Carrier 19XR, XRV specifications

Page 42

Standby Chiller Configuration and Operation — A chiller is designated as a standby chiller when its LEADLAG: CONFIG- URATION value on the LEADLAG screen is set to “3.” The standby chiller can operate as a replacement for the lag chiller only if one of the other two chillers is in an alarm (*) condition (as shown on the CVC/ICVC panel). If both lead and lag chill- ers are in an alarm (*) condition, the standby chiller defaults to operate in CCN mode, based on its configured occupancy schedule and remote contacts input.

Lag Chiller Start-Up Requirements — Before the lag chiller can be started, the following conditions must be met:

1.Lead chiller ramp loading must be complete.

2.Lead chilled water temperature must be greater than the CONTROL POINT temperature (see the MAINSTAT screen) plus 1/2 the CHILLED WATER DEADBAND temperature (see the SETUP1 screen).

NOTE: The chilled water temperature sensor may be the leaving chilled water sensor, the return water sensor, the common supply water sensor, or the common return wa- ter sensor, depending on which options are configured and enabled.

3.Lead chiller ACTIVE DEMAND LIMIT (see the MAIN- STAT screen) value must be greater than 95% of full load amps.

4.Lead chiller temperature pulldown rate (TEMP PULL-

DOWN DEG/MIN on the TEMP_CTL screen) of the chilled water temperature is less than 0.5° F (0.27° C) per minute.

5.The lag chiller status indicates it is in CCN mode and is not in an alarm condition. If the current lag chiller is in an alarm condition, the standby chiller becomes the active lag chiller, if it is configured and available.

6.The configured LAG START TIMER entry has elapsed. The LAG START TIMER starts when the lead chiller ramp loading is completed. The LAG START TIMER entry is on the LEADLAG screen, which is accessed from the EQUIPMENT SERVICE table of the SERVICE menu.

When all the above requirements have been met, the lag chiller is commanded to a STARTUP mode (SUPVSR flashing next to the point value on the STATUS table). The PIC II con- trol then monitors the lag chiller for a successful start. If the lag chiller fails to start, the standby chiller, if configured, is started.

Lag Chiller Shutdown Requirements — The following condi- tions must be met in order for the lag chiller to be stopped.

1.Lead chiller compressor motor average line current or load value (MOTOR PERCENT KILOWATTS on the MAINSTAT screen) is less than the lead chiller percent capacity.

NOTE: Lead chiller percent capacity = 115 – LAG % CA- PACITY. The LAG % CAPACITY parameter is on the LEADLAG screen, which is accessed from the EQUIP- MENT SERVICE table on the SERVICE menu.

2.The lead chiller chilled water temperature is less than the CONTROL POINT temperature (see the MAINSTAT

screen) plus 1/2 the CHILLED WATER DEADBAND tem- perature (see the SETUP1 screen).

3.The configured LAG STOP TIMER entry has elapsed. The LAG STOP TIMER starts when the lead chiller chilled water temperature is less than the chilled water CONTROL POINT plus 1/2 of the CHILLED WATER DEADBAND and the lead chiller compressor motor load (MOTOR PERCENT KILOWATT or AVERAGE LINE CURRENT on the MAINSTAT screen) is less than the lead chiller percent capacity.

NOTE: Lead chiller percent capacity = 115 – LAG % CAPAC- ITY. The LAG % CAPACITY parameter is on the LEADLAG screen, which is accessed from the EQUIPMENT SERVICE table on the SERVICE menu.

FAULTED CHILLER OPERATION — If the lead chiller shuts down because of an alarm (*) condition, it stops commu- nicating to the lag and standby chillers. After 30 seconds, the lag chiller becomes the acting lead chiller and starts and stops the standby chiller, if necessary.

If the lag chiller goes into alarm when the lead chiller is also in alarm, the standby chiller reverts to a stand-alone CCN mode of operation.

If the lead chiller is in an alarm (*) condition (as shown on

the CVC/ICVC panel), press the RESET softkey to clear the alarm. The chiller is placed in CCN mode. The lead chiller communicates and monitors the RUN STATUS of the lag and standby chillers. If both the lag and standby chillers are run- ning, the lead chiller does not attempt to start and does not as- sume the role of lead chiller until either the lag or standby chill- er shuts down. If only one chiller is running, the lead chiller waits for a start request from the operating chiller. When the configured lead chiller starts, it assumes its role as lead chiller.

If the lag chiller is the only chiller running when the lead chiller assumes its role as a lead chiller then the lag chiller will perform a RECOVERY START REQUEST (LL_MAINT screen). The lead chiller will start up when the following condi- tions are met.

1.Lag chiller ramp loading must be complete.

2.Lag CHILLED WATER TEMP (MAINSTAT screen) is

greater than CONTROL POINT plus 1/2 the CHILLED WATER DEADBAND temperature.

3.Lag chiller ACTIVE DEMAND LIMIT value must be greater than 95% of full load amps.

4.Lag chiller temperature pulldown rate (TEMP PULL- DOWN DEG/MIN) of the chilled water temperature is less than 0.5 F (0.27 C) per minute.

5.The standby chiller is not running as a lag chiller.

6.The configured LAG START TIMER has elapsed. The LAG START TIMER is started when ramp loading is completed.

LOAD BALANCING — When the LOAD BALANCE OPTION (see LEADLAG screen) is enabled, the lead chiller sets the ACTIVE DEMAND LIMIT in the lag chiller to the lead chiller’s compressor motor load value MOTOR PERCENT KILOWATTS or AVERAGE LINE CURRENT on the MAIN- STAT screen). This value has limits of 40% to 100%. When the lag chiller ACTIVE DEMAND LIMIT is set, the CONTROL POINT must be modified to a value of 3° F (1.67° C) less than the lead chiller’s CONTROL POINT value. If the LOAD BAL- ANCE OPTION is disabled, the ACTIVE DEMAND LIMIT and the CONTROL POINT are forced to the same value as the lead chiller.

AUTO. RESTART AFTER POWER FAILURE — When an auto. restart condition occurs, each chiller may have a delay added to the start-up sequence, depending on its lead/lag con- figuration. The lead chiller does not have a delay. The lag chill- er has a 45-second delay. The standby chiller has a 90-second delay. The delay time is added after the chiller water flow is verified. The PIC II ensures the guide vanes are closed. After the guide vane position is confirmed, the delay for lag and standby chillers occurs prior to energizing the oil pump. The normal start-up sequence then continues. The auto. restart de- lay sequence occurs whether the chiller is in CCN or LOCAL mode and is intended to stagger the compressor motor starts. Preventing the motors from starting simultaneously helps re- duce the inrush demands on the building power system.

42

Image 42
Contents Start-Up, Operation, and Maintenance Instructions Safety ConsiderationsContents Contents Introduction Abbreviations and ExplanationsChiller Familiarization 19XR IdentificationTypical 19XR Components Refrigeration Cycle Motor and Lubricating OIL Cooling CycleVFD Cooling Cycle Lubrication CycleStarting Equipment Unit-Mounted Solid-State Starter OptionalUnit-Mounted Wye-Delta Starter Optional ControlsDefinitions Variable Frequency Drive VFD 19XR Controls and Sensor Locations Major PIC II Components Panel Locations PIC II Component Panel LocationControl Panel CVC/ICVC Operation and Menus Fig Example of Status Screen 19XR Chiller Display Menu Structure CVC/ICVC 19XR Service Menu Structure Time and Date Example of Time Schedule Operation Screen Example of Set Point Screen Example 1 Chiller Display Default Screen CVC/ICVC Display DataExample 3 Startup Display Screen Example 2 Maintstat Display ScreenDescription Status Units Point Startup Description Status Units PointExample 4 Compress Display Screen Example 5 Heatex Display ScreenExample 6 Power Display Screen Example 7 Ismstat Display ScreenCVC Icvc Description Status Units Point Menu Setpoint Select Description Status Units Point DefaultExample 8 CVC/ICVCPSWD Display Screen Example 9 Setpoint Display ScreenExample 11 Override Display Screen Control Algorithm Status Override Description Units PointExample 12 Llmaint Display Screen Example 13 Ismhist Display Screen Example 14 Wsmdefme Display ScreenControl Algorithm Status Wsmdefme Description Units Point Example 15 Netopt Display Screen ISM Starter Config DataIsmconf Description Status Units Point Default Example 16 Ismconf Display ScreenExample 18 SETUP1 Display Screen Spare ALERT/ALARM EnableExample 17 Options Display Screen Example 19 SETUP2 Display Screen Example 20 Leadlag Display ScreenLAG=2, STANDBY=3 Example 21 Rampdem Display Screen Description Status Units Point DefaultReset Type Example 22 Tempctl Display ScreenMode IGV VFD Normal Control mode occurs when Active Delta TSurge Prevention Mode occurs when Active Delta T PIC II System FunctionsPage Protective Safety Limits and Control Settings Page Capacity Overrides Evaporator Freeze Protection Icvc only a Page Surge Protection Fixed Speed Chiller Head Pressure Reference OutputPage Page Point Example of Attach to Network Device Screen Example of Holiday Period Screen Recycle Sequence Fig Default CVC/ICVC screen, press the MenuSTART-UP/SHUTDOWN Local Start-Up Local start-up or a manual start-up isEntering Condenser Water temperature plus 3 F -1.6C Before Initial START-UP Job Data RequiredEquipment Required 19XR Leak Test Procedures Page Page HFC-134a Pressure Temperature F HFC-134a Pressure Temperature CTemperature Pressure Inspect Wiring Perform dehydration as followsCheck Starter Manufacturer Cable noWhite G Software Configuration Parameter Benshaw RediStart Micro Menu Items Verify VFD Configuration and Change Parameters if Necessary VFD Title Setting Parameter Description SettingDescription Settings Press Status Press Compress Press Select Press Menu Press Status Press Compress Press SelectEstimated Minimum Load Conditions Load Surge Prevention Occurs TOO Soon Occurs TOO LateCCM Temperature Thermistors Charge Refrigerant into Chiller Control Test Menu FunctionsTests to be Devices Tested Performed Initial START-UP Refrigerant HFC-134a ChargeDry Run to Test Start-Up Sequence Check Motor RotationCheck Oil Pressure and Compressor Stop To Start the Chiller Operating InstructionsOperator Duties To Stop the ChillerPumpout and Refrigerant Transfer Procedures Operating the Optional Pumpout UnitBearing Date Cooler Condenser CompressorTime FLATurn off pumpout condenser water Valve ConditionChillers with Isolation Valves General Maintenance Test After Service, Repair, or Major Leak IfWeekly Maintenance Guide Vane Actuator LinkageScheduled Maintenance Check Safety and Operating Controls MonthlyCompressor Bearing and Gear Maintenance Inspect the Heat Exchanger Tubes and Flow DevicesOrdering Replacement Chiller Parts When Optional Pumpout System ControlsTroubleshooting Guide Checking Pressure TransducersHeatex LlmaintOccdefcm ICE Build Terminate Pumpdown ModeShutdown in Progress Ready to StartAutorestart in Progress PrestartAlert Running Temp ControlLimited FaultRUN Capacity SensorStart ProtectiveFailure to StopPotential LossCommunication FREEZE-UPAutorestart Sensor AlertLOW OIL Pressure PendingOption Sensor Pressure AlertRecycle DiffuserThermistor Temperature F vs. Resistance/Voltage Drop DropThermistor Temperature C vs. Resistance/Voltage Drop Temperature PIC ResistancePower is connected to Plug J1 on each module Control ModulesChiller Control Module CCM Fig Integrated Starter Module FigReplacing Defective Processor Modules Integratedstartermodule Measure SCR Pairs Recorded Being Between CheckedHeat Exchanger Data English Number of Tubes English CodeHeat Exchanger Data SI Number of Tubes CodeCompressor Weights 19XR Additional Data for Marine Waterboxes19XR Motor Weights Standard and High Efficiency Motors English Motor19XR Waterbox Cover Weights English lb 19XR Waterbox Cover Weights SI kg Additional Miscellaneous Weights Optional Pumpout System Electrical DataMotor Voltage Code Compressor Assembly Torques Description TorqueView B High Speed Shaft 19XR Compressor Clearances Compressor Code100 Allen-Bradley Wye-Delta Unit-Mounted Starter101 102 ISM103 Temp104 105 106 Power Panel Wiring Schematic 107Cutler-Hammer Wye Delta Unit Mounted Starter Sizes 3-5DP 108Cutler-Hammer Wye Delta Unit Mounted Starter Size 6DP 109Ground Fault Phase Current Option Separate Metering Option111 112 AUX113 FU Fuse114 115 VFDTypical Variable Frequency Drive VFD Wiring Schematic 116117 118 119 120 121 122 Index Index Remove and use for job file JOB Data RequiredInspect Wiring and Record Electrical Data Ratings CL-260.0 40 to 10010 to 15 toCL-4 105 to 115 200 to460 85 to20 to Psi 30 to50 to CL-6125 150 to90 to 125 to65 to 90 to 100Amp 250 CL-8 25 to CL-950 to 145 CL-100000 to 0200 0000 to0200 CL-11028 10 to Job Sheet 60 for 60 Hz and 50 for 50 Hz 002 Power Module Dependent Selected motor 100% amps004 To H.022 Job Sheet 60 for 60 Hz and 50 for 50 Hz 000 100 to Selected line voltageCL-13 CCN Local Reset CL-14Page Incurring obligations
Related manuals
Manual 40 pages 46.08 Kb

19XR, XRV specifications

The Carrier 19XR and 19XRV chillers are sophisticated cooling solutions that represent the forefront of HVAC technology. Designed for large commercial and industrial applications, these chillers provide exceptional performance, energy efficiency, and reliability, making them ideal for a variety of environments ranging from hospitals to manufacturing facilities.

One of the most significant features of the Carrier 19XR and 19XRV chillers is their advanced scroll compressor technology. These units employ a tandem scroll design that enhances efficiency while minimizing operational noise. This makes them ideal for urban environments where noise restrictions may be in place. Moreover, the compressors are equipped with variable speed drive options in the 19XRV model, which allows for greater energy savings by adjusting cooling output based on real-time demand.

In addition to their advanced compressors, the 19XR and 19XRV units incorporate the Carrier GreenChoice refrigerant, which has a lower global warming potential compared to traditional refrigerants. This innovative choice not only meets regulatory requirements but also contributes to sustainability goals, making these chillers a responsible choice for environmentally conscious organizations.

The units are engineered with a robust heat exchanger design, which enhances heat transfer efficiency and overall system performance. This ensures optimal operation even in extreme conditions. They feature a microprocessor-based control system that allows for precise monitoring and control of the chiller’s performance, enabling operators to make real-time adjustments to maximize energy efficiency.

The Carrier 19XR and 19XRV chillers also prioritize serviceability. The design incorporates easy access to key components, simplifying maintenance procedures and reducing downtime. This focus on maintainability extends the lifespan of the equipment, leading to lower lifecycle costs.

In terms of connectivity, these chillers are equipped with advanced Building Management System (BMS) integration capabilities. This allows for seamless monitoring and control of the chillers using a centralized platform, facilitating energy management and operational optimization.

Overall, the Carrier 19XR and 19XRV chillers stand out in the market for their blend of cutting-edge technology, energy efficiency, and user-friendly features. They are engineered to meet the demanding needs of modern commercial and industrial applications, making them a preferred choice for facility managers seeking reliable cooling solutions.