System Setup

2.0Scope

System Setup describes receiving and handling of the Galaxy PW™ 100 to 225kVA, a description of major compo- nents, the battery cabinet, and definition of the control panel indicators, which includes electrical, mechanical and environmental specifications.

MGE also recommends obtaining an MGE field service engineer for final installation and basic startup for single and parallel units.

CAUTION

Scheduling of the MGE Field Service Engineers typically should be done 7 to

 

10 days before they are required on-site. If the startup of the UPS is critical

 

to maintaining your schedule, please call the MGE toll free telephone number

 

at 1-800-438-7373 for assistance. The MGE Field Service Engineers will insure a

 

quick installation for the initial safe startup and configuration of your Galaxy PW™.

 

 

Final installation and start-up should be completed by a qualified MGE Field Service Engineer.

2.0.1First steps by an on-site qualified Technical Engineer

Step 1. Unpack and position the unit.

Step 2. Connect the main (utility) power.

Step 3. Connect the power circuits.

2.0.2Final steps by MGE Field Service Engineer

Step 4. Call MGE and wait for the MGE Field Service Engineer to complete the installation.

Step 5. The MGE Field Service Engineer finalizes installation and the startup process.

Optional:

Procedure for temporary power prior to the final startup.

2.0.3Required Equipment and Tools

The following equipment and tools are recommended for on-site installation:

Digital volt meter (DVM)

1/8 inch slotted screwdriver

Pallet jack/forklift

Conduit installation tools

Nut driver set

86-133060-00 A00

System Setup

2 — 1