PHASE RESEARCH
USER GUIDE
7.Press 
to change the time in
NOTE: The ending time of each shift coincides with the starting time of the next shift for the same day, though you may use different shifts for each day of the week. Shift 1 always starts at the opening time for the day, and the last programmed shift always ends at the closing time for the day.
8.Press 
to add a new shift by moving the cursor immediately to the right of the first unused shift number (for which START and STOP times have not yet been entered).
9.Press
or
to add the shift. The START and STOP times are now entered.
10.Press 


to delete shifts by moving the cursor to the [=] field of the first shift – in order from top (1) to bottom (4) – you wish to remove.
11.Press
to delete the shift. Any shifts that follow will automatically be removed as well. And the store’s closing time will automatically be entered in place of the STOP time for the last remaining shift.
NOTE: If all days use the same shifts, you can set the shifts for only one day and then use the COPY TO feature to copy the same settings to all other days, as explained in the following steps.
12.Press 
to move the cursor immediately to the right of DAY:.
13.Press
or
to select the desired day from which to copy.
14.Press
to move cursor to COPY.
15.Press
to move the cursor to <ENTER>.
16.Press
to copy the displayed shift settings to all other days, replacing any individual shifts previously set for these days.
SECTION 13 - PARAMETERS PROGRAMMING |