Installation
Diversion Control Mode Wiring
The procedure below is illustrated in Figure
When using the
NEGATIVE.
To connect the C-Series as a diversion load controller:
1.Connect your DC current source (PV, wind, hydro, etc.) directly to the RE disconnect.
2.Connect another cable from the other side of the RE disconnect to the battery positive terminal.
3.Run a negative wire from the DC current source (PV, wind, hydro, etc.) to the battery negative terminal.
4.Connect a cable from controller terminal marked BAT POS to the battery disconnect.
5.Connect a cable from the battery disconnect to the positive terminal of the battery.
6.Connect a cable from the negative battery terminal to one of the terminals marked COMMON NEGATIVES on the controller’s circuit board.
7.Connect a cable from the controller’s other terminal marked COMMON NEGATIVES to the negative terminal of your DC diversion load.
8.Connect a cable from the controller’s terminal marked PV+/LOAD+ to the positive terminal of your DC diversion load.
9.Tighten per torque requirements outlined on page 39. Allow a little slack on the cables within the controller and secure the wiring with strain reliefs.
Important: Do not use light bulbs for diversion loads. Use only resistive loads such as air- or
46 |