106 SPARC Enterprise T5440 Server Service Manual • June 2011
Power off the server, using one of the methods described in the section, “Powering
Off the System” on page67.
“Extend the Server to the Maintenance Position” on page70
“Perform Electrostatic Discharge – Antistatic Prevention Measures” on page73
“Remove the Top Cover” on page73
Do the following :
1. Identify the correct slot for installation.
2. Remove the air baffle.
Squeeze the air baffle latches toward each other and lift the air baffle straight up
and out of the chassis.
3. If you are installing the module into a previously empty slot, remove the plastic
connector cover on the motherboard.
4. Slide the module down into its slot.
5. Rotate the ejector levers down to secure the module into place.
Next Steps
“Install the Top Cover” on page154
“Slide the Server Into the Rack” on page 155
“Power On the Server” on page157