions, CVC/ICVC operation, occupancy schedule, set points, safety controls, and auxiliary and optional controls.

AUXILIARY EQUIPMENT — Starters and disconnects, separate electrical sources, pumps, and cooling tower.

DESCRIBE CHILLER CYCLES — Refrigerant, motor cooling, lubrication, and oil reclaim.

REVIEW MAINTENANCE — Scheduled, routine, and ex- tended shutdowns, importance of a log sheet, importance of water treatment and tube cleaning, and importance of maintain- ing a leak-free chiller.

SAFETY DEVICES AND PROCEDURES — Electrical dis- connects, relief device inspection, and handling refrigerant.

CHECK OPERATOR KNOWLEDGE — Start, stop, and shutdown procedures, safety and operating controls, refrigerant and oil charging, and job safety.

REVIEW THE START-UP OPERATION, AND MAINTE- NANCE MANUAL.

OPERATING INSTRUCTIONS

Operator Duties

1.Become familiar with the chiller and related equipment before operating the chiller.

2.Prepare the system for start-up, start and stop the chiller, and place the system in a shutdown condition.

3.Maintain a log of operating conditions and document any abnormal readings.

4.Inspect the equipment, make routine adjustments, and perform a Control Test. Maintain the proper oil and re- frigerant levels.

5.Protect the system from damage during shutdown periods.

6.Maintain the set point, time schedules, and other PIC functions.

Prepare the Chiller for Start-UpFollow the steps described in the Initial Start-Up section, page 64.

To Start the Chiller

1.Start the water pumps, if they are not automatic.

2.On the CVC/ICVC default screen, press the LOCAL or

CCN softkey to start the system. If the chiller is in the OCCUPIED mode and the start timers have expired, the start sequence will start. Follow the procedure described in the Start-Up/Shutdown/Recycle Sequence section, page 46.

Check the Running System — After the compres- sor starts, the operator should monitor the CVC/ICVC display and observe the parameters for normal operating conditions:

1.The oil reservoir temperature should be above 120 F (49 C) during shutdown.

2.The bearing oil temperature accessed on the COMPRESS table should be 120 to 165 F (49 to 74 C). If the bearing

temperature reads more than 180 F (83 C) with the oil pump running, stop the chiller and determine the cause of the high temperature. Do not restart the chiller until corrected.

3.The oil level should be visible anywhere in one of the two sight glasses. Foaming oil is acceptable as long as the oil pressure and temperature are within limits.

4.The oil pressure should be between 18 and 30 psid (124 to 207 kPad) differential, as seen on the CVC/ICVC de- fault screen. Typically the reading will be 18 to 25 psid (124 to 172 kPad) at initial start-up.

5.The moisture indicator sight glass on the refrigerant motor cooling line should indicate refrigerant flow and a dry condition.

6.The condenser pressure and temperature varies with the chiller design conditions. Typically the pressure will range between 60 and 135 psig (390 to 950 kPa) with a corresponding temperature range of 60 to 105 F (15 to 41 C). The condenser entering water temperature should be controlled below the specified design entering water temperature to save on compressor kilowatt requirements.

7.Cooler pressure and temperature also will vary with the design conditions. Typical pressure range will be between 60 and 80 psig (410 and 550 kPa), with temperature rang- ing between 34 and 45 F (1 and 8 C).

8.The compressor may operate at full capacity for a short time after the pulldown ramping has ended, even though the building load is small. The active electrical demand setting can be overridden to limit the compressor IkW, or the pulldown rate can be decreased to avoid a high demand charge for the short period of high demand oper- ation. Pulldown rate can be based on load rate or temper- ature rate and is accessed on the EQUIPMENT SER- VICE screen, RAMP_DEM table (Table 2, Example 21).

To Stop the Chiller

1.The occupancy schedule starts and stops the chiller auto- matically once the time schedule is configured.

2.By pressing the STOP button for one second, the alarm light blinks once to confirm the button has been pressed. The compressor will then follow the normal shutdown sequence as described in the Shutdown Sequence, Start- Up/Shutdown/Recycle Sequence section, page 46. The

chiller will not restart until the CCN or LOCAL soft- key is pressed. The chiller is now in the OFF control mode.

IMPORTANT: Do not attempt to stop the chiller by opening an isolating knife switch. High intensity arcing may occur.

Do not restart the chiller until the problem is diagnosed and corrected.

After Limited Shutdown — No special preparations should be necessary. Follow the regular preliminary checks and starting procedures.

Preparation for Extended Shutdown — The refrig- erant should be transferred into the pumpout storage tank (if supplied; see Pumpout and Refrigerant Transfer Procedures) to reduce chiller pressure and the possibility of leaks. Maintain a holding charge of 5 to 10 lbs (2.27 to 4.5 kg) of refrigerant or nitrogen to prevent air from leaking into the chiller.

If freezing temperatures are likely to occur in the chiller ar- ea, drain the chilled water, condenser water, and the pumpout condenser water circuits to avoid freeze-up. Keep the waterbox drains open.

66

Image 66
Contents Start-Up, Operation, and Maintenance Instructions Safety ConsiderationsContents Contents Introduction Abbreviations and ExplanationsChiller Familiarization 19XR IdentificationTypical 19XR Components Refrigeration Cycle Motor and Lubricating OIL Cooling CycleVFD Cooling Cycle Lubrication CycleStarting Equipment Unit-Mounted Solid-State Starter OptionalUnit-Mounted Wye-Delta Starter Optional ControlsDefinitions Variable Frequency Drive VFD 19XR Controls and Sensor Locations Major PIC II Components Panel Locations PIC II Component Panel LocationControl Panel CVC/ICVC Operation and Menus Fig Example of Status Screen 19XR Chiller Display Menu Structure CVC/ICVC 19XR Service Menu Structure Time and Date Example of Time Schedule Operation Screen Example of Set Point Screen Example 1 Chiller Display Default Screen CVC/ICVC Display DataExample 3 Startup Display Screen Example 2 Maintstat Display ScreenDescription Status Units Point Startup Description Status Units PointExample 4 Compress Display Screen Example 5 Heatex Display ScreenExample 6 Power Display Screen Example 7 Ismstat Display ScreenCVC Icvc Description Status Units Point Menu Setpoint Select Description Status Units Point DefaultExample 8 CVC/ICVCPSWD Display Screen Example 9 Setpoint Display ScreenExample 11 Override Display Screen Control Algorithm Status Override Description Units PointExample 12 Llmaint Display Screen Example 13 Ismhist Display Screen Example 14 Wsmdefme Display ScreenControl Algorithm Status Wsmdefme Description Units Point Example 15 Netopt Display Screen ISM Starter Config DataIsmconf Description Status Units Point Default Example 16 Ismconf Display ScreenExample 18 SETUP1 Display Screen Spare ALERT/ALARM EnableExample 17 Options Display Screen Example 19 SETUP2 Display Screen Example 20 Leadlag Display ScreenLAG=2, STANDBY=3 Example 21 Rampdem Display Screen Description Status Units Point DefaultReset Type Example 22 Tempctl Display ScreenMode IGV VFD Normal Control mode occurs when Active Delta TSurge Prevention Mode occurs when Active Delta T PIC II System FunctionsPage Protective Safety Limits and Control Settings Page Capacity Overrides Evaporator Freeze Protection Icvc only a Page Surge Protection Fixed Speed Chiller Head Pressure Reference OutputPage Page Point Example of Attach to Network Device Screen Example of Holiday Period Screen Recycle Sequence Fig Default CVC/ICVC screen, press the MenuSTART-UP/SHUTDOWN Local Start-Up Local start-up or a manual start-up isEntering Condenser Water temperature plus 3 F -1.6C Before Initial START-UP Job Data RequiredEquipment Required 19XR Leak Test Procedures Page Page HFC-134a Pressure Temperature F HFC-134a Pressure Temperature CTemperature Pressure Inspect Wiring Perform dehydration as followsCheck Starter Manufacturer Cable noWhite G Software Configuration Parameter Benshaw RediStart Micro Menu Items Verify VFD Configuration and Change Parameters if Necessary VFD Title Setting Parameter Description SettingDescription Settings Press Status Press Compress Press Select Press Menu Press Status Press Compress Press SelectEstimated Minimum Load Conditions Load Surge Prevention Occurs TOO Soon Occurs TOO LateCCM Temperature Thermistors Charge Refrigerant into Chiller Control Test Menu FunctionsTests to be Devices Tested Performed Initial START-UP Refrigerant HFC-134a ChargeDry Run to Test Start-Up Sequence Check Motor RotationCheck Oil Pressure and Compressor Stop To Start the Chiller Operating InstructionsOperator Duties To Stop the ChillerPumpout and Refrigerant Transfer Procedures Operating the Optional Pumpout UnitBearing Date Cooler Condenser CompressorTime FLATurn off pumpout condenser water Valve ConditionChillers with Isolation Valves General Maintenance Test After Service, Repair, or Major Leak IfWeekly Maintenance Guide Vane Actuator LinkageScheduled Maintenance Check Safety and Operating Controls MonthlyCompressor Bearing and Gear Maintenance Inspect the Heat Exchanger Tubes and Flow DevicesOrdering Replacement Chiller Parts When Optional Pumpout System ControlsTroubleshooting Guide Checking Pressure TransducersHeatex LlmaintOccdefcm ICE Build Terminate Pumpdown ModeShutdown in Progress Ready to StartAutorestart in Progress PrestartAlert Running Temp ControlLimited FaultRUN Capacity SensorStart ProtectiveFailure to StopPotential LossCommunication FREEZE-UPAutorestart Sensor AlertLOW OIL Pressure PendingOption Sensor Pressure AlertRecycle DiffuserThermistor Temperature F vs. Resistance/Voltage Drop DropThermistor Temperature C vs. Resistance/Voltage Drop Temperature PIC ResistancePower is connected to Plug J1 on each module Control ModulesChiller Control Module CCM Fig Integrated Starter Module FigReplacing Defective Processor Modules Integratedstartermodule Measure SCR Pairs Recorded Being Between CheckedHeat Exchanger Data English Number of Tubes English CodeHeat Exchanger Data SI Number of Tubes CodeCompressor Weights 19XR Additional Data for Marine Waterboxes19XR Motor Weights Standard and High Efficiency Motors English Motor19XR Waterbox Cover Weights English lb 19XR Waterbox Cover Weights SI kg Additional Miscellaneous Weights Optional Pumpout System Electrical DataMotor Voltage Code Compressor Assembly Torques Description TorqueView B High Speed Shaft 19XR Compressor Clearances Compressor Code100 Allen-Bradley Wye-Delta Unit-Mounted Starter101 102 ISM103 Temp104 105 106 Power Panel Wiring Schematic 107Cutler-Hammer Wye Delta Unit Mounted Starter Sizes 3-5DP 108Cutler-Hammer Wye Delta Unit Mounted Starter Size 6DP 109Ground Fault Phase Current Option Separate Metering Option111 112 AUX113 FU Fuse114 115 VFDTypical Variable Frequency Drive VFD Wiring Schematic 116117 118 119 120 121 122 Index Index Remove and use for job file JOB Data RequiredInspect Wiring and Record Electrical Data Ratings CL-260.0 40 to 10010 to 15 toCL-4 105 to 115 200 to460 85 to20 to Psi 30 to50 to CL-6125 150 to90 to 125 to65 to 90 to 100Amp 250 CL-8 25 to CL-950 to 145 CL-100000 to 0200 0000 to0200 CL-11028 10 to Job Sheet 60 for 60 Hz and 50 for 50 Hz 002 Power Module Dependent Selected motor 100% amps004 To H.022 Job Sheet 60 for 60 Hz and 50 for 50 Hz 000 100 to Selected line voltageCL-13 CCN Local Reset CL-14Page Incurring obligations
Related manuals
Manual 40 pages 46.08 Kb

19XR, XRV specifications

The Carrier 19XR and 19XRV chillers are sophisticated cooling solutions that represent the forefront of HVAC technology. Designed for large commercial and industrial applications, these chillers provide exceptional performance, energy efficiency, and reliability, making them ideal for a variety of environments ranging from hospitals to manufacturing facilities.

One of the most significant features of the Carrier 19XR and 19XRV chillers is their advanced scroll compressor technology. These units employ a tandem scroll design that enhances efficiency while minimizing operational noise. This makes them ideal for urban environments where noise restrictions may be in place. Moreover, the compressors are equipped with variable speed drive options in the 19XRV model, which allows for greater energy savings by adjusting cooling output based on real-time demand.

In addition to their advanced compressors, the 19XR and 19XRV units incorporate the Carrier GreenChoice refrigerant, which has a lower global warming potential compared to traditional refrigerants. This innovative choice not only meets regulatory requirements but also contributes to sustainability goals, making these chillers a responsible choice for environmentally conscious organizations.

The units are engineered with a robust heat exchanger design, which enhances heat transfer efficiency and overall system performance. This ensures optimal operation even in extreme conditions. They feature a microprocessor-based control system that allows for precise monitoring and control of the chiller’s performance, enabling operators to make real-time adjustments to maximize energy efficiency.

The Carrier 19XR and 19XRV chillers also prioritize serviceability. The design incorporates easy access to key components, simplifying maintenance procedures and reducing downtime. This focus on maintainability extends the lifespan of the equipment, leading to lower lifecycle costs.

In terms of connectivity, these chillers are equipped with advanced Building Management System (BMS) integration capabilities. This allows for seamless monitoring and control of the chillers using a centralized platform, facilitating energy management and operational optimization.

Overall, the Carrier 19XR and 19XRV chillers stand out in the market for their blend of cutting-edge technology, energy efficiency, and user-friendly features. They are engineered to meet the demanding needs of modern commercial and industrial applications, making them a preferred choice for facility managers seeking reliable cooling solutions.