Inverter/Charger Installation
AC Wiring for a Dual-Inverter System
1.Disconnect the AC wires (from the utility grid or generator and to the
2.Remove bypass interlock bracket.
3.Disconnect INV1 AC LOAD (INV1
4.Add three additional
5.Attach the four distribution bars (supplied in
6.Connect grid wiring and loads/subpanel wiring to the new distribution bars as shown in Figure
7.Connect INV1 LOAD (INV1
8.Connect neutral (INV2
9.Connect wiring at the inverter/chargers as shown in Figure
10.Remove the knockouts on upper wire cover for additional breakers to fit through.
11.
12.Install bypass interlock plate with provided screws and nylon shoulder washers (supplied in
Power Distribution bars in the XW Power Distribution Panel accept up to a #2/0 AWG cable (maximum).
See Figure
FROM MAIN AC
DISTRIBUTION PANEL
FROM GENERATOR
DISCONNECT
INV 1 IN | INV 2 IN |
(GRID) | (GRID) |
GRID | GRID |
BYPASS | BYPASS |
INV 1 OUT | INV 1 OUT |
(AC LOADS) | (AC LOADS) |
INV 1 IN | INV 2 IN |
(GEN) | (GEN) |
TO AC1 ON INV1 | TO AC1 ON INV2 | TO AC2 ON INV1 | TO AC2 ON INV2 |
TO INVERTER AC
DISTRIBUTION PANEL