Turbomachinery Package Specification

Titan 250 Generator Set

 

 

17.4.2Alignment Tooling

As an option, alignment tooling can be provided to align the reduction gearbox output shaft hub to the generator input shaft hub. The alignment tooling includes a dial indicator kit, gearbox-to-generator alignment tool, axial distance gauge, and custom storage container.

17.4.3Lube Oil Cooler(s)

The lube oil cooler(s) is/are not integral with the package and must be located and installed separately.

17.4.4Gas Turbine Air Inlet System

The gas turbine air inlet should be located so that entry of gas turbine exhaust, oil tank vent vapor, or other contaminants is minimized. The air inlet duct must be free of accumulated water prior to starting the gas turbine.

17.4.5Gas Turbine Exhaust System

The importance of having an exhaust system properly installed cannot be overemphasized. A poorly installed exhaust system can cause a loss of power and impose severe mechanical strains on the gas turbine. The exhaust duct system must be terminated in a manner that precludes recirculation of exhaust products through the gas turbine air inlet or oil cooler. Exhaust installation considerations include the relative height of the exhaust duct above the air inlet, building roof design, direction of prevailing winds, and the proximity of adjacent structures. When exhaust silencing is required, provisions must be made to adequately mount and support the equipment and limit the exhaust silencer pressure loss.

17.5Documentation

Four copies of the Operation and Maintenance Instruction (OMI) manuals and Quality Control (QC) data books are provided on CD-ROM. Additional copies and alternative formats can be ordered at additional cost. Project specific drawings are provided in electronic format and include:

Electrical schematic

Wiring diagram

Electrical interface/Interconnect diagram

Turbotronic software documentation

Cause and effect drawing

Mechanical interface drawing

Start, Fuel, Lube, Air/Drain, and Enclosure system schematics

Solar’s Product Information Letter 184 “Documentation for New Equipment” provides a complete list of all the documentation supplied on a typical project.

17.5.1Quality Control Data Book

The QC data book typically includes the following:

Inspection and test plan (ITP)

Describes the quality assurance requirements for each product on a project basis.

Lists the primary controlling and verifying documents, codes and standards used to define the quality requirements, and identifies inspection points.

Package certified test report

© 2008 Solar Turbines Incorporated. All rights reserved.

TPS250GS/908 - Preliminary

67