13.Reattach the Molex plug to the gas valve.

14.Models 55 - 285 only, turn the gas valve power switch to the “ON” position.

15.Model 399 only, turn on power at the source.

16.After the installation is complete, fill out the gas conversion label (in the conversion kit bag) and affix it to the unit under the boiler rating plate inside the unit. Attach the LP caution label (in the conversion kit bag) to the left side of the unit in the lower left corner.

17.Replace the front access cover.

￿ WARNING

After converting to LP, check combustion

per the Start-up procedure in Section 10

of this manual. Failure to check and verify combustion could result in severe personal injury, death, or substantial property damage.

Figure 2-3Installing Propane Orifice

GAS VALVE

GROMMET

BRASS ORIFICE

SCREWS

VENTURI

Mounting the boiler

See page 9 of this manual for boiler mounting location instructions.

NOTICE

The Knight Wall Mount boiler is not

intended for floor installation.

 

Mounting to a wood studded wall:

1.The wall mount bracket is designed for a stud spacing of 16 inches from center. For other stud spacing a solid mounting surface must be provided by the installer.

￿WARNING Do not mount the boiler to a hollow wall. Be sure to mount the boiler to the studs

only.

2.Mount the wall bracket using the 2 1/4" lag bolts provided. Make sure the top edge of the bracket is away from the wall. Ensure the bracket is level when mounted. Extreme care is needed to ensure the bolts are secured in the center of the studs.

3.Hang the boiler on the bracket and secure the bottom of the boiler with two (2) additional lag bolts provided.

Installation & Operation Manual

￿WARNING The boiler is too heavy for a single person to lift. A minimum of two people is needed for

mounting the boiler onto the bracket.

Mounting to a concrete wall:

1.Mount the wall bracket using the two (2) wedge anchor bolts provided with the bracket. To mount the wedge anchor bolts, drill a 1/4" diameter hole 1 1/8" deep and insert anchor. Hang the bracket from the anchor and secure with the two nuts provided. Make sure the top edge of the bracket is away from the wall. Ensure bracket is level when mounted. Extreme care is needed to ensure the bolts are secured in the center of the studs.

Note: If wall thickness does not allow a 1 1/8" deep hole, field supplied hardware suitable for the application should be provided.

2.Hang the boiler on the bracket and secure the bottom of the boiler with two (2) remaining anchors, following the instructions above.

The boiler is too heavy for a single person to ￿ WARNING lift. A minimum of two people is needed for

mounting the boiler onto the bracket.

Mounting to a metal studded wall:

1.The wall mount bracket is designed for a stud spacing of 16 inches from center. For other stud spacing a solid mounting surface must be provided by the installer.

￿WARNING Do not mount the boiler to a hollow wall. Be sure to mount the boiler to the studs only.

2.Mount the wall bracket using two (2) field supplied toggle bolts capable of supporting 100 pounds each. Ensure the top edge of the bracket is away from the wall. Ensure the bracket is level when mounted. Extreme care is needed to ensure the bolts are secured in the center of the studs.

3.Hang the boiler on the bracket and secure the bottom of the boiler with two (2) field supplied toggle bolts.

￿WARNING The boiler is too heavy for a single person to lift. A minimum of two people is needed

for mounting the boiler onto the bracket.

Figure 2-4Mounting the Boiler

WALL:

WOOD OR METAL STUDS ON 16" CENTERS -OR-

MASONRY / POURED CONCRETE MOUNTING BRACKET (FACTORY SUPPLIED)

FASTENERS

APPROPRIATE

FOR WALL TYPE

QTY: 4