Cleveland Range KGL-80-T, KGL-40-SH Pressure Relief Valve Periodic Testing, Calibrating Procedure

Models: KGL-40, KGL-60, KGL-80, KGL-100, KGL-40-T, KGL-60-T, KGL-80-T, KGL-40-SH, KGL-60-SH, KGL-40-TSH KGL-100, KGL-40-T KGL-40-TSH, KGL-40, KGL-40-T, KGL-40SH KGL-80-T, KGL-40-SH

1 42
Download 42 pages 34.91 Kb
Page 32
Image 32
PRESSURE RELIEF VALVE PERIODIC TESTING

PRESSURE RELIEF VALVE PERIODIC TESTING

Pressure

Relief Valve

Valve

Ring

Access

Panel

Most insurance agencies require periodic testing of pressure relief valves used on pressure vessels. This procedure will allow you to safely and quickly test your kettle's pressure relief valve. We recommend this test be performed twice a year.

DANGER: PRESSURE RELIEF VALVE WILL EXHAUST HIGH TEMPERATURE STEAM. CONTACT WITH SKIN COULD RESULT IN SERIOUS BURNS. KEEP FACE,

HANDS AND BODY CLEAR OF DISCHARGE.

DANGER: WORKING ON MACHINES

WITH POWER COULD RESULT IN

SEVERE ELECTRICAL SHOCK.

NOTE: The following instruction is intended for use by qualified service personnel.

WARNING: Kettle surface will be hot and steam will be released during testing. Take necessary precautions including the use of gloves and eye protection to

NOTES:

If valve appears to be sticking replace pressure relief valve.

If foreign material is discharged then drain kettle and replace pressure relief valve.

See KETTLE JACKET FILLING AND DRAINING PROCEDURES on page #30 for full instructions on the correct method for draining and refilling kettle jacket.

WARNING: Improper refilling of kettle jacket will result in irreversible damage to unit.

5.Replace Access Panel.

6.Reconnect main power at fused disconnect switch..

CALIBRATING PROCEDURE

Solid State Temperature

 

Adjustment

Control Box

 

Pot

 

 

 

1.Insure the unit has a vacuum before you begin calibrating procedures. If unit requires venting refer to KETTLE VENTING INSTRUCTIONS on

page #27.

prevent personal injury.

5

6

7

 

2. Turn kettle ON and set

temperature control to 10.

5 6

7

4

8

3

 

 

9

2

 

1

10

 

1.

With the kettle empty, turn

 

unit ON and set temperature

 

control to 10. Allow the kettle

 

to heat until the unit cycles

 

off.

2.

Switch unit OFF and

 

disconnect main power at

4

 

3

 

2

 

1

10

 

OFF

 

83. Allow the unit to cycle twice.

4.Check temperature of the

9 inner kettle surface with a digital surface thermometer.

5.Temperature should be between 260°F and 265°F.

OFF

fused disconnect switch.

3. Remove Access Panel at

back of main kettle console.

6.Using a screw driver adjust temperature by turning the

potentiometer on the Solid State Temperature Control Box. Turn very little. Turn clockwise to INCREASES and counter-clockwise to DECREASE

4.Pull Pressure Relief Valve Ring open for a maximum of one second. Repeat test three to four times. Each time the mechanism should move freely and be accompanied by a rapid escape of steam.

temperature.

7.Allow the unit to cycle twice.

8.Check temperature of the inner kettle surface with a digital surface thermometer.

9.Repeat steps 4. through 8. until unit is calibrated.

29

Page 32
Image 32
Cleveland Range KGL-80-T, KGL-40-SH, KGL-100, KGL-40-T manual Pressure Relief Valve Periodic Testing, Calibrating Procedure