Returning the Server to Operation 157
▼Connect the Power Cords to the Server●Reconnect both power cords to the power supplies.
Note – As soon as the power cords are connected, standby power is applied.
Depending on the configuration of the firmware, the system might boot. See the
SPARC Enterprise T5440 Server Administration Guide for configuration and power-on
information.
▼Power On the Server●To power on the server, do one of the following:
■To initiate the power-on sequence from the service processor prompt, issue the
poweron command.
■You will see an -> Alert message on the system console. This message
indicates that the system is reset. You will also see a message indicating that the
VCORE has been margined up to the value specified in the default.scr file
that was previously configured.
■Example:
■To initiate the power-on sequence manually, use a pen or pencil to press the
Power button on the front panel. See “Front Panel Diagram” on page3 for
Power button location.
Note – If you are powering on the server following an emergency shutdown
triggered by the top cover interlock switch, you must use the poweron command.
-> start /SYS