3.4 Preparing for Installation
Switches can be mounted in a standard
The site needs the following:
•Centrally located to the devices you want to link
•Near a power outlet.
•Constant temperature within 32° to 104°F (0° to 40°C) and its humidity within 10% to 90%,
•Adequate space (approximately 2 in or 5 cm) on all sides for proper air flow
•Accessible for installing, cabling and maintaining the devices
•Clearly visible status LEDs
Additional precautions:
•Keep the front of the chassis free from obstruction and away from the exhaust air of other equipment. Electrical equipment generates heat and the ambient room temperature be enough to cool the equipment to required operating temperatures.
•Make sure
•Make sure that the unit is connected to a separate grounded power outlet that provides 100 to 240 VAC, 50 to 60 Hz, is within 8 ft (2.44 m) of each device and is powered from an independent circuit breaker. As with any equipment, using a filter or surge suppressor is recommended.
3.5 Unpacking and Inspecting
Before you unpack your equipment examine all shipping containers for damage. If any damage has occurred, notify the shipping carrier immediately. Unpack the unit by removing the packing material and lifting it from the protective enclosures. Visually examine the equipment and check the container for parts and accessories. You should have the following items:
•An IntraCore IC3624PWR PoE switch
•Four adhesive foot pads
•A Rack Mounting Kit
•Two brackets
•Four screws for attaching the brackets
•An AC Power Cord
•An
Contact your dealer immediately if any item is missing.
IntraCore IC3624PWR Layer 2 PoE Switch with Dual Gigabit