Electrical work

AP55M2Series

Using 4poles ELCB(Earth Leakage Circuit Breaker)

1.Remove the cover of electric box on side panel of the outdoor unit.

2.Connect the electric input wires [L1(R), L2(S), L3(T), N] to each terminal [L1(R), L2(S), L3(T), N] of the electric box on the outdoor unit respectively. (Input wires are purchased by the user separately.)

3.Connect the electric wires to each terminal on the indoor and outdoor unit respectively.

 

Control box

 

 

Indoor unit

Outdoor Unit

 

Knife switch or

 

 

 

 

automatic circuit

 

 

breaker

Earth

Earth

ON

 

Earth

 

R S T N

 

 

Earth

 

Indoor and outdoor

Power cable

 

connection wire

(Purchase separately)

Using 3poles ELCB and 2poles ELCB

1.Remove the cover of electric box on side panel of the outdoor unit.

2.Disconnect the connector A(R-L connection) from the outdoor unit.

3.Connect the electric input wires [L1(R), L2(S), L3(T)] to each terminal [L1(R), L2(S), L3(T)] and input wires(N,L) to each terminal(N,L) of the electric box on the outdoor unit respectively. (Input wires are purchased by the user separately.)

4.Connect the electric wires to each terminal on the indoor and outdoor unit respectively.

 

Indoor unit

Outdoor Unit

 

Knife switch or

 

 

automatic circuit

 

 

breaker

Earth

Earth

Earth

 

 

 

 

NFB

 

 

Earth

 

Indoor and outdoor

 

 

connection wire

Power cable

 

 

(Purchase separately)

36

PAC MIRAGE HPCO-AR-PH_IBIM_05321A-01_EN.indd 36

2015-03-03 오후 4:39:43