Network Management Card – User Manual 34003991EN/EB Page 69/118

5.1.3.2 Sequential startup

It is possible to delay outlet power-on to reduce inrush currents on startup or to sequence the startup of several
devices.
Controlled outlet startup after a given time is based on startup of the main outlet.
5.2 T he different server and UPS shutdown sequences 5.2.1 Extended power outage, shutdown initiated by the Shutdown Timer (Shutdown after)
During battery backup time, the Shutdown Timer of the Network Management Card is reached: After a user-defined
backup time period
(Shutdown parameters page), the shutdown of all servers is initiated, followed by the UPS
shutdown (depending on its configuration). The UPS restarts when utility power is restored (depending on its
configuration)
Shutdown duration: Maximum value of shutdown times of protection application subscribed to the card. This value is
updated each time a client subscribes/ unsubscribes.
Start shutdown main
output
Utility failure
Utility
Shutdown after
:
NSM 2 on output 1
NSM 1 on main
output
Shutdown duration
main output
Main output
Utility restore
Start shutdown
output 1
Output 1
Shutdown
duration output 1
Shutdown after 1
:
5.2.2 Extended power outage, shutdown initiated by the "Low battery power" message
When the "Low battery power" criterion is displayed, the UPS is shut off after taking into account the shutdown
duration of the servers.
"Low battery power": The message appears if either of the two following criteria is checked:
- Low Battery Level
- Low Battery Delay