INITIAL START-UP (NO LOAD)

Begin testing the system without any electrical loads connected, as follows:

1.Set the AUTO/OFF/MANUAL switch to OFF.

2.Set the generator’s main circuit breaker to its OFF (open) position.

3.Install the 15 Amp fuse in the control panel.

4.Set the AUTO/OFF/MANUAL switch to MANUAL.

NOTE: When the Home Standby Generator is started for the very first time, it will require that air in the gaseous fuel lines be purged.This may take a few minutes.

5.DO NOT crank engine for more than 15 seconds, then pause for 15 seconds to reduce heat in the starter.

6.Repeat process until engine starts.

7.Listen for unusual noises, vibration or other indications of abnormal operation. Check for oil leaks while the engine runs.

8.Let the engine warm up for about five minutes to allow internal temperatures to stabilize.Then, set the generators main circuit breaker to its ON (or closed) position.

9.Connect an accurate AC voltmeter and a frequency meter to check generator output at the load side of the circuit breaker.Voltage should be 239-250 Volts, frequency should be 62.0 - 62.5 Hz.

NOTE: If either parameter is outside these ranges, perform the Engine Adjustments described on page 14.

10.Check generator output between one of the generator connection lugs and the neutral lug, then between the other generator connection lug and the neutral lug. In both cases, voltage reading should be between 121-126 Volts.

11.Set the AUTO/OFF/MANUAL switch to OFF. Engine should stop.

IMPORTANT: DO NOT proceed until you are certain that generator AC voltage and frequency are correct and within the stated limits.To obtain the proper generator frequency, see Engine Adjustments on page 14.

Engine Adjustment

There are regional variances in the composition of natural gas. Each HSG unit is adjusted at the factory for NG operation. If the generator output voltage or frequency measured during Initial Start-Up (paragraph #9) is outside the listed ranges, the combustibility of the gas supplied at the installation site may be substantially different.

To adjust the engine for this difference, proceed as follows.

1.Remove the Air Intake and Control Panel access doors.

2.Remove the three M5 sheet metal screws that hold the control panel wiring cover to the air intake guard (Figure 13).

Figure 13 — Accessing Back of Control Panel

3.Connect an accurate frequency meter to the load side of the main circuit breaker (on the back of the control panel).

4.Ensure that the 15 Amp fuse is installed.

5.Set the generator’s main circuit breaker ON.

6.Set the AUTO/OFF/MANUAL switch to MANUAL. When the engine starts, allow it to warm up for two minutes.

14

Image 14
Contents Installation and Start-Up Manual Equipment Description Table of ContentsCustomer Responsibilities Installer Responsibilities Safety Rules Amp fuse Before working on the equipmentInstallation Procedures Port Fuel and Electrical Inlet DimensionsLifting the Generator Conduit AttachmentInsert Access DoorsBattery DoorGaseous Fuel System Installation Manual To Remove an Access DoorTo Install an Access Door From Fuel To Home Standby10ft 15ft 20ft 30ft 40ft 50ft 60ft 70ft 80ft 90ft 100ft Fuel ConsumptionFuel Pipe Sizing LoadRemote LED Output Volt DC, .5 Amp Output Internal power supplyKnow Your System Control Board Generator AC Connection System Fault Detection SystemTo install the remote LED panel Grounding the SystemSystem Control Panel Battery ConnectionBefore Initial START-UP Engine OilFuel System Selection To configure the fuel system for LP useDo not dispose of battery in a fire Fuel Supply SystemInitial START-UP no Load Engine AdjustmentInstall the 15 Amp fuse in the control panel Automatic Operation Sequence Engine Cool-down TimerAdjustment Nut Utility Voltage Dropout SensorTo perform the Set Exercise procedure Setting Exercise TimerInstallation Inspection Withdrawal Rate 32F 20F 10F 30F 40F Fuel Comparison ChartPhysical Properties Butane Propane Natural Gas Responsabilidades DEL Cliente Tabla DE ContenidoDescripción DEL Equipo Responsabilidades DEL InstaladorPrecaución Conserve Estas Instrucciones Instrucciones DE SeguridadAdvertencia Procedimientos DE Instalación PeligroConector de la tubería De combustible Dimensiones de la Entrada para Electricidad y CombustibleElevación del Generador 13.5Entrada de Combustible Puertas de AccesoPara Para Instalar una Puerta de Acceso Sistema DE Combustible Gaseoso AdvertenciaPara Retirar una Puerta de Acceso Figura 19 Manómetro Instalado Transitoriamente El Generador Doméstico viene preparado de fábrica paraModelo Gas Natural Vapor de PL Dimensiones de la Cañería de CombustibleConsumo de Combustible Gas Natural peso específico =Conozca LA Tarjeta DE Control DE SU Sistema Interconexiones del Circuito de Control Sistema de Conexión de c.a. del GeneradorConexión a Tierra del Sistema Sistema de Detección de FallasAceite de Motor Antes DEL Arranque Inicial DEL MotorPanel de Control del Sistema Conexión de la BateríaSistema de Suministro de Combustible Para configurar el sistema de combustible para uso de LPSelección DEL Sistema DE Combustible Instale el fusible de 15 Amperios en el panel de controlFije el interruptor AUTO/OFF/MANUAL en la posición Arranque Inicial SIN CargaInstale el fusible de 15 Amperios en el panel de control Cargue el generador al valor nominal de gas natural Ajuste del MotorDel Regulador Inspección Posterior a LA Instalación Configuración DEL Temporizador DE PrácticaSecuencia DE Operación Automática Tasa de consumo 32F 20F 10F 30F 40F Cuadro de Comparación de CombustiblesPropiedades físicas Butano Propano Gas natural Table DES Matières Responsabilités DE LinstallateurGuide dInstallation Description DE LéquipementVeuillez Conserver CES Instructions Règles DE Sécurité AvertissementProcédures Dinstallation Connecteur de tuyauterie De combustible 91 cm EmplacementSoulèvement de la Génératrice Pour Tuyau ici Tuyau fourni par linstallateurPortes dAccès Pour enlever une porte daccèsPour installer une porte daccès LE Système DE Combustible Gazeux AvertissementManomètre Temporaire Installé Le groupe électrogène a été réglé en usine pourModèle Gas Naturel Vapeur PL Consommation de CombustibleGrosseur du Tuyau de Combustible Gaz Naturel densité = 0,65Sortie de panneau DEL à distance Système de Branchement C.A. de la Génératrice Interconnexions du Circuit de CommandeTableau de Commande du Système Mise à la Masse du SystèmeBranchement de la Batterie Avant LE Démarrage Initial DU MoteurHuile à Moteur Système dAlimentation en Combustible Sélection DU Système DE CombustibleDémarrage Initial Sans Réglez linterrupteur AUTO/OFF/MANUAL sur AutoDu Régulateur Réglage du MoteurÉcrou de Réglage Chargez la génératrice au débit de gaz naturel nominalRéglage DE LA Minuterie DE Cycle Dexercice Vérification InstallationSéquence DE Fonctionnement Automatique Densité 31,26 Charte de Comparaison des CombustiblesPropriétés physiques Butane Propane Gaz naturel Poids† Indice d’octane Recherche