Carrier 19XR, XRV specifications

Page 50

Leak Test Chiller — Due to regulations regarding refrig- erant emissions and the difficulties associated with separating contaminants from the refrigerant, Carrier recommends the following leak test procedure. See Fig. 28 for an outline of the leak test procedure. Refer to Fig. 29 and 30 during pumpout procedures and Tables 5A and 5B for refrigerant pressure/ temperature values.

1.If the pressure readings are normal for the chiller condition:

a.Evacuate the holding charge from the vessels, if present.

b.Raise the chiller pressure, if necessary, by adding refrigerant until pressure is at the equivalent satu- rated pressure for the surrounding temperature. Follow the pumpout procedures in the Transfer Refrigerant from Pumpout Storage Tank to Chiller section, Steps 1a - e, page 69.

Never charge liquid refrigerant into the chiller if the pres- sure in the chiller is less than 35 psig (241 kPa) for HFC-134a. Charge as a gas only, with the cooler and con- denser pumps running, until this pressure is reached, using PUMPDOWN LOCKOUT and TERMINATE LOCK- OUT mode on the PIC II. Flashing of liquid refrigerant at low pressures can cause tube freeze-up and considerable damage.

c.Leak test chiller as outlined in Steps 3 - 9.

2.If the pressure readings are abnormal for the chiller condition:

a.Prepare to leak test chillers shipped with refriger- ant (Step 2h).

b.Check for large leaks by connecting a nitrogen bottle and raising the pressure to 30 psig (207 kPa). Soap test all joints. If the test pressure holds for 30 minutes, prepare the test for small leaks (Steps 2g - h).

c.Plainly mark any leaks that are found.

d.Release the pressure in the system.

e.Repair all leaks.

f.Retest the joints that were repaired.

g.After successfully completing the test for large leaks, remove as much nitrogen, air, and moisture as possible, given the fact that small leaks may be present in the system. This can be accomplished by following the dehydration procedure, outlined in the Chiller Dehydration section, page 53.

h.Slowly raise the system pressure to a maximum of 160 psig (1103 kPa) but no less than 35 psig (241 kPa) for HFC-134a by adding refrigerant. Proceed with the test for small leaks (Steps 3-9).

3.Check the chiller carefully with an electronic leak detec- tor, halide torch, or soap bubble solution.

4.Leak Determination — If an electronic leak detector indi- cates a leak, use a soap bubble solution, if possible, to confirm. Total all leak rates for the entire chiller. Leakage at rates greater than 1 lb./year (0.45 kg/year) for the entire chiller must be repaired. Note the total chiller leak rate on the start-up report.

5.If no leak is found during the initial start-up procedures, complete the transfer of refrigerant gas from the pumpout storage tank to the chiller (see Transfer Refrigerant from Pumpout Storage Tank to Chiller section, page 69). Re- test for leaks.

6.If no leak is found after a retest:

a.Transfer the refrigerant to the pumpout storage tank and perform a standing vacuum test as out- lined in the Standing Vacuum Test section, below.

b.If the chiller fails the standing vacuum test, check for large leaks (Step 2b).

c.If the chiller passes the standing vacuum test, dehydrate the chiller. Follow the procedure in the Chiller Dehydration section. Charge the chiller with refrigerant (see Transfer Refrigerant from Pumpout Storage Tank to Chiller section, page 69).

7.If a leak is found after a retest, pump the refrigerant back into the pumpout storage tank or, if isolation valves are present, pump the refrigerant into the non-leaking vessel (see Pumpout and Refrigerant Transfer procedures section).

8.Transfer the refrigerant until the chiller pressure is at 18 in. Hg (40 kPa absolute).

9.Repair the leak and repeat the procedure, beginning from Step 2h, to ensure a leak-tight repair. (If the chiller is opened to the atmosphere for an extended period, evacu- ate it before repeating the leak test.)

Standing Vacuum Test — When performing the standing vacuum test or chiller dehydration, use a manometer or a wet bulb indicator. Dial gages cannot indicate the small amount of acceptable leakage during a short period of time.

1.Attach an absolute pressure manometer or wet bulb indi- cator to the chiller.

2.Evacuate the vessel (see Pumpout and Refrigerant Trans- fer Procedures section, page 67) to at least 18 in. Hg vac, ref 30-in. bar (41 kPa), using a vacuum pump or the pump out unit.

3.Valve off the pump to hold the vacuum and record the manometer or indicator reading.

4.a. If the leakage rate is less than 0.05 in. Hg (0.17 kPa) in 24 hours, the chiller is sufficiently tight.

b.If the leakage rate exceeds 0.05 in. Hg (0.17 kPa) in 24 hours, repressurize the vessel and test for leaks. If refrigerant is available in the other vessel, pressur- ize by following Steps 2-10 of Return Chiller To Normal Operating Conditions section, page 71. If not, use nitrogen and a refrigerant tracer. Raise the vessel pressure in increments until the leak is detected. If refrigerant is used, the maximum gas pressure is approximately 70 psig (483 kPa) for HFC-134a at normal ambient temperature. If nitro- gen is used, limit the leak test pressure to 230 psig (1585 kPa) maximum.

5.Repair the leak, retest, and proceed with dehydration.

50

Image 50
Contents Start-Up, Operation, and Maintenance Instructions Safety ConsiderationsContents Contents Introduction Abbreviations and ExplanationsChiller Familiarization 19XR IdentificationTypical 19XR Components Refrigeration Cycle Motor and Lubricating OIL Cooling CycleVFD Cooling Cycle Lubrication CycleStarting Equipment Unit-Mounted Solid-State Starter OptionalDefinitions Unit-Mounted Wye-Delta Starter OptionalControls Variable Frequency Drive VFD 19XR Controls and Sensor Locations Major PIC II Components Panel Locations PIC II Component Panel LocationControl Panel CVC/ICVC Operation and Menus Fig Example of Status Screen 19XR Chiller Display Menu Structure CVC/ICVC 19XR Service Menu Structure Time and Date Example of Time Schedule Operation Screen Example of Set Point Screen Example 1 Chiller Display Default Screen CVC/ICVC Display DataExample 3 Startup Display Screen Example 2 Maintstat Display ScreenDescription Status Units Point Startup Description Status Units PointExample 4 Compress Display Screen Example 5 Heatex Display ScreenExample 6 Power Display Screen Example 7 Ismstat Display ScreenCVC Icvc Description Status Units Point Menu Setpoint Select Description Status Units Point DefaultExample 8 CVC/ICVCPSWD Display Screen Example 9 Setpoint Display ScreenExample 12 Llmaint Display Screen Example 11 Override Display ScreenControl Algorithm Status Override Description Units Point Control Algorithm Status Wsmdefme Description Units Point Example 13 Ismhist Display ScreenExample 14 Wsmdefme Display Screen Example 15 Netopt Display Screen ISM Starter Config DataIsmconf Description Status Units Point Default Example 16 Ismconf Display ScreenExample 17 Options Display Screen Example 18 SETUP1 Display ScreenSpare ALERT/ALARM Enable LAG=2, STANDBY=3 Example 19 SETUP2 Display ScreenExample 20 Leadlag Display Screen Example 21 Rampdem Display Screen Description Status Units Point DefaultReset Type Example 22 Tempctl Display ScreenMode IGV VFD Normal Control mode occurs when Active Delta TSurge Prevention Mode occurs when Active Delta T PIC II System FunctionsPage Protective Safety Limits and Control Settings Page Capacity Overrides Evaporator Freeze Protection Icvc only a Page Surge Protection Fixed Speed Chiller Head Pressure Reference OutputPage Page Point Example of Attach to Network Device Screen Example of Holiday Period Screen Recycle Sequence Fig Default CVC/ICVC screen, press the MenuSTART-UP/SHUTDOWN Local Start-Up Local start-up or a manual start-up isEntering Condenser Water temperature plus 3 F -1.6C Equipment Required Before Initial START-UPJob Data Required 19XR Leak Test Procedures Page Page Temperature Pressure HFC-134a Pressure Temperature FHFC-134a Pressure Temperature C Inspect Wiring Perform dehydration as followsWhite G Check StarterManufacturer Cable no Software Configuration Parameter Benshaw RediStart Micro Menu Items Verify VFD Configuration and Change Parameters if Necessary Description Settings VFD Title Setting ParameterDescription Setting Press Status Press Compress Press Select Press Menu Press Status Press Compress Press SelectEstimated Minimum Load Conditions Load Surge Prevention Occurs TOO Soon Occurs TOO LateCCM Temperature Thermistors Tests to be Devices Tested Performed Charge Refrigerant into ChillerControl Test Menu Functions Initial START-UP Refrigerant HFC-134a ChargeCheck Oil Pressure and Compressor Stop Dry Run to Test Start-Up SequenceCheck Motor Rotation To Start the Chiller Operating InstructionsOperator Duties To Stop the ChillerPumpout and Refrigerant Transfer Procedures Operating the Optional Pumpout UnitBearing Date Cooler Condenser CompressorTime FLATurn off pumpout condenser water Valve ConditionChillers with Isolation Valves General Maintenance Test After Service, Repair, or Major Leak IfWeekly Maintenance Guide Vane Actuator LinkageScheduled Maintenance Check Safety and Operating Controls MonthlyCompressor Bearing and Gear Maintenance Inspect the Heat Exchanger Tubes and Flow DevicesOrdering Replacement Chiller Parts When Optional Pumpout System ControlsTroubleshooting Guide Checking Pressure TransducersOccdefcm HeatexLlmaint ICE Build Terminate Pumpdown ModeShutdown in Progress Ready to StartAutorestart in Progress PrestartAlert Running Temp ControlLimited FaultRUN Capacity SensorStart ProtectiveFailure to StopPotential LossCommunication FREEZE-UPAutorestart Sensor AlertLOW OIL Pressure PendingOption Sensor Pressure AlertRecycle DiffuserThermistor Temperature F vs. Resistance/Voltage Drop DropThermistor Temperature C vs. Resistance/Voltage Drop Temperature PIC ResistancePower is connected to Plug J1 on each module Control ModulesReplacing Defective Processor Modules Chiller Control Module CCM FigIntegrated Starter Module Fig Integratedstartermodule Measure SCR Pairs Recorded Being Between CheckedHeat Exchanger Data English Number of Tubes English CodeHeat Exchanger Data SI Number of Tubes CodeCompressor Weights 19XR Additional Data for Marine Waterboxes19XR Motor Weights Standard and High Efficiency Motors English Motor19XR Waterbox Cover Weights English lb 19XR Waterbox Cover Weights SI kg Motor Voltage Code Additional Miscellaneous WeightsOptional Pumpout System Electrical Data Compressor Assembly Torques Description TorqueView B High Speed Shaft 19XR Compressor Clearances Compressor Code100 Allen-Bradley Wye-Delta Unit-Mounted Starter101 102 ISM103 Temp104 105 106 Power Panel Wiring Schematic 107Cutler-Hammer Wye Delta Unit Mounted Starter Sizes 3-5DP 108Cutler-Hammer Wye Delta Unit Mounted Starter Size 6DP 109Ground Fault Phase Current Option Separate Metering Option111 112 AUX113 FU Fuse114 115 VFDTypical Variable Frequency Drive VFD Wiring Schematic 116117 118 119 120 121 122 Index Index Remove and use for job file JOB Data RequiredInspect Wiring and Record Electrical Data Ratings CL-260.0 40 to 10010 to 15 toCL-4 105 to 115 200 to460 85 to20 to Psi 30 to50 to CL-6125 150 to90 to 125 toAmp 250 CL-8 65 to90 to 100 25 to CL-950 to 145 CL-100000 to 0200 0000 to0200 CL-11028 10 to Job Sheet 60 for 60 Hz and 50 for 50 Hz 002 Power Module Dependent Selected motor 100% amps004 To H.022 Job Sheet 60 for 60 Hz and 50 for 50 Hz 000 100 to Selected line voltageCL-13 CCN Local Reset CL-14Page Incurring obligations
Related manuals
Manual 40 pages 46.08 Kb

19XR, XRV specifications

The Carrier 19XR and 19XRV chillers are sophisticated cooling solutions that represent the forefront of HVAC technology. Designed for large commercial and industrial applications, these chillers provide exceptional performance, energy efficiency, and reliability, making them ideal for a variety of environments ranging from hospitals to manufacturing facilities.

One of the most significant features of the Carrier 19XR and 19XRV chillers is their advanced scroll compressor technology. These units employ a tandem scroll design that enhances efficiency while minimizing operational noise. This makes them ideal for urban environments where noise restrictions may be in place. Moreover, the compressors are equipped with variable speed drive options in the 19XRV model, which allows for greater energy savings by adjusting cooling output based on real-time demand.

In addition to their advanced compressors, the 19XR and 19XRV units incorporate the Carrier GreenChoice refrigerant, which has a lower global warming potential compared to traditional refrigerants. This innovative choice not only meets regulatory requirements but also contributes to sustainability goals, making these chillers a responsible choice for environmentally conscious organizations.

The units are engineered with a robust heat exchanger design, which enhances heat transfer efficiency and overall system performance. This ensures optimal operation even in extreme conditions. They feature a microprocessor-based control system that allows for precise monitoring and control of the chiller’s performance, enabling operators to make real-time adjustments to maximize energy efficiency.

The Carrier 19XR and 19XRV chillers also prioritize serviceability. The design incorporates easy access to key components, simplifying maintenance procedures and reducing downtime. This focus on maintainability extends the lifespan of the equipment, leading to lower lifecycle costs.

In terms of connectivity, these chillers are equipped with advanced Building Management System (BMS) integration capabilities. This allows for seamless monitoring and control of the chillers using a centralized platform, facilitating energy management and operational optimization.

Overall, the Carrier 19XR and 19XRV chillers stand out in the market for their blend of cutting-edge technology, energy efficiency, and user-friendly features. They are engineered to meet the demanding needs of modern commercial and industrial applications, making them a preferred choice for facility managers seeking reliable cooling solutions.