Quadra-Fire SAPPH-D-CSB, 839-1460, SAPPH-D-CWL, 839-1390, 839-1440 owner manual Cathedral Ceiling

Page 18

2. Cathedral Ceiling

Step 1.

Follow installation Steps 1 and 2 under vertical installation section, page 15.

Step 2.

Using the plumb-bob, mark the center line of the venting system on the ceiling, and drill a small hole through the ceiling and roof at this point. From the roof, locate the drill hole and mark the outline of the cathedral ceiling support box.

Step 3.

Remove shingles or other roof covering as necessary to cut the rectangular hole for the support box. Cut the hole 1/8 in. (3mm) larger than the support box outline.

Step 4.

Lower the support box through the hole in the roof until the bottom of the support box protrudes at least 2 in. (51mm) below the ceiling (Figure 5.16). Align the support box both vertically and horizontally with a level. Temporarily tack the support box in place through the inside walls and into the roof sheathing.

LEVEL

CATHEDRAL CEILING

SUPPORT BOX

Figure 5.17

Step 6.

Complete the cathedral ceiling installation by following the same procedures outlined in steps 4 through 8 for vertical installations, page 16.

Step 7.

Place the support clamp (provided with the support box) inside the support box (at the bottom), and secure to the pipe section. The clamp allows the support box to support the weight of the pipe sections. Continue to add pipe sections until you are above the roofline.

Step 8.

CUT HOLE 1/8 in. (3mm) GREATER IN SIZE THAN PATTERN OF SUPPORT BOX AS IT IS PROJECTED ONTO ROOF LINE

Figure 5.16

Step 5.

2 in. (51mm)

MIN. BELOW FINISHED CEILING

Install the black trim collar around the outside of the cathedral ceiling support box (Figure 5.18). The two pieces of the trim collar slide over one another to allow for easy adjustment around the support box. Using the six screws provided, secure the four corners and the overlapping sections of the trim collar to the ceiling. You may want to predrill the holes for the overlapped sections for ease of installation.

TRIM COLLAR

Using tin snips, cut the support box from the top corners down to the roofline, and fold the resulting flaps over the roof sheathing (Figure 5.17). Before nailing it to the roof, run a bead of non-hardening mastic around the top edges of the support box to make a seal between it and the roof. Clean out any combustible material from inside the support box.

CATHEDRAL

CEILING

SUPPORT SCREWS

BOX

Figure 5.18

Page 18

Quadra-Fire · Sapphire · 250-7233F

January 28, 2008

Image 18
Contents Quartet Front What to do if you smell gasSolitaire Front Do not Discard this ManualQuadra-Fire · Sapphire · 250-7233F January 28 Table of Contents 1Listing and Code Approvals Requirements for the Commonwealth of Massachusetts BELOW. Keep Clear of ALL ObstructionsManufacturer Requirements Getting Started Tools and Supplies NeededAppliance Location and Clearances Selecting Appliance LocationClearances 4Termination Locations Vent Termination Minimum ClearancesAlcove Applications Use of Elbows Vent InformationVenting Components Measuring StandardsHow to Use the Vent Graph Venting Guidelines TOP Vent Graph Rear Venting with Vertical RiseHorizontal Termination Type B Rear Installations for Use with Rear Vent KitType a Up & Out Installations for Top Vent Configurations StepElbow in Corner Installation 203mm 178mm 152mm Vertical Termination Direct Vent PipeStep Twist-lock the vent cap and seal Cathedral Ceiling Class a Metal Chimney Existing Masonry Chimney Ft mCap Flex Liner Flex Coupler Sheet Metal Screws Gas Information Fuel ConversionsConverting to LP Gas Propane Natural GAS Gas Pressures PressureGas Connection Check for GAS LeaksStanding Pilot Ignition System Wiring Recommendation for WireConnecting to the Appliance Wire Size Max. LengthThermopile GAS Pilot Ignitor Thermocouple Top and Rear Vent Conversion Appliance SetupRemove Shipping Materials At the TOP of the appliance, with exceptions notedReplace Burner Orifice for Horizontal Vent Configurations Grille Cover Plate Installation Accessories059 53 DMS 096 41DMS For Both Quartet and Solitaire Fronts Front InstallationFronts are shipped attached to the face Quartet Door AlignmentHearth Legs Installation Positioning the LogsQty Description Mineral Wool Glass Door Assembly InstallationBlower Installation Blower from frontPage 26 Blower Wiring Diagram BlowerFor TOP or Rear Vent Installations Damper AdjustmentShutter Adjustment Make adjustmentOperating Instructions Before Lighting ApplianceControls For Your Safety Read Before Lighting Lighting ApplianceFrequently Asked Questions Initial Break-in ProcedureAfter Appliance is Lit Troubleshooting Symptom Possible Cause Corrective ActionBe Placed in this Opening Maintaining and Servicing Appliance After servicingMaintenance Tasks Inspect Necessary. USE Caution When CLEANING/HANDLING Ceramic BurnerService and Maintenance Log Date of Service Performed By Description of ServiceAppliance Dimension Diagram Reference MaterialsVent Components Diagram Vent Components List MiscellaneousRD. Service Parts List Item # DescriptionRD. Service Parts cont’d Service Parts cont’d Accessories Cast Parts Individual PiecesWarranty Policy This page Intentionally Left Blank January 28 Quadra-Fire · Sapphire · 250-7233E Sapphire Contact InformationDealer Telephone