Important: Events are only removed or marked “cleared” when their automatic delay time is completed. See the topics, Configuring the Clearing of Events” on page 167 and Configuring the Deletion of Events” on page 167.

Assume you set the clearing and deletion frequency to every 15 minutes with the initial time at 11:00 a.m. So every 15 minutes the management server checks for events marked for deletion and for clearing, and it updated the user interface accordingly. Let's assume Informational events are set to be cleared every hour, and an Informational event occurs at 12:20 p.m. Exactly after an hour has passed, the management server marks this event as “cleared” but the user interface is not updated because the frequency update of the user interface is every 15 minutes. If you looked at the Event Manager at 1:35 p.m. the event would be marked cleared. See Modifying the Clearing and Deletion Frequency” on page 166 for more information.

The Clearing of Events - You can determine how often events are marked “cleared.” See Configuring the Clearing of Events” on page 167.

The Deletion of Events - You can determine how often events are deleted. Events are deleted every two weeks by default. See Configuring the Deletion of Events” on page 167.

Modifying the Clearing and Deletion Frequency

You can modify how often the user interface in Event Manager removes events and marks events as “cleared.” Events are still displayed as they occur in the user interface.

IMPORTANT: Events are only removed or marked “cleared” when their automatic delay time is completed. See the topics, Configuring the Clearing of Events” on page 167 and Configuring the Deletion of Events” on page 167.

Assume you set the clearing and deletion frequency to every 15 minutes with the initial time at 11:00 a.m. So every 15 minutes the management server checks for events marked for deletion and for clearing, and it updated the user interface accordingly. Let's assume Informational events are set to be cleared every hour, and an Informational event occurs at 12:20 p.m. Exactly after an hour has passed, the management server marks this event as “cleared” but the user interface is not updated because the frequency update of the user interface is every 15 minutes. If you looked at the Event Manager at 1:35 p.m. the event would be marked cleared. See Modifying the Clearing and Deletion Frequency” on page 166 for more information.

To modify the clearing and deletion frequency:

1.Select Options > Events > Storage Essentials > Event Configuration.

2.Click the calendar icon, .

3.In the Time field, type the time in 24-hour format with the hour and minutes separate by a colon, for example, 22:15. Click the date on which you want to run the clearing and deletion frequency. Today’s date is highlighted in pink. Click Set.

The date and time appear in the Next Scheduled Run field in the yyyy-mm-dd hh:min format.

If you change the date in the field to a date that does not exist in a month, the software automatically calculates the date to the next month. For example, if you enter 2003-11-31, the software assumes the date is 2003-12-01.

166 Configuring the Management Server