Airport Systems

10.Attach wires with the push on connectors to the following terminals.

(a)White wire to the outer bottom right terminal

(b)Black wire to the terminal that matches the Controller input voltage. (240v shown in Figure 5-1.)

11.You will need to replace the terminal lugs on the other 2 white wires before attaching to the transformer.

(a)Cut off wire terminal lugs as close to lug as possible

(b)Strip insulation back and crimp on new push on connectors.

12.Attach White wires with new connectors to the upper back terminals shown in diagram.

13.Re-install switch panel assembly to standoffs.

14.Visually inspect for loose connectors or any short-circuited lines.

15.Apply power to the Controller from the Circuit breaker.

16.Set Controller power switch to on and verify normal operation.

5.2SGF-60 Flashhead

Normal maintenance of the Flashhead requires periodic cleaning of the window with a non-abrasive soap.

WARNING!

Ensure that the power is off and the energy storage capacitors have been discharged before opening the Flashhead. Do not put hands or tools in the Flashhead until the High Voltage Indicator neon lamp DS1 on the High Voltage & Trigger board is extinguished. Refer to Figure 1-2, Page 1-3, for the location of High Voltage Indicator DS1 - do not confuse the High Voltage Indicator DS1, with the PWR ON lamp DS1.

Note that it is possible for the High Voltage Indicator DS1 to be lit even when the PWR ON lamp DS1 if off. If this happens, the energy storage capacitors C1 - C3 must be discharged before performing maintenance.

5.2.1Flashtube Replacement

Flashtubes that are faulty or degraded in performance by aging shall be replaced per the following procedure:

1.Shut off the power to the system by opening the main AC power circuit breakers.

2.Release the Flashhead cover latches.

3.Swing the cover open, exercising caution not to damage the glass face or the gasket.

4.Release the old flashtube by disconnecting the electrode wire fastons at each end and carefully snapping the flashtube from its holders.

SG-60 High Intensity Strobe System

5-2

Manual EPM-00000019 Rev A

Page 72
Image 72
Honeywell SG-60 installation and operation guide White wire to the outer bottom right terminal, SGF-60 Flashhead