Carrier XRV, 19XR specifications Point

Page 43

Ice Build Control — The ice build control option auto- matically sets the CONTROL POINT of the chiller to a temper- ature that allows ice building for thermal storage.

NOTE: For ice build control to operate properly, the PIC II must be in CCN mode.

NOTE: See Fig. 17 and 18 for more information on ice build- related menus.

The PIC II can be configured for ice build operation.

From the SERVICE menu, access the EQUIPMENT SERVICE table. From there, select the OPTIONS screen to enable or disable the ICE BUILD OPTION. See Table 2, Example 17.

The ICE BUILD SETPOINT can be configured from the SETPOINT display, which is accessed from the PIC II main menu. See Table 2, Example 9.

The ice build schedule can be viewed or modified from the SCHEDULE table. From this table, select the ice build schedule (OCCPC02S) screen. See Fig. 19 and the section on Time Schedule Operation, page 20, for more information on modifying chiller schedules.

The ice build time schedule defines the period(s) during which ice build is active if the ice build option is enabled. If the ice build time schedule overlaps other schedules, the ice build time schedule takes priority. During the ice build period, the CONTROL POINT is set to the ICE BUILD SETPOINT for temperature control. The ICE BUILD RECYCLE and ICE BUILD TERMINATION parameters, accessed from the OPTIONS screen, allow the chiller operator to recycle or ter- minate the ice build cycle. The ice build cycle can be config- ured to terminate if:

the ENTERING CHILLED WATER temperature is less than the ICE BUILD SETPOINT. In this case, the opera- tor sets the ICE BUILD TERMINATION parameter to 0 on the OPTIONS screen.

the REMOTE CONTACT inputs from an ice level indi- cator are opened. In this case, the operator sets the ICE BUILD TERMINATION parameter to 1 on the OPTIONS screen.

the chilled water temperature is less than the ice build set point and the remote contact inputs from an ice level indicator are open. In this case, the operator sets the ICE BUILD TERMINATION parameter to 2 on the OPTIONS screen.

the end of the ice build time schedule has been reached.

ICE BUILD INITIATION — The ice build time schedule (OCCPC02S) is the means for activating the ice build option. The ice build option is enabled if:

a day of the week and a time period on the ice build time schedule are enabled. The SCHEDULE screen shows an X in the day field and ON/OFF times are designated for the day(s),

and the ICE BUILD OPTION is enabled.

The following events take place (unless overridden by a higher authority CCN device).

CHILLER START/STOP is forced to START.

The CONTROL POINT is forced to the ICE BUILD SET-

POINT.

Any force (Auto) is removed from the ACTIVE DEMAND LIMIT.

NOTE: A parameter’s value can be forced, that is, the value can be manually changed at the CVC/ICVC by an operator, changed from another CCN device, or changed by other algo- rithms in the PIC II control system.

NOTE: The Ice Build steps do not occur if the chiller is config- ured and operating as a lag or standby chiller for lead/lag oper- ation and is actively being controlled by a lead chiller. The lead chiller communicates the ICE BUILD SET POINT, the desired CHILLER START/STOP state, and the ACTIVE DEMAND

LIMIT to the lag or standby chiller as required for ice build, if configured to do so.

START-UP/RECYCLE OPERATION — If the chiller is not running when ice build activates, the PIC II checks the follow- ing conditions, based on the ICE BUILD TERMINATION value, to avoid starting the compressor unnecessarily:

if ICE BUILD TERMINATION is set to the TEMP option and the ENTERING CHILLED WATER temperature is less than or equal to the ICE BUILD SETPOINT;

if ICE BUILD TERMINATION is set to the CONTACTS option and the remote contacts are open;

if the ICE BUILD TERMINATION is set to the BOTH (temperature and contacts) option and the ENTERING CHILLED WATER temperature is less than or equal to the ICE BUILD SETPOINT and the remote contacts are open.

The ICE BUILD RECYCLE on the OPTIONS screen deter- mines whether or not the chiller will go into an ice build RE- CYCLE mode.

If the ICE BUILD RECYCLE is set to DSABLE (dis- able), the PIC II reverts to normal temperature control when the ice build function terminates.

If the ICE BUILD RECYCLE is set to ENABLE, the PIC II goes into an ICE BUILD RECYCLE mode and the chilled water pump relay remains energized to keep the chilled water flowing when the ice build function termi- nates. If the temperature of the ENTERING CHILLED WATER increases above the ICE BUILD SETPOINT plus the RECYCLE RESTART DELTA T value, the compres- sor restarts and controls the chilled water/brine tempera- ture to the ICE BUILD SETPOINT.

TEMPERATURE CONTROL DURING ICE BUILD — During ice build, the capacity control algorithm shall use the CONTROL POINT minus 5 F (–2.8 C) for control of the LEAVING CHILLED WATER temperature. (See Table 2, ex- ample 10, the CAPACITY CONTROL parameter on the CA- PACITY screen.) The ECW CONTROL OPTION and any tem- perature reset option shall be ignored, if enabled, during ice build. The AUTO DEMAND LIMIT INPUT shall also be ignored if enabled during ice build.

ECW CONTROL OPTION and any temperature reset options (configured on TEMP_CTL screen).

20 mA DEMAND LIMIT OPT (configured on RAMP_DEM screen).

TERMINATION OF ICE BUILD — The ice build function terminates under the following conditions:

1.Time Schedule — When the current time on the ice build time schedule (OCCPC02S) is not set as an ice build time period.

2.Entering Chilled Water Temperature — Compressor operation terminates, based on temperature, if the ICE BUILD TERMINATION parameter is set to 0 (TEMP), the ENTERING CHILLED WATER temperature is less than the ICE BUILD SETPOINT, and the ICE BUILD RECYCLE is set to DSABLE. If the ICE BUILD RECY- CLE OPTION is set to ENABLE, a recycle shutdown oc- curs and recycle start-up depends on the LEAVING CHILLED WATER temperature being greater than the water/brine CONTROL POINT plus the RESTART DELTA T temperature.

3.Remote Contacts/Ice Level Input — Compressor opera- tion terminates when the ICE BUILD TERMINATION parameter is set to 1 (CONTACTS) and the remote con- tacts are open and the ICE BUILD RECYCLE is set to DSABLE (0). In this case, the contacts provide ice level termination control. The contacts are used to stop the ice build function when a time period on the ice build sched- ule (OCCPC02S) is set for ice build operation. The re- mote contacts can still be opened and closed to start and

43

Image 43
Contents Safety Considerations Start-Up, Operation, and Maintenance InstructionsContents Contents Abbreviations and Explanations Introduction19XR Identification Chiller FamiliarizationTypical 19XR Components Motor and Lubricating OIL Cooling Cycle Refrigeration CycleLubrication Cycle VFD Cooling CycleUnit-Mounted Solid-State Starter Optional Starting EquipmentControls Unit-Mounted Wye-Delta Starter OptionalDefinitions Variable Frequency Drive VFD 19XR Controls and Sensor Locations PIC II Component Panel Location Major PIC II Components Panel LocationsControl Panel CVC/ICVC Operation and Menus Fig Example of Status Screen 19XR Chiller Display Menu Structure CVC/ICVC 19XR Service Menu Structure Time and Date Example of Time Schedule Operation Screen Example of Set Point Screen CVC/ICVC Display Data Example 1 Chiller Display Default ScreenStartup Description Status Units Point Example 2 Maintstat Display ScreenDescription Status Units Point Example 3 Startup Display ScreenExample 5 Heatex Display Screen Example 4 Compress Display ScreenExample 7 Ismstat Display Screen Example 6 Power Display ScreenExample 9 Setpoint Display Screen Menu Setpoint Select Description Status Units Point DefaultExample 8 CVC/ICVCPSWD Display Screen CVC Icvc Description Status Units PointControl Algorithm Status Override Description Units Point Example 11 Override Display ScreenExample 12 Llmaint Display Screen Example 14 Wsmdefme Display Screen Example 13 Ismhist Display ScreenControl Algorithm Status Wsmdefme Description Units Point Example 16 Ismconf Display Screen ISM Starter Config DataIsmconf Description Status Units Point Default Example 15 Netopt Display ScreenSpare ALERT/ALARM Enable Example 18 SETUP1 Display ScreenExample 17 Options Display Screen Example 20 Leadlag Display Screen Example 19 SETUP2 Display ScreenLAG=2, STANDBY=3 Example 22 Tempctl Display Screen Description Status Units Point DefaultReset Type Example 21 Rampdem Display ScreenPIC II System Functions Normal Control mode occurs when Active Delta TSurge Prevention Mode occurs when Active Delta T Mode IGV VFDPage Protective Safety Limits and Control Settings Page Capacity Overrides Evaporator Freeze Protection Icvc only a Page Head Pressure Reference Output Surge Protection Fixed Speed ChillerPage Page Point Example of Attach to Network Device Screen Example of Holiday Period Screen Local Start-Up Local start-up or a manual start-up is Default CVC/ICVC screen, press the MenuSTART-UP/SHUTDOWN Recycle Sequence FigEntering Condenser Water temperature plus 3 F -1.6C Job Data Required Before Initial START-UPEquipment Required 19XR Leak Test Procedures Page Page HFC-134a Pressure Temperature C HFC-134a Pressure Temperature FTemperature Pressure Perform dehydration as follows Inspect WiringManufacturer Cable no Check StarterWhite G Software Configuration Parameter Benshaw RediStart Micro Menu Items Verify VFD Configuration and Change Parameters if Necessary Description Setting VFD Title Setting ParameterDescription Settings Press Menu Press Status Press Compress Press Select Press Status Press Compress Press SelectLoad Surge Prevention Occurs TOO Soon Occurs TOO Late Estimated Minimum Load ConditionsCCM Temperature Thermistors Control Test Menu Functions Charge Refrigerant into ChillerTests to be Devices Tested Performed Refrigerant HFC-134a Charge Initial START-UPCheck Motor Rotation Dry Run to Test Start-Up SequenceCheck Oil Pressure and Compressor Stop To Stop the Chiller Operating InstructionsOperator Duties To Start the ChillerOperating the Optional Pumpout Unit Pumpout and Refrigerant Transfer ProceduresFLA Date Cooler Condenser CompressorTime BearingValve Condition Turn off pumpout condenser waterChillers with Isolation Valves Test After Service, Repair, or Major Leak If General MaintenanceGuide Vane Actuator Linkage Weekly MaintenanceCheck Safety and Operating Controls Monthly Scheduled MaintenanceInspect the Heat Exchanger Tubes and Flow Devices Compressor Bearing and Gear MaintenanceOptional Pumpout System Controls Ordering Replacement Chiller Parts WhenChecking Pressure Transducers Troubleshooting GuideLlmaint HeatexOccdefcm Ready to Start Terminate Pumpdown ModeShutdown in Progress ICE BuildRunning Temp Control PrestartAlert Autorestart in ProgressSensor FaultRUN Capacity LimitedStop ProtectiveFailure to StartFREEZE-UP LossCommunication PotentialPending Sensor AlertLOW OIL Pressure AutorestartDiffuser Pressure AlertRecycle Option SensorDrop Thermistor Temperature F vs. Resistance/Voltage DropTemperature PIC Resistance Thermistor Temperature C vs. Resistance/Voltage DropControl Modules Power is connected to Plug J1 on each moduleIntegrated Starter Module Fig Chiller Control Module CCM FigReplacing Defective Processor Modules Integratedstartermodule Checked Measure SCR Pairs Recorded Being BetweenNumber of Tubes English Code Heat Exchanger Data EnglishNumber of Tubes Code Heat Exchanger Data SI19XR Additional Data for Marine Waterboxes Compressor WeightsEnglish Motor 19XR Motor Weights Standard and High Efficiency Motors19XR Waterbox Cover Weights English lb 19XR Waterbox Cover Weights SI kg Optional Pumpout System Electrical Data Additional Miscellaneous WeightsMotor Voltage Code Description Torque Compressor Assembly TorquesCompressor Code View B High Speed Shaft 19XR Compressor ClearancesAllen-Bradley Wye-Delta Unit-Mounted Starter 100101 ISM 102Temp 103104 105 106 107 Power Panel Wiring Schematic108 Cutler-Hammer Wye Delta Unit Mounted Starter Sizes 3-5DP109 Cutler-Hammer Wye Delta Unit Mounted Starter Size 6DPSeparate Metering Option Ground Fault Phase Current Option111 AUX 112FU Fuse 113114 VFD 115116 Typical Variable Frequency Drive VFD Wiring Schematic117 118 119 120 121 122 Index Index JOB Data Required Remove and use for job fileCL-2 Inspect Wiring and Record Electrical Data Ratings15 to 40 to 10010 to 60.0CL-4 85 to 200 to460 105 to 115CL-6 30 to50 to 20 to Psi125 to 150 to90 to 12590 to 100 65 toAmp 250 CL-8 CL-9 25 toCL-10 50 to 145CL-11 0000 to0200 0000 to 0200000 100 to Selected line voltage 002 Power Module Dependent Selected motor 100% amps004 To H.022 Job Sheet 60 for 60 Hz and 50 for 50 Hz 028 10 to Job Sheet 60 for 60 Hz and 50 for 50 HzCL-13 CL-14 CCN Local ResetPage Incurring obligations
Related manuals
Manual 40 pages 46.08 Kb

19XR, XRV specifications

The Carrier 19XR and 19XRV chillers are sophisticated cooling solutions that represent the forefront of HVAC technology. Designed for large commercial and industrial applications, these chillers provide exceptional performance, energy efficiency, and reliability, making them ideal for a variety of environments ranging from hospitals to manufacturing facilities.

One of the most significant features of the Carrier 19XR and 19XRV chillers is their advanced scroll compressor technology. These units employ a tandem scroll design that enhances efficiency while minimizing operational noise. This makes them ideal for urban environments where noise restrictions may be in place. Moreover, the compressors are equipped with variable speed drive options in the 19XRV model, which allows for greater energy savings by adjusting cooling output based on real-time demand.

In addition to their advanced compressors, the 19XR and 19XRV units incorporate the Carrier GreenChoice refrigerant, which has a lower global warming potential compared to traditional refrigerants. This innovative choice not only meets regulatory requirements but also contributes to sustainability goals, making these chillers a responsible choice for environmentally conscious organizations.

The units are engineered with a robust heat exchanger design, which enhances heat transfer efficiency and overall system performance. This ensures optimal operation even in extreme conditions. They feature a microprocessor-based control system that allows for precise monitoring and control of the chiller’s performance, enabling operators to make real-time adjustments to maximize energy efficiency.

The Carrier 19XR and 19XRV chillers also prioritize serviceability. The design incorporates easy access to key components, simplifying maintenance procedures and reducing downtime. This focus on maintainability extends the lifespan of the equipment, leading to lower lifecycle costs.

In terms of connectivity, these chillers are equipped with advanced Building Management System (BMS) integration capabilities. This allows for seamless monitoring and control of the chillers using a centralized platform, facilitating energy management and operational optimization.

Overall, the Carrier 19XR and 19XRV chillers stand out in the market for their blend of cutting-edge technology, energy efficiency, and user-friendly features. They are engineered to meet the demanding needs of modern commercial and industrial applications, making them a preferred choice for facility managers seeking reliable cooling solutions.