INSTALLATION
ÊUPS Initial Startup
To start up the UPS:
NOTE Verify that the total equipment ratings do not exceed the UPS capacity to prevent an overload alarm.
1.Verify that the internal batteries are connected. Rack models. See “Installing the UPS” on page 23. Tower models. See “Installing the UPS” on page 30.
2.If optional EBMs are installed, verify that the EBMs are connected to the UPS.
Rack models. See “Connecting the EBM(s)” on page 26. Tower models. See “Connecting the EBM(s)” on page 32.
3.Plug the equipment to be protected into the UPS, but do not turn on the protected equipment.
4.Make any necessary provisions for cord retention and strain relief.
5.Models without an attached power cord. Plug the detachable UPS power cord into the input connector on the UPS rear panel.
6.Plug the UPS power cord into a power outlet.
The UPS front panel display illuminates and shows a status of “UPS initializing...”
7.Verify that the UPS transfers to Standby mode (”UPS on standby”).
8.Press the button on the UPS front panel for at least one second. The UPS front panel display changes status to “UPS starting...”
9.Check the UPS front panel display for active alarms or notices. Resolve any active alarms before continuing. See “Troubleshooting” on page 101.
If the indicator is on, do not proceed until all alarms are clear. Check the UPS status from the front panel to view the active alarms. Correct the alarms and restart if necessary.
34 | Eaton® 9130 UPS |