Airport Systems

2.5Final Installation Check

Before applying power to the equipment, perform the procedures in Sections 2.5.1 -

2.5.4.If any test does not pass, please consult SECTION 4. TROUBLESHOOTING in this manual or call Honeywell Technical Support at (805) 581-5591.

2.5.1Preliminary

1.Verify that all AC input power circuit breakers are turned off.

2.Check that all printed circuit boards are properly seated in their sockets, and retaining brackets are securely fastened..

3.Check that any user-installed wiring does not interfere with relay operation when covers are closed.

4.Check that all Flashheads are mounted are mounted at the correct elevation per Section 2.3.2.1, Page 2-7. Check that all Flashhead covers are shut properly for a weather-tight seal with all latches closed.

5.Set Master Controller switches as follows:

POWER SWITCH -----------------------------------------------------------------

OFF

LOCAL / REMOTE Switch ---------------------------------------------------

LOCAL

MODE Switch -----------------------------------------------------------------------

DAY

2.5.2Verify Correct Wiring in Master Controller

Verify correct wiring of the Master Controller as specified in section 2.4 page 2-11.

2.5.3Verifying Photocell Wiring

Verify correct wiring of the photocell as specified in section 2.4.3 page 2-12.

2.5.4Verify Proper Tower Wiring for Data/Control Cable

This test assumes a typical tower configuration with the data cable terminating at the Master Controller.

1.Unplug Data Cable connector TB5 from PCB1 in Master Controller.

2.Verify 120-140 ohms resistance between TB5-A and TB5-B on the Data Cable. (This checks that a single 100-ohm data line termination resistor is in the circuit. Resistance of 70 ohms or less indicates that more than one Flashhead has the terminating resistor switch set to on. See SW4 page 2-5.

3.Verify open circuit by measuring resistance between TB5-S on the Data Cable and panel ground.

4.Verify open circuit between TB5-A on the Data Cable and panel ground.

5.Verify open circuit between TB5-B on the Data Cable and panel ground.

SG-60 High Intensity Strobe System

2-27

Manual EPM-00000019 Rev A

Page 42
Image 42
Honeywell SG-60 installation and operation guide Final Installation Check