Figure 27. Turbine Cleaning System14.2.1On-Crank Cleaning System

The on-crank cleaning system only operates at gas turbine cranking speed with the fuel system and ignition system deactivated. The gas turbine cranking and cleaning solution activation can be initiated from the control console or turbine control junction box.

14.2.2On-Line Cleaning System

The on-line cleaning system only operates when the gas turbine speed is between 90 and 100% gas producer speed and with or without load. Cleaning solution activation can be initiated from the control console or turbine control junction box. This system is intended to supplement the on-crank system by increasing the time intervals between periodic on-crank cleaning.

14.2.3Turbine Cleaning Cart

A portable offskid cleaning tank (Figure 28) can be provided to supply cleaning fluid to the skid edge cleaning system connection. The cleaning tank can be used to mix, hold, and pressurize the turbine cleaning solution. The tank comes with wheels that are removable for stationary installation.

Figure 28. Turbine Cleaning Cart

© 2008 Solar Turbines Incorporated. All rights reserved.

TPS250GS/908 - Preliminary

58