Inspection and Startup Checklist

3.0INSPECTION AND STARTUP CHECKLIST

Unit Serial Number

Unit Model Number

Date

3.1 Inspection

! WARNING

All equipment inspection procedures are to be performed with power to the unit turned off and locked out.

___ 1. Confirm that the exterior of unit is undamaged (including cables and receptacles, if furnished).

___ 2. Confirm that service and ventilation clearances are adequate. (See Figures 1 through 3.)

___ 3. Remove accessible exterior and internal panels.

___ 4. Inspect all wire and conductor insulation for damage.

___ 5. Check all transformer terminal connections for tightness. Retorque if necessary.

___ 6. Check all breaker connections for tightness. Retorque if necessary.

___ 7. Check all terminal block connections for tightness. Retorque if necessary.

___ 8. Check transformer mounting bolts for tightness. Retorque if necessary.

___ 9. Remove any foreign objects from the components or the interior area of the unit. Make sure air passages on transformers are clear and free of debris.

___ 10. Check that the intake and exhaust air screens are clean and free of obstructions.

___ 11. Replace internal and exterior side panels, leaving access to circuit breakers for the following start-up procedure.